This document is a detailed specification document for the Roosevelt Creek Channel 5 Improvements project, prepared by Pinellas County, Florida, involving roadway and channel construction. The project encompasses multiple technical specifications for clearing and grubbing, survey and layout, maintenance of traffic, erosion control, pipe lining, concrete structures, and environmental planting. Key activities include removing an existing salinity weir, constructing a new weir, lining existing pipe connections, installing manatee grates, addressing channel erosion, and implementing environmental plantings. The specifications provide comprehensive technical requirements for contractors, including detailed instructions on pipe cleaning, CCTV inspections, cured-in-place pipe (CIPP) lining, plant installation, and 90-day environmental maintenance.
The project is funded and will be executed with specific pay items for various activities, with measurement and payment structured on a per linear foot, square yard, or lump sum basis depending on the specific task. The specifications include precise requirements for water quality management, turbidity monitoring, archaeological discovery protocols, and environmental protection measures. Contractors will be responsible for public notifications, traffic control, water flow management, and ensuring 100% survival of planted vegetation during a 90-day maintenance period. The project appears to be supported by local funding and potentially includes ARPA (American Rescue Plan Act) funding, with a focus on improving hydrological connectivity, habitat value, and marine life passage in the Roosevelt Creek Channel.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1of 34
SPECIFICATIONS
ROAD AND STREET CONSTRUCTION
P.I.D. No. 002123A
ROOSEVELT CREEK CHANNEL 5 IMPROVEMENTS
In Pinellas County, Florida
TO ACCOMPANY PINELLAS COUNTY STANDARD TECHNICAL SPECIFICATIONS FOR
ROADWAY AND RELATED CONSTRUCTION (JULY 2019 EDITION), AND FLORIDA
DEPARTMENT OF TRANSPORTATION (FDOT) STANDARD SPECIFICATIONS FOR ROAD
AND BRIDGE CONSTRUCTION – DIVISIONS II AND III ONLY (JULY 2022):
Modified Pinellas County Standard Technical Specification (Replaces the July 2019 Clearing and Grubbing Specification)
CLEARING & GRUBBING 110
The work specified under this Section consists of the clearing and preparation of sites for proposed construction, in accordance with the requirements of Section 110 of the FDOT Specifications, as amended herein. The work specified under this Section must include the removal and off-site disposal of all trees indicated on the plans to be removed, the removal and off-site disposal of all brush, stumps, roots, rubbish and debris, and all obstructions resting on or protruding through the surface of the existing ground and the surface of excavated areas, the removal and off-site disposal of all existing facilities, drainage structures, culverts, pipes, and pavement indicated on the plans to be removed, and the removal and off-site disposal of all buildings, structures, appurtenances, and other facilities necessary to prepare the area for the proposed construction.
No stock piling of material on the roadway, within tree protection zones (TPZ), or on the sidewalk is allowed. All extra dirt and/or debris must be removed daily as part of the daily clean-up process.
The roadway and the sidewalks must be swept daily. All costs associated with daily clean-up process and sweeping must be included in the Lump Sum bid for Clearing and Grubbing. All buildings, structures, utilities, and other obstructions indicated on the plans to remain, must be carefully protected against displacement or damage. Materials and labor for this protection must be included in the Lump Sum cost of Clearing and Grubbing.
Except as otherwise provided for in these specifications, the work to be performed under this Section must also include the clearing and grubbing necessary for the excavation of detention ponds, borrow pits, and the like, and the clearing and grubbing necessary for the construction of designated haul routes, and including the removal and off-site disposal of all product and debris except that which is to be salvaged or which is required to complete the construction of the project.
Where possible, all trenching or excavation within tree protection zones (TPZ) shall be done by hand or an air spade. After excavation, all tree roots greater than one inch (1”) in diameter must be cleanly pruned or saw cut, not crushed or torn. Where it is not possible to hand trench, mechanical excavation may be approved by the Engineer. Trunk/root flare and soil/root protection measures in accordance with Pinellas County Standard Detail Index 1111 must be employed to prevent tree damage from mechanical excavation equipment. The Contractor must not cut tree roots greater than three inches (3”) in diameter within the critical root zone (CRZ) without prior approval of the Engineer, after the inspection of an International Society of Arborists (ISA) Certified Arborist, preferably ISA Tree Risk Assessment Qualified (TRAQ).
All root pruning must conform to ANSI A300 (Part 8) Standard Practices (Root Management).
After root pruning, cut roots should be covered and kept moist until final grade is established.
Cutting tree roots greater than 3” in diameter in the critical root zone (CRZ) or tree roots greater than six inches (6”) in diameter within the TPZ shall be reviewed by a County Arborist to determine if a tree designated to remain may need to be removed to prevent future liability.
The Contractor must make his own inspection to determine the character, density and extent of trees, vegetation, and other items subject to removal and disposal under these provisions. The attention of the Contractor is directed to the fact that the burning of debris resulting from clearing and grubbing operations will not be permitted within County-owned lands or rights-of-way. Nothing in these provisions must be construed to authorize the removal or disturbance of any tree or other form of vegetation, or any marine, land or air creatures’ natural habitat, which may be subject to the jurisdiction of regulatory agencies. This Section must also include the cost for trimming of trees and disposal of the trimmings, as shown on the plans and/or required for construction of project. All tree trimming must be performed by or under the supervision of an ISA Certified Arborist and conform to ANSI A300 (Part 1) Standard Practices (Pruning), cost of which is included in the Clearing and Grubbing pay item.
This Section must also include the temporary relocation of mailboxes during construction and permanent relocation after construction has been completed. The work must also include the relocation of the mailbox foundation. The Contractor must coordinate with the Post Office to confirm the mailbox locations. Mailboxes must be restored to equal or better condition that existed prior to the commencement of construction activities, location of which must meet roadway clear zone requirements found in the FDOT Florida Green Book. Work related to mailboxes must be included in the Lump Sum pay item for Clearing and Grubbing.
A. Ownership of Removals:
i. All removed materials not claimed by the County must become the property of the Contractor and must be disposed of by the Contractor in areas provided by the Contractor. This work must be included in the pay item Clearing and Grubbing.
ii. Transporting and placement of removed material must be paid for under and included in the pay item of Clearing and Grubbing.
B. Items in County Right-of-Way:
The Contractor must notify in writing all property owners to remove any items (landscaping, signs, irrigation systems, lighting, etc.) from the County Right-of-Way that owners wish to salvage a minimum of fourteen (14) calendar days in advance of construction activities. After the notification period, it is the Contractor’s responsibility to remove said items that conflict with construction activities prior to construction. For irrigation systems that the owners wish to salvage, the contractor must place a cap and a location stake on the pipe that feeds into the irrigation system conflicting with construction activities within County Right of Way. The price and payment for capping and removal of irrigation systems, and removal of other items must be included in the payment item of Clearing and Grubbing.
C. Tree Protection: Trees not within the Clearing and Grubbing area and those specified to remain within County property/right of way, must be protected during construction with Tree Protection Barricades, in accordance with Pinellas County Standard Detail Index 1111. All project-specific tree and root protection; mulching within all critical root zones; tree and root pruning; and all tree protection as shown on the plans. Contractor shall provide a certified arborist on site to supervise all tree and root pruning, as well as all tree protection installation work as shown on the plans.
D. Tree and Stump Removal: Unless otherwise indicated by the Engineer in the construction documents, all trees deemed in conflict with the construction activities must be marked by the Contractor for removal, and field validated by the Engineer and a County Arborist in advance of construction. The Contractor must not remove any trees without authorization from the Engineer, after inspection by an ISA Certified Arborist.
E. This work must be included and paid for under the pay item Clearing and Grubbing. Tree stumps, roots, debris, subterranean items, and other abandoned items:
i. Unless otherwise directed by the Engineer, must be removed from sidewalk, drainage, roadway, and driveway areas to a depth of1) six (6) inches below the bottom of the aforementioned item OR 2) four (4) feet below the proposed surface (the greater of the two) and backfilled with A-1 or A-3 soil material. The excavation and backfilling must be included in the Lump Sum cost of Clearing and Grubbing.
Basis of Payment The work and incidental costs specified as being covered under this Section must be paid for at the contract unit price per Lump Sum (LS), for Clearing and Grubbing. If the Schedule of Values includes a specific pay item from the list provided in FDOT Section 110-12.8 Payment Items, then the work must be paid for at the contract unit price.
Section 900-0100 of the Pinellas County Roadway Std. Tech. Specs. SIGN - PROJECT
IDENTIFICATION
PAY ITEM NO. 900-0100 SIGN, PROJECT IDENTIFICATION, Erect & Maintain
The work specified under this Section consists of the furnishing of all labor and equipment required for the erection and maintenance of one 4-foot x 8-foot x 1/8-inch aluminum Project Identification Sign and one 24-inch x 30-inch Penny for Pinellas sign, at locations to be designated by the Engineer, prior to construction.
The signs shall be provided and transported to the project site by the County, but shall be erected by the Contractor, and shall be maintained by the Contractor, to the satisfaction of the Engineer, for the duration of the construction period. At substantial completion of the construction period, the Contractor shall remove and dispose of the Project Identification Sign. The 24-inch x 30-inch Penny for Pinellas sign shall remain in a permanent location designated by the Engineer.
Basis of Payment The work specified under this Section shall be paid for Lump Sum (LS) as constructed and accepted.
SUPPLEMENTAL SPECIFICATIONS
ROADWAY / DRAINAGE
(The following supplemental specifications are in addition to the Pinellas County Standard Technical Specifications for Roadway and General Construction) http://www.pinellascounty.org/technical/pdf/roadway-tech-specs-July-2019.pdf
Section 005-0700 of the Pinellas County Roadway Std. Tech. Specs. Survey and Layout
The specification for Survey, Construction Layout shall be amended to include:
• The right of way shall be staked out with a stake or marker every 100 feet on both sides of the project boundaries.
• All property corners and section corners shall be protected through the contract period by the contractor. If a property corner is damaged, they will be restored by a Florida registered Professional Land Surveyor at no additional cost to the County.
PAY ITEM NO. 005-0700, Survey and Layout the work specified under this Section must be one Lump Sum (LS) quantity.
Section 005-0850 of the Pinellas County Roadway Std. Tech. Specs. Permitting As-Built Survey Requirements by Contractor The specification for Survey, Permitting As-Built Survey Requirements by Contractor shall be amended to include:
The items requiring as-built surveying include the specific as-built requirements for the United States Army Corps of Engineers (USACOE) permit and the Southwest Florida Water Management District (SWFWMD) permit, including but not limited to:
• Cross sections of Articulated Concrete Block (ACB) mat stabilized area located at the
Manatee Exclusion Fence and Trash Collector sufficient to demonstrate planned verses as-built conditions.
• Cross sections at the former weir location/Articulated Concrete Block (ACB) mat stabilized area sufficient to demonstrate planned verses as-built conditions.
• Flow line pipe inverts at the fourteen new endwalls.
• Verify all Manatee Exclusion Devices are installed.
• As-builts information shall be provided at substantial completion of the project.
Please reference Appendix 6 - SWFWMD Agreement, Exhibit “C” Project Plan (pdf p. 15):
Spatial Reference, CAD and GIS Deliverable Requirements
• All survey and mapping services and deliverables shall be certified as meeting or exceeding, in quality and precision, the standards applicable for this work, as set forth in Chapter 472, F.S.
• Horizontal datum will be referenced to the Florida State Plane Coordinate System, West Zone (0902), Units US Survey Feet, North American Datum of 1983 (NAD83/2011) Current Adjustment including the most recent NSRS adjustment.
• Vertical Datum will be referenced to the North American Vertical Datum of 1988 (NAVD 88), Units US Survey Feet, using the most recent geoid model to compute orthometric heights based on GPS derived ellipsoid heights.
• Metadata must be provided for GIS deliverables and must be delivered in an ESRI ArcCatalog compatible XML format. Each data layer in the deliverable requires its own metadata XML file.
• Metadata must be compliant with the Federal Geographic Data Committee’s (FGDC) Content Standard for Spatial Metadata and current District standards (Metadata Writing Guide for Contractors) which is located on the District’s ftp website at: http://ftp.swfwmd.state.fl.us/pub/gisdata/metadata.stnds/, file name ContractorsXML.zip, incorporated herein by reference. All feature classes must be checked for geometrical, topological, and attribute errors and corrected accordingly. All metadata must pass through the USGS metadata parser at http://geo-nsdi.er.usgs.gov/validation/ with no errors.
PAY ITEM NO. 005-0850, SURVEY, Permitting As-built Requirements the work specified under this Section must be one Lump Sum (LS) quantity.
Section 101-0100 of the Pinellas County Roadway Std. Tech Specs. – Mobilization
The specification for Mobilization shall be amended to include:
• The Mobilization necessary for the CIPP lining.
PAY ITEM NO. 101-0100, Mobilization – the work specified in this Section, including this Special Provision listed above shall be paid for at the contract unit price per Lump Sum (LS).
Section 102-1000 of the Pinellas County Roadway Std. Tech Specs. – Maintenance of Traffic
The specification for Maintenance of Traffic shall be amended to include:
• The Maintenance of Traffic necessary for the CIPP lining.
PAY ITEM NO. 102-1000, Maintenance of Traffic – the work specified in this Section, including this Special Provision listed above shall be paid for at the contract unit price per Lump Sum (LS).
http://ftp.swfwmd.state.fl.us/pub/gisdata/metadata.stnds/ http://geo-nsdi.er.usgs.gov/validation/
PAY ITEM NO. 104-1 of the Pinellas County Roadway Standard Technical Specs. – Prevention, Control, and Abatement of Erosion and Water Pollution
The specification for Prevention, Control, and Abatement of Erosion and Water Pollution shall be amended to include:
Turbidity monitoring, as described in dewatering testing requirements in Section 1-0100 of the Pinellas County Roadway Standard Technical Specs. – Specifications for Roadway and General Construction shall be required every 4 hours (testing conducted by the contractor) during active construction throughout the entire duration of the project at the locations specified in the attached SWFWMD permit. Equipment calibration is to be performed as outlined in the permit.
PAY ITEM NO. 104-1, Prevention, Control, and Abatement of Erosion and Water Pollution – the work specified in this Section, including this Special Provision listed above shall be paid for at the contract unit price per Lump Sum (LS).
PAY ITEM NO. 104-9 ROLLED EROSION CONTROL PRODUCTS (BIONET SC150BN)
Description: This work specified under this Section shall consist of Rolled erosion control products comprised of RollMax BioNet SC150BN or an approved equal shall be applied in locations as shown in the plans to prepare the areas for planting by others at the bank stabilization areas within the tidal range (0.00 feet NAVD to 1.24 feet NAVD), the littoral shelf planting area at the weir and at the existing and proposed (10) Bald Cypress trees.
Rolled erosion control products comprised of RollMax BioNet SC150BN or an approved equal shall be applied in locations as shown in the plans to prepare the areas for planting by others at the bank stabilization areas within the tidal range (0.00 feet NAVD to 1.24 feet NAVD), the littoral shelf planting area at the weir and at the existing and proposed (10) Bald Cypress trees.
The rolled erosion control product shall be an extended-term double net erosion control blanket machine-produced mat of 70% agricultural straw and 30% coconut fiber with a functional longevity of up to 18 months. (NOTE: functional longevity may vary depending upon climatic conditions, soil, geographical location, and elevation). The blanket shall be of consistent thickness with the straw and coconut evenly distributed over the entire area of the mat. The blanket shall be covered on the top and bottom sides with a 100% biodegradable woven natural organic fiber netting. The netting shall consist of machine directional strands formed from two intertwined yarns with cross directional strands interwoven through the twisted machine strands (commonly referred to as Leno weave) to form an approximate 0.50 x 1.0 in. (1.27 x 2.54 cm) mesh. The blanket shall be sewn together on 1.50-inch (3.81 cm) centers with degradable thread. The blanket shall be manufactured with a colored thread stitched along both outer edges (approximately 2-5 inches [5-12.5 cm] from the edge) as an overlap guide for adjacent mats. The SC150BN shall meet Type 3.B specification requirements established by the Erosion Control Technology Council (ECTC) and Federal Highway Administration’s (FHWA) FP-03 Section 713.17
Material Content
Matrix 70% Straw Fiber 0.35 lbs/sq yd (0.19 kg/sm) 30% Coconut Fiber 0.15 lbs/sq yd (0.08 kg/sm)
Netting Top: Leno woven 100% biodegradable jute
9.35 lb/1000 sq ft (4.5 kg/100 sm)
Bottom: 100% biodegradable organic jute
7.7 lb/1000 sq ft (3.76 kg/100 sm)
Thread Biodegradable Standard Roll Size
Standard Roll Sizes Width 6.67 ft (2.03 m) 8.0 ft (2.4 m) 15.5 ft (4.72 m) Length 108 ft (32.92 m) 112 ft (34.14 m) 90 ft (27.43 m) Weight ± 10% 52.22 lbs (23.69 kg) 65.28 lbs (29.61 kg) 101.2 lbs (45.9 kg) Area 80 sq yd (66.9 sm) 100 sq yd (83.61 sm) 155 sq yd (129.6 sm) Leno weave top only Leno top and bottom Leno top and bottom
Index Property Test Method Typical Thickness ASTM D6525 0.25 in. (6.35 mm) Resiliency ECTC Guidelines 86% Water Absorbency ASTM D1117 311% Mass/Unit Area ASTM D6475 8.32 oz/sy (282.9 g/sm) Swell ECTC Guidelines 46% Smolder Resistance ECTC Guidelines Yes Stiffness ASTM D1388 0.42 oz-in Light Penetration ASTM D6567 7.6% Tensile Strength - MD ASTM D6818 201.6 lbs/ft (2.99 kN/m) Elongation - MD ASTM D6818 13.4% Tensile Strength - TD ASTM D6818 164.4 lbs/ft (2.44 kN/m) Elongation - TD ASTM D6818 14.2% Biomass Improvement ASTM D7322 641%
Design Permissible Shear Stress Unvegetated Shear Stress 2.10 psf (100 Pa) Unvegetated Velocity 8.00 fps (2.44 m/s)
Slope Design Data: C Factors Slope Gradients (S) Slope Length (L) ≤ 3:1 3:1 3:1 – 2:1 ≥ 2:1 ≤ 20 ft (6 m) 0.001 0.029 0.063 20-50 ft 0.051 0.055 0.092 ≥ 50 ft (15.2 m) 0.10 0.080 0.120
Roughness Coefficients – Unveg.
Flow Depth Manning’s n ≤ 0.50 ft (0.15 m) 0.050
0.50 – 2.0 ft 0.050-0.018 ≥ 2.0 ft (0.60 m) 0.018
PAY ITEM NO. 104-9, Rolled Erosion Control Products (BioNet SC150BN) – the work specified in this Section, including this Special Provision listed above shall be paid for at the contract unit price per Square Yard (SY).
Section 110-0100 of the Pinellas County Roadway Std. Tech Specs. – Clearing & Grubbing
The specification for Clearing & Grubbing, shall be amended to include:
• Clearing and grubbing will consist of removal of ground cover in areas where erosion will be repaired as indicated on the plans, and removal of exotic/invasive vegetation, such as Brazilian Pepper, in the area surrounding the weir replacement as shown on the plans.
• No trees (other than those which are exotic/invasive, such as Brazilian Pepper, in the area surrounding the weir replacement, including the 30-foot swath to be cleared immediately downstream of the weir crest) are to be trimmed, damaged, or removed, and shall be protected for the entire duration of the construction activities.
• Around trees, only hand tools will be used to accomplish clearing and grubbing as well as any necessary re-grading prior to installing the RollMax BioNet SC150BN biodegradable erosion control matting (or equivalent) or sod installation, as indicated on the plans.
• Includes trash removal along the channel and within 30 feet downstream of the salinity weir location (tires, plastic, electronics, etc.)
• Clearing of brush around existing pipes with end treatments (headwalls, mitered end sections) to allow for installation of manatee exclusion devices.
• Includes removal of concrete weir (rubble) removal and the rip-rap adjacent to concrete weir. The 1978 as-built plans showing the concrete weir are included for informational purposes.
PAY ITEM NO. 110-0100 CLEARING & GRUBBING – the work specified in this Section shall
Section 120 of the Pinellas County Roadway Std. Tech Specs. – Excavation and Embankment
The specification for Fill Material shall be amended to include:
PAY ITEM NO 120-1140 FILL MATERIAL –
• Clean fill (A-1 or A-3 soil) required for repair of erosion along channel banks, to repair holes/ruts on the east berm behind 14228 Puffin Court, and any necessary for preparation of planting area around the weir.
• Compacting and grading activities involving fill material including the preparation for installation of the concrete stabilized sub-base and ACB mat.
PAY ITEM NO 120-1140 FILL MATERIAL – the work specified in this item shall be paid for at the contract unit price per Ton (TN). Duplicates of the sworn certificates of weight must be furnished with each truckload of material and presented to the job inspector for his signature.
Certificates of weight, which do not bear the signature of the job inspector, will not be considered for payment.
PAY ITEM 120-1141 FILL MATERIAL FOR WEIR –
• Clean fill (A-1 or A-3 soil) required for fill material replacement of unsuitable material at weir location.
PAY ITEM 120-1141 FILL MATERIAL FOR WEIR - the work specified in this item shall be paid for at the contract unit price per Ton (TN). Duplicates of the sworn certificates of weight must be furnished with each truckload of material and presented to the job inspector for his signature. Certificates of weight, which do not bear the signature of the job inspector, will not be considered for payment.
PAY ITEM NO. 120-1221 EXCAVATION, UNSUITABLE MATERIAL Under the Existing Weir, Including Disposal for ACB Mat
• Excavating and removing the unsuitable material (unsuitable soil) under the concrete weir including disposal at site provided by the contractor.
PAY ITEM NO. 120-1221 EXCAVATION, UNSUITABLE MATERIAL Under the Existing Weir, Including Disposal for ACB Mat - the work specified in this Section shall be paid for at the contract unit price per Cubic Yard (CY) removed
Section 120-1100 of the Pinellas County Roadway Std. Tech Specs. – Grading
The specification for Grading shall be amended to include:
• Bank Stabilization, more specifically:
- Repairing the areas of erosion on the slopes of the channel as indicated on the plans.
- Grading the repaired slopes as indicated in the plans, to be inspected for acceptance by the Engineer prior to stabilizing with RollMax BioNet SC150BN biodegradable erosion control matting or equivalent (does not contain monofilament or plastics) within the tidal range to be paid for by pay item 104-9 – Rolled Erosion Control Products (Bionet SC150BN) and staked sod (using biodegradable stakes), to be paid for by pay item 575-0106 – Sodding, Bahia, (Staked), above the tidal range (0.00 feet NAVD to 1.24 feet NAVD), as indicated on the plans. The stabilization via the erosion control matting or staked sod must be installed within 30 days of completion (and acceptance) of bank erosion repairs. The staked sod should slightly overlap the erosion control matting and biodegradable stakes placed into the overlapped area to secure both in place. The planting of the Spartina Alterniflora in the tidal range (0.00 feet NAVD to 1.24 feet NAVD) from Station 69+00 southward (west bank) and from Station 68+10.41 southward (east bank) are by others.
- Clean fill used to repair the areas of erosion will be supplied by the contractor and shall be paid for by pay item 120-1140 – Fill Material.
- Where areas of erosion to be repaired overlap with the existing and proposed (10) Bald Cypress trees and Muhlenberg capillaries planting areas as indicated on the plans, the repaired areas will be stabilized using the biodegradable erosion control matting described above, rather than with staked sod, in preparation for planting.
This item includes the planting of the (10) Bald Cypress. The planting of the Muhlenbergia capillaris are by others.
- If the grading is not acceptable, contractor shall repair the grading until the Engineer is satisfied before installing the erosion control matting or staked Bahia sod, as indicated on the plans.
- Grading shall include the cost of the removal and disposal of unsuitable materials, except for unsuitable materials covered under PAY ITEM NO. 120-1221 EXCAVATION, UNSUITABLE MATERIAL Under the Existing Weir, Including Disposal for ACB Mat
• Repair of Holes/Ruts on the east berm, beyond the Top of Bank, more specifically:
- Repair the holes/ruts on the east berm behind 14228 Puffin Court, as indicated on the plans.
- Clean fill used to repair the holes/ruts on east burn will be supplied by the contractor and shall be paid for by pay item 120-1140 – Fill Material.
- Grading the repaired area of the berm, to be inspected for acceptance by the Engineer prior to final dressing of Bahia sod, to be paid for by pay item 575-0103 – Sodding, Bahia.
- If the grading is not acceptable, contractor shall repair the grading until the Engineer is satisfied before installing the Bahia sod, as indicated on the plans.
Sod installation will occur within 30 days of repair (and acceptance of repair grading) of the holes/ruts.
- Repair of holes/ruts on the west berm as directed by the Engineer shall be filled with crushed concrete supply by the contractor and paid for under item 204-1001 Crushed Concrete Material, west berm.
• Preparation of Planting/Littoral Shelf Area around Weir, more specifically,
- The area surrounding the weir removal location will be graded as indicated on the plans in preparation for planting the area, to be completed by others.
- County staff shall verify the grading is acceptable and done according to the plans prior to stabilization with RollMax BioNet SC150BN or equivalent biodegradable erosion control matting (does not contain monofilament or plastics) to be paid for by pay item 104-9 – Rolled Erosion Control Products (Bionet SC150BN). The erosion control matting must be installed within 30 days of completion (and acceptance) of grading.
PAY ITEM NO. 120-1100 GRADING – the work specific in this Section shall be paid for at the contract unit price per Lump Sum (LS) inspected and accepted.
Section 204 of the Pinellas County Roadway Std. Tech Specs. – ROADWAY BASE, Crushed Concrete/Graded Aggregate
The specification for Roadway Base, Crushed Concrete/Graded Aggregate shall be amended to include:
PAY ITEM NO. 204-1001 CRUSHED CONCRETE MATERIAL, West Berm
• Crushed Concrete Material, West Berm shall include all labor and material associated with installing the crushed concrete material on the west berm as shown on the plans and as directed by the Engineer.
PAY ITEM NO. 204-1001 CRUSHED CONCRETE MATERIAL, West Berm – the work specified in this Section shall be paid for at the contract unit price per Cubic Yard (CY).
PAY ITEM NO. 204-1092 ROADWAY BASE, CRUSHED CONCRETE/GRADED
AGGREGATE, MIN. LBR 100, 12” Min. Thickness for under the weir and Manatee Exclusion Grate –
• Roadway Base, Crushed Concrete/Graded Aggregate, min. LBR 100, 12” min thickness for under the weir and Manatee Exclusion fence shall include all labor and materials associated with installing the stabilized sub-base for under the ACB mat, as indicated on the plans, titled approved subgrade (12” thickness).
PAY ITEM NO. 204-1092 ROADWAY BASE, CRUSHED CONCRETE/GRADED AGGREGATE,
MIN. LBR 100, 12” Min. Thickness for under the weir and Manatee Exclusion Grate – the work specified in this Section shall be paid for at the contract unit price per Square Yard (SY).
Section 400 of the Pinellas County Roadway Std. Tech Specs. – Concrete Structures
The specification for Concrete Structures shall be amended to include:
PAY ITEM NO. 400-2-8 CONCRETE CLASS II (REINFORCED)-TO ANCHOR ACB MAT
EDGES -
• This pay item shall include all labor and materials required to install the concrete Class II (Reinforced) with the steel required to Anchor ACB MAT Edges as shown on the plans.
PAY ITEM NO. 400-2-8 CONCRETE CLASS II (REINFORCED)-TO ANCHOR ACB MAT EDGES
- the work specified in this Section shall be paid for at the contract unit price per Cubic Yard (CY) installed and accepted.
PAY ITEM NO. 400-2-15 CONCRETE CLASS II (REINFORCED) FOR MANATEE GRATE
• This pay item shall include all labor and materials required to install the concrete Class II
(Reinforced) for the Manatee Grate slab and footing as shown in the Manatee Grate Detail Construction Plans.
PAY ITEM NO. 400-2-15 CONCRETE CLASS II (REINFORCED) FOR MANATEE GRATE
- The cost in this section shall include the concrete slab, footing, earthwork (excavation, grading, fill, removal, compaction..), and control joints. The work specified in this Section shall be paid for at the contract unit price per Cubic Yard (CY) installed and accepted.
Section 524 of the Pinellas County Roadway Std. Tech. Specs DITCH PAVEMENT.
The specification for DITCH PAVEMENT shall be amended to include:
PAY ITEM 524-3550 ARTICULATED CONCRETE BLOCK REVETMENT 6"/Fabric
• The work shall consist of all labor and material required to install the Weir Structure/ Articulated Concrete Block Revetment 6"/Fabric listed in the plans and specifications.
PAY ITEM 524-3550 ARTICULATED CONCRETE BLOCK REVETMENT 6"/Fabric the work specified under this Section must be paid for per Square Yard (SY) installed and accepted.
Section 530-2000 of the Pinellas County Roadway Std. Tech. Specs. RIPRAP The specification for RIPRAP shall be amended to include:
PAY ITEM NO. 530-2200 RIPRAP, Rubble w/ Filter Fabric
• The work shall consist of all labor and material required to install the RipRap Rubble with Filter Fabric listed in the plans and specifications.
PAY ITEM NO. 530-2200 RIPRAP, Rubble w/ Filter Fabric the work specified under this Section must be paid for per Ton (TN) installed and accepted.
Section 900-1060 of the Pinellas County Roadway Std. Tech Specs. – Cofferdams The specification for Cofferdams shall be amended to include:
PAY ITEM NO. 900-1062 STEEL COFFERDAM 250’x6’x2’ FOR ACB MAT PLACEMENT, DEWATERING FOR ACB MAT INSTALLATION, INCLUDING PUMPING AND WATER
TREATMENT -
• This pay item shall include all the labor and materials associated with installing and operating the steel cofferdam necessary for dewatering the areas for the ACB mat installation, including pumping and water treatment.
PAY ITEM NO. 900-1062 STEEL COFFERDAM 250’x6’x2’ FOR ACB MAT PLACEMENT, DEWATERING FOR ACB MAT INSTALLATION, INCLUDING PUMPING AND WATER
TREATMENT - the work specified in this Section shall be paid for at the contract unit price per Lump Sum (LS).
PAY ITEM NO. 900-1063 STEEL COFFERDAM FOR MANATEE GRATE AT STA 11+80 -
• This pay item shall include all the labor and materials associated with installing and operating the steel cofferdam necessary for dewatering the area needed for the manatee grate (STA 11+80) installation, including pumping and water treatment.
PAY ITEM NO. 900-1063 STEEL COFFERDAM FOR MANATEE GRATE AT STA 11+80 - the work specified in this Section shall be paid for at the contract unit price per Lump Sum (LS).
PAY ITEM NO. 900-1064 COFFERDAM FOR HEADWALLS AND PIPE LINING –
• This pay item shall include all the labor and materials required to the cofferdams at the 14 locations listed on the plans
PAY ITEM NO. 900-1064 COFFERDAM FOR HEADWALLS AND PIPE LINING – the work specified in this Section shall be paid for at the contract unit price per Lump Sum (LS).
SPECIAL PROVISIONS
(Amends the Pinellas County Standard Technical Specifications for Roadway and General Construction)
ITEM NO. 120-0810 DEWATERING, with Treatment Description: The work specified under this Section shall consist of all work associated with dewatering of construction area, including pond sites and area of weir construction. Also, included is monitoring of effluent and all appropriate treatment of dewatering effluent to address turbidity and/or other contamination issues.
The CONTRACTOR shall include in his/her bid all applicable costs, including monitoring, resulting from treatment and disposal of contaminated groundwater with concentration levels that exceed the allowable limits of the FDEP generic permit, and shall not be entitled to any adjustment in the Contract Price as a result of any change in the permit fees or unanticipated treatment and disposal costs.
Prior to any work commencing, and for the duration of the work, the CONTRACTOR is responsible for meeting all the conditions of the applicable permits and submitting any required reports to the appropriate agencies. Contractor shall submit a dewatering plan (shop drawing) to the County for review and approval prior to mobilization to the site.
Permitting:
Contractor shall apply for and obtain any and all permits for dewatering activities and/or treatment approvals that the Water Management District requires including, but not limited to:
1. No-Notice Short-Term Dewatering Permit (40D-2.101(1), F.A.C.) If the CONTRACTOR’S proposed work is expected to exceed 90 days in duration, or does not meet any of the other requirements listed with the requirements of Rule 40D- 20.302(3), the CONTRACTOR must apply for and obtain a Dewatering General Water Use Permit (40D-2.101(1) F.A.C.)
The CONTRACTOR shall not be entitled to file, or recover under, any delay claim based on preparation of permit applications and the time required for obtaining the applicable permits. If, prior to or during the dewatering, it is determined that the disposal or discharge of the dewatering effluent is not authorized by the FDEP’s Generic Permit for the Discharge of Produced Ground Water from Any Non-Contaminated Site Activity, the CONTRACTOR shall diligently pursue further required permit(s) from FDEP or other agencies without resort to delay claims or recompense from the COUNTY for either permit application activities or the time required to obtain such permits.
The CONTRACTOR shall consider and anticipate the potential need to obtain the herein discussed permits in developing his schedule and shall make every effort to avoid or minimize potential impacts to his critical path that might result from delays in dewatering activities due to the time necessary for the CONTRACTOR to obtain the necessary permits. The CONTRACTOR shall make every effort to schedule activities requiring dewatering as late as possible during his schedule and shall schedule activities not impacted by dewatering as early as possible. For each day, up to a maximum of one hundred eighty (180) days that the CONTRACTOR diligently pursues such permit(s) and is unable to avoid adversely impacting his critical path, a day will be added to the time allotted to the CONTRACTOR to complete performance of the Project.
If exceedances are found in the dewatering effluent, the CONTRACTOR will be required to:
1. Immediately notify the COUNTY and report the exceedances that are encountered.
2. Meet with the FDEP to determine any and all alternatives that are acceptable.
3. Obtain prior COUNTY approval of treatment and disposal alternatives.
4. Obtain prior written COUNTY authorization to use pay item 120-0810
5. Apply and obtain any and all permits and/or treatment approvals that FDEP requires including, but not limited to:
a. Generic Permit for Discharges from Petroleum Contaminated Sites (62-
621.300(1), F.A.C.). Allows discharges from sites with automotive gasoline, aviation gasoline, jet fuel, or diesel fuel contamination.
b. Permit for all Other Contaminated Sites (62-04; 62-302; 62-620 & 62-660, F.A.C.).
The coverage is available only through the individual NPDES permit issued by FDEP. Allows discharges from sites with general contaminant issues, i.e. ground water and/or soil contamination other than petroleum fuel contamination.
c. Generic Permit for the Discharge of Produced Ground Water from Any Non- Contaminated Site Activity (62-621.300(2), F.A.C.).
d. Generic Permit for Stormwater Discharge from Large or Small Construction Activities (62-621.300(4) (a), F.A.C.).
Treatment:
The term treatment as used in this technical provision means the application of all FDEP approved techniques and/or methods available to remove the exceedances out of dewatering effluent except impounding. Impounding is not considered a treatment method for purposes of compensation under this technical provision.
The CONTRACTOR shall implement the appropriate treatment that is acceptable to FDEP, COUNTY, and, if necessary, the Water Management District to attain compliance for all exceedances encountered during dewatering activities. Treatments may include, but are not limited to: chemical treatment, ion exchange treatment, filtration, and disposal of discharged groundwater in a properly permitted facility.
The CONTRACTOR shall:
1. Make every effort to minimize the spread of contamination into uncontaminated areas.
2. Provide for the health and safety of all workers at the job site and make provisions necessary for the health and safety of the public that may be exposed to any potentially hazardous conditions.
3. Ensure such provisions adhere to all applicable laws, rules or regulations covering hazardous conditions in a manner commensurate with the level of severity of the conditions.
4. If necessary, provide contamination assessment and remediation personnel to handle site assessment, determine the course of action necessary for site security, and perform the necessary steps under applicable laws, rules, and regulations for additional assessment and/or remediation work to resolve the contamination issue.
5. Delineate the contamination area(s), any staging or holding area required, and develop a work plan that will provide the schedule of projected completion dates for the final resolution of the contamination issue.
6. Maintain jurisdiction over activities inside any delineated contamination areas and any associated staging or holding areas.
7. Be responsible for the health and safety of workers within the delineated areas; and
8. Provide continuous access to representatives of regulatory or enforcement agencies having jurisdiction.
Measurement and Payment: The work specified in this section shall be paid for at one Lump Sum (LS) quantity provided and accepted.
Pay Item Number
Item Description Unit Measurement for Payment
120-0811 Dewatering/Pumping (water Treatment prior to Discharge) for the Weir
LS
120-0812 Dewatering/Pumping (water Treatment prior to Discharge) for the Manatee Grate
LS
PAY ITEM NO. 550-005 MANATEE GRATE
Description: The work specified under this item shall consist of all work associated with constructing the manatee grate, as specified in the Manatee Grate Detail Plans.
Measurement and Payment: The cost shall cover furnish and install of the grate system, including all galvanized steel post. The work specified under this item shall be paid for at the contract unit price per Lump Sum (LS).
PAY ITEM NO. 820-0020 UNANTICIPATED ARCHAEOLOGICAL AND HUMAN REMAINS
DISCOVERIES
Description: Per Department of the Army permit, specific condition No.9, if during the ground disturbing activities and construction work within the project site, there are archaeological/cultural materials encountered (which shall include, but not be limited to: pottery, modified shell, flora, fauna, human remains, ceramics, stone tools or metal implements, dugout canoes, evidence of structures or any other physical remains that could be associated with Native American cultures or early colonial or American settlement), the Contractor shall immediately stop all work and ground disturbing activities within a 100-meter diameter of the discovery and notify Engineer. After notification of the Engineer, the Contractor will relocate construction activities to a different location outside of the cultural resources/historic properties area. This item will only be used if archaeological/cultural materials are discovered.
Measurement and Payment: The work specified under this section shall be paid for at the contract unit price per Each (EA) occurrence. Payment must include all labor, materials, and equipment to stop work and relocate to a location outside of the cultural resources/historic property area.
PAY ITEM NO. 820-0021 PVC VINYL SNOW FENCE 4ft. Height, (Orange) F&I with Posts for protection of the unanticipated archaeological and human remains discoveries
Description: This item will include all labor and material necessary to construct a PVC Vinyl Snow Fence (orange) which will be placed as directed by the Engineer after the discovery of archaeological/cultural materials at the site with 2”x2” stakes with a 12” embedment spaced 6’- 10’ apart. The fence shall be https://www.homedepot.com/p/YARDGARD-4-ft-x-50-ft-Orange- Plastic-Snow-Fence-889220A/202024119 or equal with 48” long 2”x2” stakes. This item will only be used if archaeological/cultural materials are discovered.
Measurement and Payment: The work specified under this section shall be paid for at the contract unit price per Linear Foot (FT) as constructed and accepted.
PAY ITEM 900-0010 ACTIVE EAGLE NEST REQUIREMENTS
Description: The work consists of all labor and material required to adhere to an active nesting https://www.homedepot.com/p/YARDGARD-4-ft-x-50-ft-Orange-Plastic-Snow-Fence-889220A/202024119 https://www.homedepot.com/p/YARDGARD-4-ft-x-50-ft-Orange-Plastic-Snow-Fence-889220A/202024119 event.
• Avoid construction activities within 330 feet of the nest during the nesting season (1 October – 15 May, or when eagles are nesting prior to 1 October – or after 15 May).
• Avoid excessive and/or sudden loud noise, including tailgate banging, within 330 feet of the eagle’s nest tree when eagles are present.
• If eagle nests are observed and any construction activities are proposed to occur between 330 and 660 feet of the nest during nesting season (1 October – 15 May, or when eagles are nesting prior to 1 October – or after 15 May). The guidelines can be found at:
https://www.fws.gov/sites/default/files/documents/bald-eagle-monitoring-guidelines- 2007.pdf
Measurement and Payment: The work specified under this section shall be paid for at the contract unit price per Lump Sum (LS)
PAY ITEM NO. 900-2000 Maintenance of Channel Flow for Weir Structure & PAY ITEM NO. 900-2001 Maintenance of Channel Flow for Manatee Grate at STA 11+80
Description: The work consists of all labor and material required to maintain channel flow including coffer dams, pumping, temporary piping, and provisions for overflow conditions including cleanup after overflows occurs. This section shall also include all labor and materials required to keep the work area dry, including dewatering by well points, associated dewatering permits as required, and pumping out the work area with required sediment control of the discharged water as required by permit.
Measurement and Payment: The work specified under this Section shall be paid for at the contract unit price per Lump Sum (LS) constructed, operated and accepted. Payment will include labor and materials required to operate and maintain the system for the entire duration of the construction of the channel and related items as detailed on the plans and listed in the specifications.
PAY ITEM NO. 900-3001 MANATEE SIGN
Description: The work specified under this item shall consist of all work associated with providing and installing the signs required in the Army Core of Engineers Permit (located in Appendix 1 of the contract)
Measurement and Payment: The work specified under this item shall be paid for at the contract unit price per Lump Sum (LS).
PAY ITEM NO. 900-4000 COORDINATION WITH PLANT CONTRACTOR
Description: The work specified under this item shall consist of all coordination associated with the Plant Contractor selected by the Engineer for plants outside the scope of this contract. The selected Plant Contractor will begin operations with in 30 days of substantial completion. The contractor shall begin coordination with the Engineer 90 days prior to substantial completion.
https://www.fws.gov/sites/default/files/documents/bald-eagle-monitoring-guidelines-2007.pdf https://www.fws.gov/sites/default/files/documents/bald-eagle-monitoring-guidelines-2007.pdf
Measurement and Payment: The work specified under this item shall be paid for at the contract
CURED IN PLACE PIPELING SPECIFICATION
(The Specifications presented herein are project specific and are only related to this project and are not part of County’s Standard Technical Specifications).
PL0-100-000, CURED IN PLACE PIPELINING
PART I – GENERAL
SCOPE OF WORK
• The work includes furnishing all labor, supervision, manpower, tools, equipment, materials, insurance, bonds, management, transportation, and performance of all operations in connection with the rehabilitation of 15" through 64”x43” arch" gravity storm sewer lines using Cured-In-Place Pipe (CIPP) liner.
• The CIPP shall be continuous and jointless from structure to structure and shall be free of all defects that will affect the long-term life and operation of the pipe.
• All lining material shall be suitable for use in domestic sewers.
• It shall be assumed that pipelines to be rehabilitated will need cleaning. Pipelines may require removal of protruding services and by-pass pumping to successfully install the liner system. If the Contractor feels point repairs are necessary to complete lining of a particular main line segment, the County may either instruct the Contractor to make the individual necessary repairs, make the repair using County staff, or cancel that section of work at no cost to the County. The Contractor shall be responsible for all material removed from the pipeline and shall properly dispose of materials in accordance with the appropriate regulatory agency requirements and shall supply documentation of conformance to these requirements.
• Any main line or service line damage occurring during the rehabilitation process shall be the responsibility of the Contractor including, but not limited to, point repairs, main line replacement, service line replacement, any and all required permits, traffic control, and bypass pumping, including a back-up system and restoration of all disturbed areas. The Contractor shall be responsible for any wastewater or cure water spills during any operations and pay any and all fines, fees, property damage, environmental damage and cleanup costs that are associated with wastewater spill.
• All work shall be done in compliance with NPDES.
• Proper Erosion and Sediment control best management practices will be utilized on all projects. See Pinellas County Utility Technical Specifications, Stormwater Pollution Prevention Plan, and Erosion and Sediment Details.
QUALITY CONTROL
Products and Installers seeking approval must meet all the following criteria to be deemed acceptable:
• The cured-in-place pipe must have a minimum design life of 50 years. The minimum design life may be documented by submitting life estimates by national or internally recognized authorities or specifying agencies, to the County Representative. Otherwise, long-term testing and long-term in-service results may be used and results extrapolated to 50 years.
• Acceptable products shall provide documented acceptable wastewater and stormwater installations in the United States for the sizes indicated in the bid sheets.
• Liner materials shall be as specified in the Material Specification Manual.
SUBMITTALS
The Contractor shall submit the following information:
• Manufacturer’s certification that the materials to be used meet the referenced standards and these specifications.
• License or certificate verifying Manufacture’s/ Licensor’s approval of the installer.
• Provide Third Party Test Results supporting the long-term performance and structural strength of the product including any other supporting data.
• Lining Manufacturer’s product data and instructions for resin and catalyst system.
• Proposed equipment and procedures for accomplishing the work including all preparation work, cleaning operation, pre-closed-circuit television (CCTV) inspections, bypass pumping, traffic control, installation procedure, method of curing, service reconnection, quality control, testing to be performed, final CCTV inspection, and all else necessary and appropriate for a complete CIPP liner installation.
• Tube wet-out and cure method including: a complete description of the proposed wet-out procedure, manufacturer’s recommended cure method for each diameter and thickness of CIPP liner to be installed, and detailed curing procedure detailing the curing medium and the method of application.
• A detailed installation schedule.
• Design Calculations, in accordance with the Appendix of ASTM F- 1216, for each length of liner to be installed including the thickness of each proposed CIPP. The design will be chosen relative to buckling, stress and deflection failure from external loads and ring tension and deflection failure from internal loads. The equation for buckling design will be based upon the Equation Number 33 as described in AWWA C-950. All equations will be modified to include ovality as a design parameter. Design Calculations are to be completed and provided for the design of all pipe liner systems. All calculations shall include data that conforms to the requirements of these specifications.
• The finished rehabilitated pipe will have at least 100% of the flow capacity of the original pipe before rehabilitation.