Summary of Special Terms and Conditions for HVAC Units Procurement
This document contains the Special Terms and Conditions governing goods and nonprofessional services for New Kent County, Virginia's procurement of ClimateMaster HVAC units on behalf of the Department of Military Affairs, Department of Public Works at Fort Pickett. The solicitation is a brand-locked procurement requiring seven line items across five distinct ClimateMaster HVAC unit models in quantities ranging from one to two units per model, along with shipping and freight services to Building 224 at Fort Pickett in Blackstone, Virginia. Bids are due September 4, 2026 at 3:00 p.m. and must be submitted electronically through eVA on a per-item basis with a cumulative grand total. Delivery is required within sixty calendar days after receipt of order, with delivery notification to Allison Maddox required forty-eight hours prior to delivery. Award will be made on a grand total basis to the lowest responsive and responsible bidder.
Pricing shall be submitted as firm unit prices for each item during the contract period, with price escalation permitted only after an initial 120-day freeze and thereafter in 120-day intervals, subject to verification and sixty days' advance notice, while price decreases must be communicated immediately. The contract includes a commercial warranty clause requiring the most favorable warranties provided to any customer, a maintenance manual requirement including operations guides and wiring diagrams, and strict product availability prohibiting substitutions without written approval from the Contract Officer. The Commonwealth reserves the right to cancel the contract without penalty upon sixty days' written notice and may renew the contract for one year upon written agreement approximately ninety days prior to expiration. Contractors must participate in the eVA eProcurement Program and provide an electronic catalog or Punch-Out Catalog for awarded items. Invoices must be submitted within 365 days of delivery and include fifteen mandatory details per Virginia Department of Management and Analysis requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW ClimateMaster HVAC Units.pdf | ||
| General Terms & Conditions PIM45.pdf | ||
| DMA Mandatory Invoice Requirements.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
B-1 B-1
SPECIAL TERMS AND CONDITIONS
GOODS AND NONPROFESSIONAL SERVICES
1. AUDIT: The contractor shall retain all books, records, and other documents relative to this contract for five (5) years after final payment, or until audited by the Commonwealth of Virginia, whichever is sooner. The agency, its authorized agents, and/or state auditors shall have full access to and the right to examine any of said materials during said period.
2. AWARD OF CONTRACT: All solicitations must contain one of the following award clauses to specify the method of award.
A. AWARD: The Commonwealth will make the award(s) on a grand total basis to the lowest responsive and responsible bidder. The purchasing office reserves the right to conduct any test it may deem advisable and to make all evaluations. The Commonwealth also reserves the right to reject any or all bids, in whole or in part, to waive informalities and to delete items prior to making the award, whenever it is deemed in the sole opinion of the procuring public body to be in its best interest.
3. CANCELLATION OF CONTRACT: The purchasing agency reserves the right to cancel and terminate any resulting contract, in part or in whole, without penalty, upon 60 days written notice to the contractor. Any contract cancellation notice shall not relieve the contractor of the obligation to deliver and/or perform on all outstanding orders issued prior to the effective date of cancellation.
4. eVA ORDERS AND CONTRACTS: The solicitation/contract will result in one (1) purchase order with the applicable eVA transaction fee assessed for each order.
Vendors desiring to provide goods and/or services to the Commonwealth shall participate in the eVA eProcurement Program and agree to comply with the following: If this solicitation is for a term contract, failure to provide an electronic catalog (price list) or Punch-Out Catalog for items awarded will be just cause for the Commonwealth to reject your bid/offer or terminate this contract for default. The format of this electronic catalog shall conform to the eVA Catalog and/or Punch-Out Catalog Specification. For further information and details please email eVA-catalog- manager@dgs.virginia.gov.
5. RENEWAL OF CONTRACT: This contract may be renewed by the Commonwealth upon written agreement of both parties for one year under the terms of the current contract, and at a reasonable time (approximately 90 days) prior to the expiration.
6. BID ACCEPTANCE PERIOD: Any bid in response to this solicitation shall be valid for thirty (30) days. At the end of the days the bid may be withdrawn at the written request of the bidder. If the bid is not withdrawn at that time it remains in effect until an award is made or the solicitation is canceled.
7. BID PRICES: Bid shall be in the form of a firm unit price for each item during the contract period.
8. DELIVERY: Delivery of goods or performance of services shall be within the number of calendar days stated below after receipt of order (ARO) by the bidder/offeror. The Agency requires the (bidder/offeror) to deliver within a reasonable time after ARO. If the bidder/offeror does not insert a stated delivery time in the blank below, the (bidder/offeror) will be deemed to offer delivery in accordance with the Agency’s desired delivery time as stated below:
Agency’s desired delivered time: 6 0 calendar days ARO
BIDDER’S/OFFEROR’S STATED DELIVERY TIME: CALENDAR DAYS ARO
9. DELIVERY NOTIFICATION: The Agency shall be notified forty-eight (48) hours prior to delivery of any items so that personnel may be available to allow access to the building and verify items received. Notification shall be mailto:manager@dgs.virginia.gov
B-2 B-2 made to :
Allison Maddox (434) 292-2660 .
10. MAINTENANCE MANUALS: The contractor shall provide with each piece of equipment an operations and maintenance manual with wiring diagrams, parts list, and a copy of all warranties.
11. PRICE ESCALATION/DE-ESCALATION: Price adjustments may be permitted for changes in the contractor’s cost of materials not to exceed the increase in the following index: Consumer Price Index. No price increases will be authorized for 120 calendar days after the effective date of the contract. Price escalation may be permitted only at the end of this period and each 120 days thereafter and only where verified to the satisfaction of the purchasing office. However, “across the board” price decreases are subject to implementation at any time and shall be immediately conveyed to the Commonwealth.
Contractor shall give not less than 60 days advance notice of any price increase to the purchasing office.
Any approved price changes will be effective only at the beginning of the calendar month following the end of the full 60 day notification period. The contractor shall document the amount and proposed effective date of any general change in the price of materials. Documentation shall be supplied with the contractor’s request for increase which will: (1) verify that the requested price increase is general in scope and not applicable just to the Commonwealth of Virginia; and (2) verify the amount or percentage of increase which is being passed on to the contractor by the contractor’s suppliers.
The purchasing office will notify the using agencies and contractor in writing of the effective date of any increase which it approves. However, the contractor shall fill all purchase orders received prior to the effective date of the price adjustment at the old contract prices. The contractor is further advised that decreases which affect the cost of materials are required to be communicated immediately to the purchasing office.
12. WARRANTY (COMMERCIAL): The contractor agrees that the goods or services furnished under any award resulting from this solicitation shall be covered by the most favorable commercial warranties the contractor gives any customer for such goods or services and that the rights and remedies provided therein are in addition to and do not limit those available to the Commonwealth by any other clause of this solicitation and rights and remedies permitted under applicable law. A copy of this warranty should be furnished with the bid/proposal.
13. PRODUCT AVAILABILITY/SUBSTITUTION: Substitution of a product, brand or manufacturer after the award of contract is expressly prohibited unless approved in writing by the Contact Officer. The Agency may, at its discretion, require the contractor to provide a substitute item of equivalent or better quality subject to the approval of the Contract Officer, for a price no greater than the contract price, if the product for which the contract was awarded becomes unavailable to the contractor.
14. FEDERALLY IMPOSED TARIFFS: In the event that the President of the United States, the United States Congress, Customs and Border Protection, or any other federal entity authorized by law, imposes an import duty or tariff (a “tariff”), on an imported good that results in an increase in contractor’s costs to a level that renders performance under the Agreement impracticable, the Commonwealth may agree to an increase to the purchase price for the affected good. No increase in purchase price may exceed 25% of the additional tariff imposed on the goods imported or purchased by the contractor that are provided to the Commonwealth under this Agreement.
Prior to the Commonwealth agreeing to a price increase pursuant to this Section, the contractor must provide to the Commonwealth, the following documentation, all of which must be satisfactory to the Commonwealth:
- evidence demonstrating: (i) the unit price paid by contractor as of the date of award for the good or raw material used to furnish the goods to the Commonwealth under this Agreement, (ii) the applicability of the tariff to the specific good or raw material, and (iii) contractor’s payment of the increased import duty or tariff (either directly or through an increase to the cost paid for the good or raw material). The evidence submitted shall be sufficient in detail and content to allow the Commonwealth to verify that the tariff is the cause of the price change.
B-3 B-3
- a certification signed by contractor that it has made all reasonable efforts to obtain the good or the raw materials comprising the good procured by the Commonwealth at a lower cost from a different source located outside of the country against which the tariff has been imposed.
- a certification signed by contractor that the documentation, statements, and any other evidence it submits in support of its request for a price increase under this Section are true and correct, and that the contractor would otherwise be unable to perform under this Agreement without such price increase.
- as requested by the Commonwealth, written instructions authorizing the Commonwealth to request additional documentation from individuals or entities that provide the good or the raw materials to verify the information submitted by contractor. If the Commonwealth agrees to a price increase pursuant to this Section, the parties further agree to add the following terms to this Agreement:
- During the Term and for five (5) years after the termination of this Agreement, contractor shall retain, and the Commonwealth and its authorized representatives shall have the right to audit, examine, and make copies of, all of contractors books, accounts, and other records related to this Agreement and contractor’s costs for providing goods to the Commonwealth, including, but not limited to those kept by the contractor’s agents, assigns, successors, and subcontractors.
- Notwithstanding anything to the contrary in this Agreement, the Commonwealth shall have the right to terminate this Agreement for the Commonwealth’s convenience upon 15 days’ written notice to contractor.
In the event the import duty or tariff is repealed or reduced prior to termination of this Agreement, the increase in the Commonwealth’s contract price shall be reduced by the same amount and adjusted accordingly.
- Any material misrepresentation of fact by contractor relating in any way to the Commonwealth’s payment of additional sums due to tariffs shall be fraud against the taxpayer’s of the Commonwealth and subject contractor to treble damages pursuant to the Virginia Fraud Against Taxpayers Act.
BIDDER’S/OFFEROR’S STATED DELIVERY TIME: CALENDAR DAYS ARO