This is a Special Provisions document prepared by the Ada County Highway District (ACHD) for the Cloverdale Road, Franklin Road to Executive Drive Thermoplastic Replacement project in Idaho. The project involves removing and replacing existing pavement markings on concrete pavement with thermoplastic markings to improve visibility and durability while reducing future maintenance. The work is scheduled for nighttime construction between 9 PM and 6 AM unless otherwise approved by ACHD. Key deliverables required from the contractor include detailed construction staging plans, traffic control plans, a Pedestrian Temporary Traffic Control Plan, and a Stormwater Management Plan. The contractor must submit these plans for ACHD approval prior to commencing work, with seven calendar days allowed for initial review and seven calendar days for each resubmittal. The contract requires the contractor to maintain a minimum of one 10-foot travel lane in each direction through the construction zone and to maintain continuous, accessible routes for all pedestrians, bicyclists, and persons with disabilities in compliance with the Americans with Disabilities Act and the Manual on Uniform Traffic Control Devices.
The work includes specific bid items for obliterating existing pavement markings measured by linear foot or square foot, traffic control signs measured by square foot, inlet protection devices, and construction staging and traffic control plan development paid as lump sum items. All costs associated with furnishing working drawings, providing site disposal for excess materials, maintaining stormwater flows, implementing best management practices, repairing damage to areas beyond construction limits, and developing required plans are considered incidental to the project with no additional compensation provided. The contractor is responsible for coordinating with property owners regarding landscaping, irrigation, and access, and must provide appropriate documentation including weight tickets and area sketches to support pay quantity requests submitted by the 25th of each month. The contractor must also obtain current editions of the 2017 Idaho Standards for Public Works Construction to perform the work and comply with all applicable federal and state stormwater regulations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Title: Cloverdale Rd, Franklin to Executive – Thermoplastic Replacement
Project Number: Page 1 of 13
SPECIAL PROVISIONS
Cloverdale Rd, Franklin to Executive – Thermoplastic Replacement
PROJECT NO.
This stamp certifies the attached modifications to the ISPWC and ACHD supplemental provisions. It does not certify the
ISPWC or ACHD supplemental provisions.
Project Number: Page 2 of 13
GENERAL NOTES:
1. AMERICANS WITH DISABILITY ACCESS (ADA) DURING CONSTRUCTION
The needs and control of all road users (motorists, bicyclists, and pedestrians within the highway and/or public right-of-way, including persons with disabilities in accordance with the Americans with
Disabilities Act of 1990 (ADA), Title II, Paragraph 35.130) through a temporary traffic control “TTC” zone shall be an essential part of highway construction, utility work, maintenance operations, and the management of traffic incidents. The primary function of TTC is to provide for the reasonably safe and efficient movement of road users through or around TTC zones while reasonably protecting workers, responders to traffic incidents, and equipment.
Temporary facilities, including reasonably safe pedestrian routes around work sites, are also covered by the accessibility requirements of the Americans with Disabilities Act of 1990 (ADA) (Public Law
101-336, 104 Stat.327, July 26, 1990. 42 USC 12101-12213 (as amended)). Implementation of TTC plans and installation and maintenance of devices shall be the responsibility of the contractor performing the construction, alteration and/or maintenance of the highway or public right-of-way.
Temporary traffic control for pedestrians shall meet the accessibility requirements (Standards) set forth in Part 6 of the MUTCD. When an existing continuous sidewalk or street crossing route cannot be maintained for pedestrians because of construction, either temporary walkways with curb ramps are to be provided, or the construction shall be phased to maintain access to the affected addresses.
Contractors shall be allowed flexibility as long as the requirements are met.
The location of the construction project and whether or not accessible facilities are present shall also determine the extent of the needed temporary facilities. The contractor is only required to maintain practical continuity where accessible facilities already exist. On low speed rural roads that do not have sidewalks and are used by bicyclists, no additional measures are needed as the bicycles can share the available travel lanes with other traffic. On moderate to higher speed rural roads, if a bike lane exists then it should be properly detoured, complete with signage, to provide a safe route through or around the work area. If a road or bridge project affects vehicular traffic to a business, residence, school or any other type of pedestrian generating location with existing accessible facilities, then pedestrian and handicapped access must be maintained.
A continuous route for all pedestrians, including people with disabilities and bicyclists, shall be maintained at all times. When existing pedestrian facilities are disrupted, closed, or relocated in a
TTC zone, the temporary facilities shall be detectable and include accessibility features consistent with the features present in the existing pedestrian facility. The temporary route should enable pedestrians to bypass the construction site while minimizing the retracing of their steps or going significantly out of their way. Additional consideration must be given to people with disabilities since they may not have the physical or cognitive ability to improvise (e.g. balancing along the curb or a very narrow path) or use unofficial alternatives (e.g. using an adjacent grass surface). Temporary routes must meet the accessibility guidelines of the ADA for permanent facilities as well as the Public
Right-Of-Way Accessibility Guidelines (PROWAG) and shall be marked with the proper signage.
Should existing crosswalks at signalized intersections be closed or made inaccessible, temporary crosswalks should be painted in an accessible location. Temporary signals should include pedestrian phases.
Contractors shall not block temporary walkways with contractor parking, materials piles, signs, Project Number: Page 3 of 13 rubble or rubbish. Construction equipment and equipment operation must be separated from the temporary walkways. At work zones where higher volumes of pedestrian traffic or school children exist, pedestrian fences or other protective barriers may be needed to prevent access into the construction area.
Detour and diversion routes, when used for pedestrians and bicyclists, should be evaluated for the following items:
• Direct conflicts between pedestrians and vehicular traffic, work vehicles, and other work activities must be reduced with protective barriers or continuous high contrast fencing (min 36” high with a 6” high toe board). See MUTCD 6F.68 and 6D.02; PROWAG R303.
• Temporary pedestrian facilities should provide safe, accessible routes that replicate as nearly as practical the most desirable characteristics of the existing facility, and parallel the disrupted route whenever possible. A smooth, continuous hard surface should be provided throughout the entire length of the temporary pedestrian facility. There should be no curbs or abrupt changes in grade or terrain that could cause tripping or be a barrier to wheelchair use. The geometry and alignment of the facility should meet the applicable requirements of the
Americans with Disabilities Act Accessibility Guidelines (ADAAG) for Buildings and Facilities. See
MUTCD 6D.01 and 6D.02; PROWAG R303.3 and R302.6.
• Advance information placed at appropriate distances before the work zone allowing pedestrians to make timely decisions about routes through or around the work zone. See
MUTCD 6F.14; PROWAG 303.2.
• Transition information allowing pedestrians to find a safe path through and around work zones, which is critical when the pathway is restricted, diverted or detoured. See MUTCD 6F.14;
PROWAG R303.2.
• Work area information assisting in safe passage of pedestrians through the work zone. This information is needed on all pedestrian routes except detours. See MUTCD 6F.14
• Exit information directing pedestrians back to the original route. See MUTCD 6F.14
• Crosswalk placement at intersections may need additional signage, temporary striping, traffic signal modification, pedestrian signals with audible alarms if justified, proper push button height, and ramps. See MUTCD 6H.29, 6F.80, and 4E.06; PROWAG R303.5 and R304.
• Accommodations for other transit forms (busses, trains etc.) are made. See MUTCD 6D.02
• Requirements of the ADAAG, PROWAG, and MUTCD are adhered to.
• Access is maintained to the affected businesses and residences.
2. BASIS OF PAYMENT
Except as modified herein, the various roadway work called for on the Bid Schedule shall be performed, measured, and paid for as indicated on said Bid Schedules and as provided in the 2017
IDAHO STANDARDS FOR PUBLIC WORKS CONSTRUCTION (ISPWC) and the latest supplements. The
Project Number: Page 4 of 13
Contractor is required to have the current edition of the ISPWC standards to perform this work.
Unless otherwise specified herein, all plan quantities are based upon in-place, completed and accepted units.
3. CONFLICTING PAVEMENT MARKINGS
All conflicting pavement markings shall be completely obliterated using an ACHD approved method prior to applying permanent pavement markings. Payment shall be under the respective bid schedule item.
4. CONSTRUCTION STAGING
The Contractor shall furnish ACHD with a detailed construction staging plan based on their anticipated approach to construction activities. This plan and implementation will be the responsibility of the contractor. Final approval of the staging plans and revisions thereof must be granted by ACHD prior to implementation.
5. DAMAGED AREAS BEYOND SPECIFIED CONSTRUCTION LIMITS
Damage to any areas or items not specifically identified for removal, including the existing pavement, sod, sprinklers and landscaping in the contract documents shall be promptly repaired by the contractor. The cost to complete such repairs shall be considered incidental to the cost of the project and no additional compensation will be made.
6. EXCESS SITE MATERIAL
The Contractor shall be responsible for providing a site for the disposal of excess or unsuitable materials. If bituminous material is to be disposed of, the site shall meet the requirements of the
Idaho Department of Environmental Quality. All excess material sites shall be approved by ACHD.
No separate payment will be made for the acquisition or operation of the sites, or for loading, hauling or unloading the materials at the site.
7. INFORMATION GIVEN PRIOR TO AWARD
Oral explanations, instructions and interpretations given to bidders prior to award of contract will not be binding. It is the ACHD’s intent to provide all bidders equal opportunity to access and acquire all available pertinent information necessary to formulate a responsive bid. Any information, specifications, plans, data, or interpretations that ACHD discovers is lacking and may be important to all bidders will be furnished in the form of an addenda, the receipt of which shall be acknowledged by the bidder.
8. PROPERTY OWNER COORDINATION
Contractor shall coordinate items of work affecting adjacent property owners, including but not limited to landscape removal and replacement, sprinklers, irrigation facilities, fencing, sod care, and trees. Property access coordination shall be conducted according to General Condition 49 –
PROPERTY ACCESS POINTS.
9. PAY QUANTITIES
Project Number: Page 5 of 13
By the 25th of each month the Contractor shall supply quantities that are to be paid for that month.
Each bid item shall be accompanied with the appropriate backup documentation on how the pay quantity was calculated. This shall include such documentation as, but not limited to; stationing, location, tallied weight tickets, sketch of calculated areas, and/or any other appropriate documentation to verify the pay quantity request. ACHD will verify quantities prior to remitting payment. Items failing to have the appropriate backup supporting documentation will not be paid until the information is supplied. The cost associated with providing the above outlined documentation shall be considered incidental to the project and no additional compensation will be granted.
All Pay quantities shall also adhere to the criteria outlined in General Condition 41 – MANNER OF
PAYMENT.
10. SHOP DRAWING REVIEW
Plans show details of all structures, lines, grades, typical cross sections of the roadway, location and design of all structures and a summary of items appearing on the proposal. The Contractor shall keep one set of plans available on the work site at all times.
The Contractor will supplement the plans by such working drawings necessary to adequately control the work. Working drawings shall be submitted to the Engineer for review in advance of the start of the proposed work. The Contractor shall allow sufficient Engineer review time and corrections resubmitted by the Contractor without impacting the approved construction schedule. The drawings shall be on sheets measuring 22 in. x 34 in. Unless otherwise stated in the contract, the Engineer will require up to 15 business days from the date the submittals or re-submittals are received until they are returned to the Contractor. No extension to contract time will be given due to re-submittals or the failure of the Contractor to provide any information necessary in a timely fashion. If necessary, drawings will be signed and sealed by a Professional Engineer licensed to practice in the State of
Idaho.
This review time will increase if the drawings submitted do not meet the contract requirements or contain sufficient details.
For structures, six sets of working drawings shall be furnished and shall include stress sheets, shop drawings, erection plans, coffer dam plans, bending diagrams for reinforcing steel, or any other supplementary plans or similar data required of the Contractor. All structural drawings provided shall be sealed by a Professional Engineer licensed to practice in the State of Idaho.
Working drawings shall be approved before beginning the work covered by the submitted drawings.
Such approval is only for general conformance with the information given in the contract documents and does not relieve the Contractor of responsibility for correctness of the details and dimensions, nor does it waive any requirements of the specifications.
The contract price shall include the cost of furnishing all submitted shop and/or working drawings.
11. STORMWATER FLOWS
The Contractor is responsible for transmitting existing stormwater and irrigation flows during construction. All costs associated with transmitting existing flows, including flows from the
Project Number: Page 6 of 13 temporary water quality best management practices on the project, shall be considered incidental to other items of work and no additional compensation will be made.
12. STORM WATER MANAGEMENT
Contractor shall implement Best Management Practices (BMPs) controls to protect storm sewer systems and Waters of the United States located on or near project limits. Contractor shall follow the requirements of the Idaho Pollutant Discharge Elimination System (IPDES) Construction General
Permit (CGP) and/or ACHD’s Construction Site Discharge Control (CSDC) Program as required. The contractor is required to implement and maintain BMPs through life of contract. The removal of all temporary construction BMPs after completion of all required work to final stabilization is considered incidental to this project.
The ACHD CSDC Plan shall meet the CSDC Program requirements listed in Sections 8305 to 8306 of the ACHD Policy Manual https://www.achdidaho.org/Documents/ACHDpolicyManual/7000to9000/Section8300_Construction
SiteDischargeControlProgram.pdf.
The CSDC Plan shall include measures to protect the existing ACHD storm drain systems inside and outside the project boundaries from mud, dust, debris, and other pollutants generated or transported due to this project. All measures will also be implemented to protect any “Waters of the
United States” inside or outside of the project boundaries. “Pollutants” are defined in Section 8302 of the ACHD Policy Manual.
The IPDES CGP Stormwater Pollution Prevention Plan (SWPPP) shall meet the CGP requirements. The
CGP can be found on the Idaho Department of Environmental Quality (IDEQ) website at:
https://www2.deq.idaho.gov/admin/LEIA/api/document/download/16509.
BMPs for controlling pollutant transport from the construction site and activities can be found in a number of publications and locations including, but not limited to:
• Idaho Department of Environmental Quality, Idaho Catalog of Storm Water Best Management
Practices at: https://www.deq.idaho.gov/water-quality/wastewater/storm-water/ or Phone: (208) 373-0502
• United States Environmental Protection Agency – Region 10, Resources and Tools at:
https://www.epa.gov/npdes/construction-general-permit-resources-tools-and-templates or Phone: (800) 424-4372
• Idaho Transportation Department, Best Management Practices (BMP) Manual at:
https://itd.idaho.gov/env/?target=resources or Phone: (208) 334-8476
Payment for this item will be made under the appropriate bid item numbers.
13. SURVEY – SIGNS AND STRIPING
ACHD will NOT provide construction staking for new signing and striping locations that may be shown on construction plans. It shall be the Contractor’s responsibility to locate all new signage and striping
Project Number: Page 7 of 13 in conformance with the locations specified in the contract plans or as specified in the ACHD
Supplemental Traffic Provisions. The Contractor shall also notify Digline prior to any sign installations.
14. TRAFFIC CONTROL
Contractor shall furnish ACHD with a detailed traffic control plan based on their anticipated approach to construction activities. This plan and implementation will be the responsibility of the contractor.
Final approval of the traffic control plan and revisions thereof must be granted by ACHD prior to implementation. It will be the sole discretion of the ACHD Resident Engineer, or designated representative, to determine if the advanced construction signing plan contained in the contract documents shall be approved as a traffic control plan.
Standard Traffic Control Templates are available online:
https://www.achdidaho.org/projects/development-resources/popular-forms
Local and emergency vehicle access shall be maintained at all times, unless otherwise indicated in the contract documents. Short-term lane closures shall be only as approved by the Resident Engineer.
15. WARNING AND REGULATORY SIGNS
Existing warning and regulatory signing shall be retained and protected throughout the project limits unless otherwise noted. This may require multiple relocations, which will be incidental to other bid items. Existing warning and regulatory signs that are designated for removal and replacement and do not conflict with construction traffic control signs shall be maintained during construction and, if necessary, relocated to locations where the signs are visible to traffic and serve their original purpose.
16. WORKING HOURS
Work shall be conducted at night, between the hours of 9 PM and 6 AM, unless otherwise approved by ACHD.
ROADWAY SPECIAL PROVISIONS
1. 1006.4.1.C.1 – INLET PROTECTION
ON PAGE 3 OF SECTION 1006 OF THE ISPWC, PART 2.1, add the following:
B. Inlet protection shall be Stormguard Sediment Catch Basin Inserts installed according to manufacturer’s recommendations, or approved equal.
Payment will be made under:
1006.4.1.C.1 – Inlet Protection ...................................................... Per Each
2. 1103.4.1.B.1 – TRAFFIC CONTROL SIGNS
ON PAGE 7 OF SECTION 1103 OF THE ISPWC, PART 4.1.B, add the following:
Provide and install Class “A” construction signing to direct vehicular traffic in and around the project site, including informational signage, per the MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES, most current edition. Signs that will be in place longer than 3 days shall be permanent sign
Project Number: Page 8 of 13 installations. Contractor shall bag or cover signs when not in use. Contractor shall refer to the ATSSA pamphlet called Quality Standards for Work Zone Traffic Control Devices.
Payment will be made by the square foot of sign acceptably installed, initial installation only.
1103.4.1.B.1 – Traffic Control Signs ............................................... Per Square Foot
3. SSP 11400 – OBLITERATE PAVEMENT MARKINGS
Description: This item consists of furnishing all labor, materials and equipment necessary to obliterate the existing pavement markings (stop bars, cross walks, turn arrows, tum lane text, 8" turn lane separation lines, edge lines, or skip lines) as shown on the plans, in conflict with proposed construction traffic control phasing, or as directed by ACHD.
Painted markings and traffic stripes shall be removed by hydroblasting, sandblasting, or other methods approved by ACHD. If other methods besides hydroblasting are used, dust mitigation must be a part of the removal at no additional cost to the district. Any damage to the road surface as a result of the Contractor's operations shall be repaired by the Contractor, at the Contractor’s expense, as directed by ACHD. Painting over existing traffic stripes and pavement markings with paint, asphaltic products, etc., does not meet the requirements for obliteration.
Workmanship: Workmanship shall meet the requirements of ACHD DIVISION 1100 SUPPLEMENTAL
PROVISIONS, SUBSECTION 1134.02.
Measurement and Payment: Obliterate Pavement Markings will be measured by either square foot or linear foot of the pavement markings removed as identified on the bid schedule and shall include all labor, equipment and material necessary for the completion of the bid item. Markings with gaps include the gap in the lineal foot quantity.
ITEM 29, "VARIATIONS IN QUANTITIES", ON PAGE GC16 OF THE ACHD GENERAL CONDITIONS, SECOND PARAGRAPH, shall not apply to this bid item.
Payment for this item will be made under:
SSP 11400.A – 4" White - Lane Line, 7ft Length & 18 ft Gap ………….…………………………….. Per Lineal Foot
SSP 11400.B – 4" Yellow - No Passing - 2 Direction …………………..….……………………………… Per Lineal Foot
SSP 11400.C – 4" Yellow - 2 Way Left Turn, 7ft Length & 18 ft Gap ……………………………… Per Lineal Foot
SSP 11400.D – 8" White - Bike Lane At Intersection, 2 ft Length & 6 ft Gap …………………. Per Lineal Foot
SSP 11400.E – 4" White - Cat Track, 2 ft Length & 6 ft Gap ………………………………………….. Per Lineal Foot
SSP 11400.F – 8" White - Channelizing \ Bike Lane ………………………………………………………. Per Lineal Foot
SSP 11400.G – 4" Yellow - Left Edge \ Divided Hwy ……………………………………………………… Per Lineal Foot
SSP 11400.H – White Symbols (Crosswalks, Stop Bars, Railroad, Arrows, DNBI, Bikes) … Per Square Foot
4. SP 11554 – CONSTRUCTION STAGING AND TRAFFIC CONTROL PLAN
Description: The Contractor shall submit staging plans and construction traffic control plans to illustrate a logical construction sequence with work zones and proposed traffic routing. Construction staging and traffic control plans shall allow for the following:
-Maintain a minimum of one 10’ travel lane in each direction through the construction zone.
Project Number: Page 9 of 13
-Flaggers may be used to control vehicle and pedestrian traffic at the Franklin Rd. and Cloverdale Rd.
intersection.
The Contractor may propose an alternative traffic control option to facilitate their specific construction staging plans, with the intent to reduce overall impacts to traffic.
Materials: All materials (signs, barricades, temporary facilities and appurtenances) shall be in accordance with the Americans with Disabilities Act of 1990 (ADA), the Public Right-Of-Way
Accessibility Guidelines (PROWAG), and Manual on Uniform Traffic Control Devices (MUTCD). Refer to ACHD Traffic Control Plan TC-34 for an example, and TC-02 for sign and delineation spacing, taper and buffer lengths. Standard traffic control templates are available at http://www.achdidaho.org/Departments/Engineering/Traffic/trafficStandards.aspx Modifications require approval from ACHD Traffic Representatives.
Workmanship: The Contractor shall develop Construction Staging and Construction Traffic Control plans. All plans shall be submitted using the Contractor’s drawing title block. The Contractor shall submit a construction traffic control plan to accommodate the operation. Traffic control plans shall clearly indicate how traffic will be routed through the work zone including, but not limited to, lane restrictions, lane shifts, and placement of all traffic control devices and pavement markings. The plans shall specifically identify all work impacting utilities, drainage and irrigation facilities, nighttime work, lane closures, and detours. All traffic control plans shall be prepared in conformance with the
MUTCD. Allow 7 calendar days for the Engineer to review staging and traffic control plans. Allow 7
Calendar days for each resubmittal. The approved plans must be followed unless new plans are submitted and approved.
Upon approval the Contractor shall implement the prepared construction traffic control plan. The
Contractor shall be responsible for all work associated with the construction traffic control plan including all initial placement, maintenance, relocations, and removal of all signs, barriers, and temporary facilities.
Measurement and Payment: Traffic control devices used will be paid under their respective bid items when applicable. Relocation of each device to another location shall be paid under Traffic
Control Maintenance. This item includes all effort to develop, design, submit, modify, inspect, and manage the Construction Staging and Traffic Control Plan.
Development and implementation of a pedestrian routing plan is addressed in SP 11551 –
PEDESTRIAN TEMPORARY TRAFFIC CONTROL PLAN
SP 11554 - Construction Staging and Traffic Control Plans............... Lump Sum
5. SSP 06013 – STORMWATER MANAGEMENT PLAN PREPARATION AND APPROVAL
Description: This item shall consist of all work associated with contractor plan preparation and approvals to meet the requirements of the Idaho Pollutant Discharge Elimination System (IPDES)
Construction General Permit (CGP) and/or ACHD’s Construction Site Discharge Control (CSDC)
Project Number: Page 10 of 13
Program as required. The contractor is considered an operator having day-to-day control as defined in the CGP; therefore, the contractor is a co-permittee with ACHD in the implementation of the CGP requirements. A Stormwater Pollution Prevention Plan (SWPPP) will be accepted by ACHD in lieu of the CSDC Plan provided that the SWPPP meets the CSDC Program requirements listed in 8305 and
8306 of the ACHD Policy Manual. 8300 - Construction Discharge Control Program https://www.achdidaho.org/home/showpublisheddocument/2144/639092808008429757
Workmanship: The contractor is responsible for the completion, submittal, and implementation of the ACHD provided SWPPP drawing and narrative, filing of the Notice of Intent (NOI), and filing of the
Notice of Termination (NOT). Access for completing an electronic NOI and NOT can be found on the
Idaho Department of Environmental Quality (IDEQ) IPDES E-Permitting website:
https://www2.deq.idaho.gov/water/IPDES.
The CGP can be found on the Idaho Department of Environmental Quality (IDEQ) website at:
https://www2.deq.idaho.gov/admin/LEIA/api/document/download/16509. The SWPPP shall have been prepared and submitted to ACHD for acceptance prior to the filing of the NOI. Prior to filing the
NOT, the conditions listed in Part 8.2 (Conditions for Terminating CGP Coverage) of the CGP shall be met.
Once a SWPPP has been prepared, the Contractor and ACHD shall both submit an electronic NOI on the website listed above. There is a fourteen-calendar day wait after the acknowledgement of receipt has been posted on the IDEQ website for the SWPPP to be considered approved and construction allowed to commence.
Prior to starting construction, the ACHD accepted SWPPP/CSDC Plan must be implemented. No
Construction Activity or Land Disturbing Activity will be allowed to commence until the Contractor has fully implemented the accepted SWPPP/CSDC Plan as required by the District and set forth in the
ACHD Policy Manual.
Additionally, the contractor is responsible for installing, maintaining, and removing all Best
Management Practices (BMPs) and for all documentation required to keep the SWPPP current. For compliance with the District’s CSDC Program, the SWPPP/CSDC Plan should address all potential pollutants outlined in the ACHD Policy Manual.
A Rainfall Erosivity Waiver (Waiver) is available and defined in Appendix B Part B.1 of the CGP. If the
Waiver is utilized the Waiver shall have been prepared and submitted to ACHD for acceptance prior to the filing of the Waiver through the IPDES E-Permitting website. If the conditions on which the
Waiver is based change, the Contractor is responsible for updating the Waiver and/or development, including filing for NOI and NOT, and implementation of a SWPPP.
BMPs for controlling pollutant transport from the construction site can be found in a few publications including, but not limited to:
a) Idaho Department of Environmental Quality, Idaho Catalog of Storm Water Best Management
Practices at: https://www.deq.idaho.gov/water-quality/wastewater/storm-water/ or Phone: (208)
373-0502
Project Number: Page 11 of 13
b) United States Environmental Protection Agency – Region 10, Resources and Tools at:
https://www.epa.gov/npdes/construction-general-permit-resources-tools-and-templates , or phone:
(800) 424-4372
c) Idaho Transportation Department, Best Management Practices (BMP) Manual at:
https://itd.idaho.gov/env/?target=resources, phone: (208) 334-8476
Measurement and Payment: Payment for work items to implement the SWPPP or CSDC shall be per other specific bid items noted in this contract.
Payment for this plan preparation and approval item will be made under:
SSP 06013 – Stormwater Management Plan Preparation & Approval……..… Lump Sum
6. SP 11551– PEDESTRIAN TEMPORARY TRAFFIC CONTROL PLAN
Description: This work shall consist of preparation and implementation of a Pedestrian Temporary
Traffic Control (TTC) Plan as needed in the construction area inclusive to provide temporary facilities, including reasonably safe pedestrian routes around the Contractor’s work in accordance with the
Americans with Disabilities Act (ADA).
Materials: All materials (signs, barricades, temporary facilities and appurtenances) shall be in accordance with the Americans with Disabilities Act of 1990 (ADA), the Public Right-Of-Way
Accessibility Guidelines (PROWAG), and Manual on Uniform Traffic Control Devices (MUTCD).
Workmanship: The Contractor shall develop a Pedestrian TTC Plan for work at the construction site based upon his planned construction operation. The Contractor shall submit a written outline of the
TTC plan along with a layout of all temporary facilities, barricades and signing for review and approval prior to construction. The TTC plan shall provide the following:
1. The needs and control of pedestrians and bicyclists within the roadway and/or public right-of-way, including persons with disabilities in accordance with the Americans with Disabilities Act of 1990
(ADA), Title II, Paragraph 35.130) through a temporary traffic control “TTC” zone shall be an essential part of highway construction, utility work, maintenance operations, and the management of traffic incidents. The primary function of TTC is to provide for the reasonably safe and efficient movement of road users through or around TTC zones while reasonably protecting workers, responders to traffic incidents, and equipment.
2. Temporary facilities, including reasonably safe pedestrian routes around work sites, are also covered by the accessibility requirements of the Americans with Disabilities Act of 1990 (ADA) (Public Law
101-336, 104 Stat.327, July 26, 1990. 42 USC 12101-12213 (as amended)). Implementation of TTC plans and installation and maintenance of devices shall be the responsibility of the Contractor performing the construction, alteration and/or maintenance of the roadway or public right-of-way.
When an existing continuous sidewalk or street crossing route cannot be maintained for pedestrians because of construction, either temporary walkways with curb ramps are to be provided, or the construction shall be phased to maintain access to the affected addresses. Contractors shall be allowed flexibility as long as the requirements are met.
3. The location of the construction project and whether or not accessible facilities are present shall also determine the extent of the needed temporary facilities. The Contractor is only required to maintain
Project Number: Page 12 of 13 practical continuity where accessible facilities already exist. On low speed rural roads that do not have sidewalks and are used by bicyclists, no additional measures are needed as the bicycles can share the available travel lanes with other traffic. On moderate to higher speed rural roads, if a bike lane exists then it should be properly detoured, complete with signage, to provide a safe route through or around the work area. If a road or bridge project affects vehicular traffic to a business, residence, school or any other type of pedestrian generating location with existing accessible facilities, then pedestrian and handicapped access must be maintained.
4. A continuous route for all pedestrians, including people with disabilities and bicyclists, shall be maintained at all times. When existing pedestrian facilities are disrupted, closed, or relocated in a
TTC zone, the temporary facilities shall be detectable and include accessibility features consistent with the features present in the existing pedestrian facility. The temporary route should enable pedestrians to bypass the construction site while minimizing the retracing of their steps or going significantly out of their way. Additional consideration must be given to people with disabilities since they may not have the physical or cognitive ability to improvise (e.g. balancing along the curb or a very narrow path) or use unofficial alternatives (e.g. using an adjacent grass surface). Temporary routes must meet the accessibility guidelines of the ADA for permanent facilities as well as PROWAG and shall be marked with the proper signage. Should existing crosswalks at signalized intersections be closed or made inaccessible, temporary crosswalks should be painted in an accessible location.
Temporary signals should include pedestrian phases.
5. Contractors shall not block temporary walkways with Contractor parking, materials piles, signs, rubble or rubbish. Construction equipment and equipment operation must be separated from the temporary walkways. At work zones where higher volumes of pedestrian traffic or school children exist, pedestrian fences or other protective barriers may be needed to prevent access into the construction area.
6. Detour and diversion routes, when used for pedestrians and bicyclists, should be evaluated for the following items:
• Direct conflicts between pedestrians and vehicular traffic, work vehicles, and other work activities must be reduced with protective barriers or continuous high contrast fencing (min 36” high with a 6” high toe board). See Manual on Uniform Traffic Control Devices (MUTCD) 6F.68 and 6D.02; PROWAG R303.
• Temporary pedestrian facilities should provide safe, accessible routes that replicate as nearly as practical the most desirable characteristics of the existing facility, and parallel the disrupted route whenever possible. A smooth, continuous hard surface should be provided throughout the entire length of the temporary pedestrian facility. There should be no curbs or abrupt changes in grade or terrain that could cause tripping or be a barrier to wheelchair use. The geometry and alignment of the facility should meet the applicable requirements of the Americans with
Disabilities Act Accessibility Guidelines (ADAAG) for Buildings and Facilities. See MUTCD 6D.01 and 6D.02; PROWAG R303.3 and R302.6.
• Advance information placed at appropriate distances before the work zone allowing pedestrians to make timely decisions about routes through or around the work zone. See MUTCD 6F.14;
PROWAG R303.2.
• Transition information allowing pedestrians to find a safe path through and around work zones, which is critical when the pathway is restricted, diverted or detoured. See MUTCD 6F.14;
PROWAG R303.2.
• Work area information assisting in safe passage of pedestrians through the work zone. This information is needed on all pedestrian routes except detours. See MUTCD 6F.14
• Exit information directing pedestrians back to the original route. See MUTCD 6F.14
Project Number: Page 13 of 13
• Crosswalk placement at intersections may need additional signage, temporary striping, traffic signal modification, pedestrian signals with audible alarms if justified, proper push button height, and ramps. See MUTCD 6H.29, 6F.80, and 4E.06; PROWAG R303.5 and R304.
• Accommodations for other transit forms (busses, trains etc.) are made. See MUTCD 6D.02
• Requirements of the ADAAG, PROWAG, and MUTCD are adhered to.
• Access is maintained to the affected businesses and residences.
• Frequent checks of the pedestrian and bicycle accommodations are made during construction to ensure that the temporary traffic control plan is followed, traffic control devices are maintained in good condition, and safe, accessible pedestrian and bicycle routes are available at all times.
Upon approval the Contractor shall implement the prepared TTC plan. The Contractor shall be responsible for all work associated with the TTC plan including all initial placement, maintenance, relocations, and removal of all signs, barriers and temporary facilities.
Measurement and Payment: Traffic control devices used for the pedestrian or bicycle detour will be paid under their respective bid items when applicable. Relocation of each device to another location shall be paid under Traffic Control Maintenance. This item includes all design, submit, modify, inspect, and manage the Pedestrian Temporary Traffic Control Plan. Additional materials, labor, and equipment needed to complete and maintain the approved pedestrian detour will be measured and paid for by Force Account.
SP 11551 - Pedestrian Temporary Traffic Control Plan ………………………………Force Account