This is a Site-Specific Erosion and Sediment Control (ESC) Plan template required by the Ada County Highway District (ACHD) for the Cloverdale Road thermoplastic pavement marking replacement project extending from Franklin Road to Executive Drive in Idaho. The ESC Plan is a mandatory prerequisite to obtaining a Temporary Highway Use Permit and must be completed by the contractor and approved by ACHD prior to construction commencement. The project involves removing and replacing existing pavement markings on concrete pavement with thermoplastic markings to improve visibility and durability while reducing future maintenance requirements. Construction is anticipated to occur during nighttime hours, and the plan must remain on-site throughout the project duration. All disturbed areas will be stabilized upon completion of permanent construction, with Best Management Practices (BMPs) subsequently removed.

The ESC Plan addresses pollution control measures required under the Municipal Separate Storm Sewer System (MS4) National Pollutant Discharge Elimination System (NPDES) permit issued by the U.S. Environmental Protection Agency, with the objective of reducing pollutants to the Maximum Extent Practicable (MEP). Key pollution control measures include sediment controls such as street and gutter sweeping prior to forecasted rain, erosion controls, material storage protocols, waste disposal procedures, and spill prevention and response mechanisms. The contractor or qualified agent must inspect all disturbed areas and erosion/sediment control BMPs once every seven calendar days and within 24 hours of precipitation events exceeding 0.25 inches or snowmelt runoff. All concrete washout material must be collected and removed from the site, with spill cleanup materials and Safety Data Sheets maintained on-site. Stormwater discharge is directed to Evans Drain and Settlers Canal.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 | P a g e

SITE-SPECIFIC EROSION AND SEDIMENT CONTROL PLAN

• An approved Erosion and Sediment Control (ESC) Plan is required for all sites affecting the

ACHD right-of-way. The purpose of the ESC Plan is to reduce pollutants to the Maximum Extent Practicable (MEP) as required by the Municipal Separate Storm Sewer System (MS4) National Pollutant Discharge Elimination System (NPDES) permit issued by the U.S.

Environmental Protection Agency.

• This plan will need to be completed by the contractor and approved by ACHD prior to issuance of the Temporary Highway Use Permit.

• The ESC Plan shall be amended if it proves to be ineffective in significantly reducing pollutants. All amendments shall be signed, dated, and kept as attachments to the original ESC Plan.

• A working copy of this ESC Plan must be kept at the construction site.

Project Name and Location:

Cloverdale Rd, Franklin Rd to Executive Dr – Thermoplastic Replacement

Company Name, Address, and Phone Number:

Person Responsible and Certification Number:

Description of the Proposed Construction Activity

• Area disturbed for new pavement ∼ 0 square yards

• Area disturbed for sidewalk and driveway approaches ∼ 0 square yards

• Area disturbed for curb and gutter ∼ 0 square yards

• Area disturbed for asphalt repair ∼ 0 square yards

• Area disturbed for concrete repair ∼ 0 square yards

• Area disturbed for gravel repair ∼ 0 square yards

• Area disturbed for fill and sod repair ∼ 0 square yards

• Installation and maintenance of various types of erosion and sediment control measures

• Approximate total area disturbed ∼ 0 square yards (0 acres)

Schedule The following is a general schedule guideline for implementing BMPs during construction of this project. Construction is anticipated to begin mm/dd/yyyy and end mm/dd/yyyy.

Once all permanent construction is completed, all remaining areas will be stabilized (sod repair if needed) and BMPs will be removed.

Receiving Waters (include drains, ditches, and canals):

Evans Drain, Settlers Canal

Associated Industrial Activities (Identify waste sites to which waste will be hauled.)

2 | P a g e

Potential Sources of Pollution The primary construction activities, related materials, and wastes that have the potential to pollute stormwater include:

Solid wastes from curb, gutter, and asphalt demolition and removal.

Temporary on-site storage of construction materials General site litter and waste containers Port-a-pot, fuel tanks, chemical storage areas, and form oils, etc.

Erosion and sediment from exposed soil Dust from exposed soil Concrete from washout or excess

Pollution Control Measures/Best Management Practices

Sediment Controls Sidewalks, streets, and gutters will be swept before forecasted rain and at the completion of each site location.

Erosion Controls

Material Storage, Waste Disposal, Spill Prevention and Response Spill clean-up materials, safety data sheets (SDS), and a material inventory will be maintained on site to contain and clean-up spills and prevent material discharges offsite. Refer to the SDS for the manufacturer’s emergency number. Call 911 or the Idaho Communications Center (1-800-632- 8000). Report oil and chemical spills to the National Response Center: 1-800-424-8802. Spill clean-up materials kept onsite will include granular absorbent and hydrocarbon specific absorbent.

All concrete cleanout material will be collected and removed from the site. At no time will concrete washout be discharged into the street, gutter, or storm drain. Cleanout will be collected in buckets or in lined concrete washout pits.

Inspection/Maintenance Procedures The contractor or his qualified agent is required to inspect all disturbed areas and areas used for storage of materials and equipment that are exposed to precipitation. He is also required to inspect all erosion and sediment control BMPs. Inspections shall occur once every 7 calendar days and within 24 hours of the occurrence of a storm event of 0.25 inches or greater, or the occurrence of runoff from snowmelt sufficient to cause a discharge.

The following sources may be used to obtain weather forecasts:

The National Weather Service: http://www.wrh.noaa.gov/boi/ The Western Regional Climate Center http://www.wrcc.dri.edu/CURRENTOBS.html

All erosion and sediment control measures and other protective measures must be maintained in effective operating condition. If BMPs are not operating effectively, maintenance must be performed as soon as possible and before the next storm event whenever practicable to maintain the continued effectiveness of storm water controls.

http://www.wrh.noaa.gov/boi/ http://www.wrcc.dri.edu/CURRENTOBS.html

3 | P a g e

The contractor or his qualified agent is required to inspect all disturbed areas and areas used for storage of materials and equipment that are exposed to precipitation. He is also required to inspect all erosion and sediment control BMPs. Inspections shall occur once every 7 calendar days and within 24 hours of the occurrence of a storm event of 0.25 inches or greater, or the occurrence of runoff from snowmelt sufficient to cause a discharge.

(Operator and/or Responsible Authority) Date

4 | P a g e

TO BE PROVIDED BY ACHD:

GENERAL LOCATION MAP

SITE-SPECIFIC PLAN VIEW MAP SHOWING

♦ North Arrow, Scale, and Date ♦ Excavation, Grade, Paved Areas, Pond Elevations, Structures, and Utilities ♦ Property Boundaries and Lot Lines ♦ All Drainage Features ♦ Location and Type of Best Management Practices ♦ Key of Symbols

STANDARD DRAWINGS/ BMPs:

DI

Material storage Spill containment Sodding

Site-Specific Erosion and sediment Control Plan
Description of the Proposed Construction Activity
Schedule
Receiving Waters (include drains, ditches, and canals):
Associated Industrial Activities (Identify waste sites to which waste will be hauled.)
Potential Sources of Pollution
Pollution Control Measures/Best Management Practices
Material Storage, Waste Disposal, Spill Prevention and Response
Inspection/Maintenance Procedures