This document is a consolidation schedule for a special February 2026 equipment-only procurement conducted under the PACT ACT. The schedule outlines a compressed acquisition timeline spanning approximately three months, with all milestones applicable across all modalities.
The procurement process begins with requirements due to the NAC (National Acquisition Center) on February 27, 2026, followed by posting of requirements and the Request for Offers on March 18, 2026. Vendors have until March 24, 2026 to submit equipment-related questions, with NAC publishing responses via amendment by March 31, 2026. Vendors must submit their offers to the NAC by April 14, 2026, and customers receive these vendor offers via shared drive on April 22, 2026. Customers then submit technical evaluations and best value selections by May 6, 2026. The NAC assigns contracting officer workload on May 13, 2026, with execution of delivery order awards scheduled for May 22, 2026. The document notes that all dates are estimates and subject to change.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Zipped Files Updated.zip | ZIP file | |
| Copy of SPECIAL FEB 2026 EQ Consolidation Schedule of Line Items QA.xlsx | XLSX spreadsheet | |
| 36A79726Q0014 0003.docx | DOCX document | |
| 36A79726Q0014 0002.docx | DOCX document | |
| 687B63002.zip | ZIP file | |
| 36A79726Q0014 0002.docx | DOCX document | |
| SPECIAL FEB 2026 EQ Consolidation Schedule of Line Items Updated.xlsx | XLSX spreadsheet | |
| Memorandum for Training.pdf | ||
| VA Directive 6550 - New Appendix A - published Jun. 2023.pdf | ||
| 626B64018 _ 687B63002.zip | ZIP file | |
| Vendor Folders.zip | ZIP file | |
| Vendor Workup Spreadsheet - 36A79726Q0014.xlsx | XLSX spreadsheet | |
| SPECIAL FEB 2026 EQ Consolidation - Schedule of Line Items.xlsx | XLSX spreadsheet | |
| 534B62010 - 626B64017.zip | ZIP file | |
| 36A79726Q0014_2.docx | DOCX document |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIAL FEB 2026 EQUIPMENT ONLY CONSOLIDATION SCHEDULE
Dates *PACT ACT Special
Consolidation* Milestone – All Modalities
2/27/2026 Requirements due to the NAC in FORCE
3/18/2026 Post Requirements and Request for Offers (RFO)
3/24/2026 Vendors to submit Equipment Questions to NAC
3/31/2026
NAC Published Responses to Vendor Questions via
Amendment
4/14/2026 Vendors to Submit Offers to NAC
4/22/2026 Customers Receive Vendor Offers via the Shared Drive
5/6/2026
Customers Submit Technical Evaluations (Best Value
Selections)
5/13/2026 NAC Assigns CO Workload
5/22/2026 Execution of Delivery Order Awards
*Dates are estimates and are subject to change*