SPE605-21-R-0211 Questions and Answers.pdf

PDF 128 KB Posted

Attached to
Jet Fuel for Washington and Montana
Solicitation number
SPE605-21-R-0211
Issued by

View the file

Other files

File Type Posted
Attachment F C clauses.pdf PDF
Attachment G E clauses.pdf PDF
Offeror Submission Package.doc DOC document
Attachments C D and E.pdf PDF
Schedule A and B.pdf PDF
COG 8 Instructions and Clauses.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPE605-21-R-0211 QUESTIONS AND ANSWERS

Pertaining to both line items:

1. Can the escalator be changed?

No, DLA Energy’s Industrial Economists recommend that PLATTS escalators be used for Jet Fuel. As stated in the solicitation, DLA Energy does not intend to discuss any aspects of the offers and therefore will not accept any exception to the solicitation.

2. Please clarify the mode of delivery and receiving tank information. See below.

Line item 0002 (Montana)

This location has 2 above ground tanks with the capacity of 4,000 gallons per tank. The safety level for each tank is 3,800 gallons. The fuel does not require additives.

Line item 0003 (Washington)

This location has 1 above ground tank with the capacity of 30,000 gallons per tank. The fuel requires the following additives:

a) Corrosion Inhibitor/lubricity improver (CI/LI)

b) Fuel System Icing Inhibitor (FSII)

c) Static Dissipater Additive (SDA)