ATTACHMENT B - QandA.pdf

PDF 134 KB Posted

Attached to
Government Owned Contractor Operated Fuel Storage Facility at DFSP Tampa, FL
Solicitation number
SPE60326R0518
Issued by

About this file

This file is a Questions and Answers (Q&A) document from a federal contract solicitation for fuel storage and terminal operations services at Defense Fuel Supply Point (DFSP) Tampa. The document contains 58 numbered questions and corresponding Government answers addressing clarifications on contract requirements, responsibilities, staffing, facilities, equipment, and operational procedures.

Key operational requirements include: Type C petroleum product testing conducted on-site using Government-furnished laboratory equipment, with Type A and Type B testing funded directly by DLA Energy at an off-site laboratory (Intertek Fort Lauderdale); contractor responsibility for identifying and reporting facility deficiencies to the Government while Government maintains major facility systems; contractor responsibility for OSRO (Oil Spill Response Organization) retainer maintenance throughout the contract period; contractor furnishing of commercial phoneline, high-speed internet, radios, and base station with accessories; contractor responsibility for routine maintenance and consumables for Government-furnished generators; and Environmental Technician position authorized to have collateral duties. Terminal security requirements specify guard coverage 4:00 p.m. to 7:00 a.m. daily plus 24-hour coverage on weekends, Sundays, and holidays. Historical data indicates average fuel shipment size of 75 million barrels, with generator fuel consumption of 2,500 gallons over three years and pickup truck consumption of 25 gallons per quarter. Staffing requirements are outlined in PWS paragraphs 1.8, 1.11, and 1.12, with specific positions including Environmental Technician, Terminal Supervisor, Fuel Distribution System Manager, and security personnel. The contract involves Controlled Unclassified Information (CUI) with CMMC compliance requirements per DFARS 252.204-7021. Amendment P00014 removed "Sampling and Testing of Petroleum Products (Storage)" provisions, with all sampling and testing to be conducted per updated PWS dated November 18, 2026. Custody transfer point drawings, pipeline operating procedures, facility drawings, and environmental permits will be provided upon contract award.

View the file

Other files

File Type Posted
ATTACHMENT IA - Updated PWS.pdf PDF
SF30_SPE60326R05180014.pdf PDF
SF30_SPE60326R05180013.PDF.pdf PDF
SF30_SPE60326R05180012.PDF.pdf PDF
SF30_SPE60326R05180011.PDF.pdf PDF
SF30_SPE60326R05180010.PDF PDF
SF30_SPE60326R05180009.pdf PDF
SF30_SPE60326R05180008.pdf PDF
SF30_SPE60326R05180007.PDF.pdf PDF
SPE60326R0518 Amendment 0006.pdf PDF
SF30 SPE60326R0518 0005.pdf PDF
SF30 SPE60326R0518 0004.pdf PDF
SF30_SPE60326R05180003.PDF PDF
SPE60326R0518 Amendment 0002.pdf PDF
SF30_SPE60326R0518 Amendment 0001.PDF PDF
SF 1449 Solicitation.pdf PDF
ATTACHMENT III CONSOLIDATED QAP.pdf PDF
ATTACHMENT V PPQ.pdf PDF
ATTACHMENT VII PPRL.pdf PDF
ATTACHMENT II PPF.pdf PDF
ATTACHMENT IV Consent Form.pdf PDF
ATTACHMENT I PWS.pdf PDF
ATTACHMENT VI WD.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Question: C-2.2.1: Will the Government please clarify if the Type A and Type B laboratory testing costs are funded directly by DLA Energy, or should transportation and shipping costs for samples be included in the offeror's price?

Answer: The Performance Work Statement (PWS), has been updated to provide clarity.

Please refer to the PWS Para C-2.2.1 and C-2.2.2.

2. Question: C-1.12.2: Will the government clarify if the contract falls under normal RM/MR, meaning quarterly and semi-annual inspections will be accomplished under the DLA-SRM RM/MR program, or are quarterly and semi-annual inspections system maintenance tasks accomplished by the contractors FDSM?

Answer: The contract falls under RMMR and the PWS outlines FDSM responsibly in Para 1.12.2

3. C-2.1.2: Will the Government please specify what advanced notice is typically provided for tanker arrivals?

Answer: Schedules are shared months in advance.

4. Question: C-2.1.2: Will the Government please specify how frequently simultaneous operations occur involving tanker receipt, pipeline transfer, truck loading, maintenance, and quality surveillance?

Answer: Movements are mission based, please see PWS Table1 for Operating hours and Table 2 for tank truck and Pipeline shipment information.

5. Question: Will the Government please specify if there is a minimum response time requirement for after-hours receipts and transfers?

Answer: Common practice for receipts will be coordinated in advance with tanker branch and port Tampa. And all transfers to MacDill AFB will also be coordinated in advance refer to PWS Para 2.1.2 and 2.1.3

6. Question: C-2.4: Will the Government please provide the most recent API 653, inspection, and engineering reports (suitability reports) for the three storage tanks?

Answer: API 653 will be provided once contract is awarded.

7. Question: C-2.10: Will the Government please specify if the contractor is responsible for maintaining an OSRO retainer throughout the entire contract period?

Answer: Yes, the contractor is responsible, Please refer to PWS Para 2.10.5.3.The Performance Work Statement (PWS) has been updated to provide clarity.

8. Question: C-2.10.7: Will the Government please provide annual hazardous waste generation volumes for the last three years?

Answer: Roughly 22 Drums of filters and 750 gals of Petroleum Contact Water over the last 3 years.

9. Question: Will the Government please clarify when and how it intends to validate each offeror's CMMC Status prior to award?

Answer: CMMC will be checked in accordance with DFARS 252.204-7021, found on page 64 of the Solicitation..

10. Question: C-1.6: Will the Government please clarify that commercial phoneline, high speed internet, radios and base station with accessories are the responsibility of the contractor?

Answer: Yes these are the responsibility of the Contractor, please see PWS Para 1.6 , MacDill POC will be provided on contract award:

11. Question: C-2.4.2: Will the Government please clarify that the contractor is responsible for building maintenance for such actions as replacing broken windows, roof leak repairs, electrical troubleshooting, and fuse replacement?

Answer: Government facility maintenance will be conducted in accordance with PWS C- 2.4.2, the contractor is responsible for identifying and reporting all facility deficiencies to the Government, . The Performance Work Statement (PWS) has been updated to provide clarity.

12. Question: Can the government provide an annual estimate of the cost for calibrating laboratory equipment?

Answer: Contractors are responsible for developing their own cost estimates. Appendix C contains the list of provided laboratory equipment. Calibration equipment information can be found PWS Para 2.2.2

13. Question: Can the government provide an estimated cost for the weed control contract that is being used?

Answer: Contractors are responsible for their own estimates, Grounds maintenance information can be found PWS Para 2.4.10, 2.4.11 and 2.10.10.

14. Question: During the site visit there was discussion about a retainer fee (I believe it was a ORSO) can the government provide more information relating to this fee?

Answer: The PWS was updated to provide clarification. Please reference Para 2.10.5.3.

15. Question: Reference, Solicitation document, Supplement – Sampling and Testing of

Petroleum Products (Storage)

a. Question: The solicitation references an attachment entitled "Minimum Requirements for Storage Sampling and Testing." This attachment does not appear to have been included with the solicitation package posted to SAM.gov. Please provide a copy of the referenced attachment.

Answer: MIL STD 3004-1 latest revision.

b. Question: Based upon PWS Sections C-2.2.1 (Sampling) and C-2.2.2 (Testing), and discussions during the pre-proposal conference, our understanding is that the Contractor performs Type C testing utilizing the Government-furnished laboratory and equipment located at DFSP Tampa, while Type A and Type B samples are shipped to an approved off-site laboratory. Please confirm this understanding.

Answer: Correct, Type A and Type B samples are shipped to an approved off-site laboratory. The Contractor performs Type C testing utilizing the Government-furnished laboratory and equipment located at DFSP Tampa per PWS Para 2.2.1 and 2.2.2.

c. Question: Under the "Sampling and Testing of Petroleum Products (Storage)" provision, Offerors are required to select one of the testing options. Please clarify whether Option 1 applies solely to Type C testing performed using the Government furnished laboratory and equipment located at DFSP Tampa.

Answer: Amendment P00014 has been issued to remove "Sampling and Testing of Petroleum Products (Storage)" from the solicitation (page 8). All sampling and testing shall be conducted in accordance with the updated PWS dated November 18, 2026.

d. Question: Please clarify whether Option 3 applies to Type A and Type B samples that are shipped to an approved off-site laboratory for analysis.

Answer: Amendment P00014 has been issued to remove "Sampling and Testing of Petroleum Products (Storage)" from the solicitation (page 8). All sampling and testing shall be conducted in accordance with the updated PWS dated November 18, 2026.

16. Question: Reference C-1.6, Contractor Furnished Equipment. Communication Service Requirement.

a. Please provide the radio system specifications required for Contractor operations including encryption requirements and any required radio models or approved equipment lists.

Answer: For radio system specifications, including encryption requirements, and any radio models approved equipment lists; please refer to PWS Para 1.6, Communication Service Requirement 4th bullet.

17. Question: Reference C-1.6, Contractor Furnished Equipment. Vehicle Requirement

a. Question: Please provide historical annual fuel consumption data for Government-furnished generators and contractor-furnished vehicles utilized in support of DFSP Tampa operations for the previous three years, if available.

Answer: 2,500 gals for the generator (3 years) and the pickup is 25 gals per quarter

b. Question: Please clarify whether routine maintenance and consumables associated with Government-furnished generators (including oil changes, filters, and fluids) are the responsibility of the Contractor.

Answer: Yes, these are the responsibility of the Contractor Per PWS Para 2.4.9

18. Reference PWS C-1.12.5, Environmental Technician.

a. Question: Please clarify whether the Environmental Technician is intended to be a dedicated, full-time position assigned to DFSP Tampa or whether the Environmental Technician responsibilities may be performed as an additional duty by another qualified contractor employee (e.g., TS, ATS, FDSO or similar position) provided all PWS requirements and qualification requirements are met.

Answer: Position can have collateral duties please see PWS para 1.12.5.

19. Question: Reference C-2.1.2 Terminal Product Receipts. Product Receipts from Tampa Dock and Manifold Facilities.

a. Question: Please provide the average and maximum duration of fuel receipt operations from the Tampa Dock and Manifold System under current operating conditions.

Answer: Average shipment size is 75MBBL, and Pipeline pumping information can be found in PWS Para 2.1.1

b. Question: Please provide the anticipated fuel receipt rate and estimated duration of receipt operations following completion of the planned pipeline improvements.

Answer: Please refer to the answer above.

20. Question: Reference C-2.2.2 Testing. Type A and Type B testing will be funded directly by DLA Energy.

a. Please clarify whether Government reimbursement includes:

i. Laboratory testing costs:

ii. Sample shipping costs:

iii. Packaging materials:

iv. Chain of custody materials:

v. Other associated transportation expenses:

Answer: Testing information is under PWS par 2.2.2

b. Question: Please identify the laboratory currently utilized for these services.

Answer: Intertek Fort Lauderdale, Government contracted Lab.

21. Reference C-2.4 Maintenance-General, the Contractor is responsible for preventive maintenance and repair of terminal facilities and equipment (outside of RMMR/SRM)

a. Question: Please clarify the division of maintenance responsibilities between Contractor performed maintenance and Government-performed maintenance under the Repair, Maintenance, Minor Repair (RMMR) and Sustainment, Restoration, and Modernization (SRM) programs.

Answer: Please refer to PWS Para 2.4 and sub parts.

b. Question: Specifically, please identify whether quarterly, semi-annual, and annual maintenance activities are Contractor responsibilities or Government (RMMR) responsibilities.

Answer: Please refer to PWS Para 2.4 and sub parts.

22. Question: Reference C-2.4.2 Buildings.

a. Question: Please clarify the extent of Contractor responsibility for roof repairs. Is the Contractor responsible only for minor repairs and leak mitigation, or does responsibility include major roof repair or roof replacement?

Answer:, the contractor is responsible for identifying and reporting all facility deficiencies to the Government, please refer to PWS para 2.4.2.

b. Question: Please clarify whether lighting maintenance responsibilities include perimeter security lighting, tank farm lighting, and elevated pole-mounted lighting.

Answer: Government facility maintenance will be covered by the Government however the contractor is responsible for identifying and reporting all facility deficiencies to the Government, please refer to PWS para 2.4.2.

c. Question: If elevated lighting maintenance is Contractor responsibility, please identify whether Government-furnished access equipment (e.g., manlift or bucket truck) is available.

Answer: the contractor is responsible for identifying and reporting all facility deficiencies to the Government, please refer to PWS para 2.4.2.

23. Question: Reference C-2.4.4 Pits. Please provide the following:

a. Total number of pits at DFSP Tampa

Answer: PWS paragraph 2.4.4 has been updated to reflect that the total number of pits is 6.

b. Number of pits classified as permit-required confined spaces requiring access by the Contractor.

Answer: There are currently zero permit-required pits, please refer to the PWS and solicitation for all proposal requirements.

c. Question: Please confirm if the referenced vacuum truck is provided by the base and who is responsible for disposing of water collected in the vacuum truck.

Answer: Updated PWS 2.4.4, Truck is coordinated through FMSR/RMMR

24. Reference C-2.4.13 Fire Protection. The Contractor may be required to complete repairs.

a. Question: Please clarify the extent of Contractor responsibility for fire protection system repairs. Specifically, please identify whether Contractor responsibilities are limited to inspections, testing and minor repairs or include major repairs and component replacement of fire suppression system.

Answer: Contractors’ responsible items are outlined in PWS Para 2.4.13 and government items in Appendix C other provided property

25. Reference C-2.5 Contractor Personnel Training and Recordkeeping. Table 3 Required

Contractor Training Elements.

a. Question: Please identify any required training, certifications, and recurring training frequencies applicable to security guards.

Answer: Guard responsibilities are outlined in PWS Para 2.11.1

26. Reference C-3.3 CLIN 0001 Structure and Description. Maintenance.

a. Question: Additionally, please clarify whether the hydrant system maintenance pertains to fire protection hydrants, fuel transfer hydrants or both.

Answer: Hydrant system maintenance pertains to fire protection hydrants per PWS para 2.4.13, DFSP Tampa has no fuel hydrant system.

27. Question: Reference Appendix B Provided Facilities, Fire Hydrants. Hand-held dry chemical fire extinguishers. Please identify the total quantity of portable fire extinguishers and whether annual inspection, maintenance, recharge, hydrostatic testing and replacement are Contractor responsibility.

Answer: Updated PWS Para 2.4.13 for clarification and see Appendix C for equipment listing . There are 12 portable and 5 150# Purple K fire extinguishers

28. Question: Reference Appendix C Provided Equipment. Government Property Inventory

Listing.

a. Question: Lab Eq: We acknowledge two flash testers, oven and a conductivity meter is provided for Contractor use. Please confirm if FSII sampling equipment (i.e. B-2 Refractometer) is provided by the Government.

Answer: All items to conduct C-Level testing are on site and provided.

29. Question: Reference PWS C-2.11 Terminal Security: The paragraph states “The hours stated in this paragraph are 4:00 p.m. to 7:00 a.m. daily and two unarmed guards 24 hours per day on Saturdays, Sundays, and holidays.” However, during the site visit it was stated that the guards currently work 4:00 p.m. – 12:00 a.m. and 12 a.m. – 8:00 a.m. Please clarify why guards are working 12:00 a.m.-8:00 a.m. Monday through Friday as opposed to 12:00 a.m.-7 a.m.

Answer: Information about Guard Requirements can be found in PWS para 2.11

30. GOCO vs COCO Pricing Basis

Question: Please confirm that Amendment 0001 supersedes the original Attachment II Price Proposal Form in its entirety, and that CLIN 0002 is intended to be priced as GOCO fuel storage services for DFSP Tampa rather than COCO services at Port Tampa.

Answer: Yes, it does.

31. Question: Proposal Attachments and Submission Requirements.

Please confirm the correct attachment mapping and proposal submission requirements for the Price Volume and Past Performance Volume, including the applicable Price Proposal Form, Past Performance Questionnaire, Consent Form, and Reference List attachments.

Answer: Please see amendment 0001 for applicable price proposal form. All other referenced attachments remain as stated in section J of the solicitation.

32. Question: Proposal Plans vs. Post-Award Plans Please clarify which plans must be submitted with the proposal versus post-award, including the Maintenance Plan, Operations Plan, Product Inventory Control and Accountability Plan, Product Quality Surveillance Plan, Safety Plan, Security Plan, Training Plan, Contract Compliance Plan, and Environmental Protection Plan. For plans required with the proposal, should offerors provide a technical approach or fully developed procedures?

Answer: The Staffing plan must be submitted with the proposal. All other plans must be submitted NLT 60 days prior to start of contract period of performance IAW para

1.5.1 – 1.5.12.

33. Question: Historical Workload Data Please provide the last three years of historical workload data by month, including receipts, shipments, throughput, tank truck loading activity, after-hours operations, weekend and holiday operations, surge events, average daily activity, and peak daily activity.

Answer: For Planning information see PWS par 1.7, 2.1.2 and Table 1 and 2

34. Historical Receipt Duration Data

Question: Please provide historical average duration data for tanker and barge receipt operations, including preparation, receipt, testing, displacement activities, documentation, and return-to-service actions.

Answer: For Planning information see PWS par 1.7, 2.1.2 and Table 1

35. Out-of-Service Pipeline Status

Question: Please provide the current status of the out-of-service 8-inch receipt pipeline, anticipated return-to-service plans if known, and contractor responsibilities associated with that pipeline.

Answer: There are no longer out of service pipelines, as they have been filled with Slurry and are no longer in use. Updated PWS par’s 2.1.1

36. Demurrage and Delay Responsibility

Question: Please clarify the contractor's responsibilities regarding coordination activities intended to prevent demurrage and identify which delay events are considered within versus outside the contractor's control for performance evaluation purposes.

Answer: Contractor is responsible for proper coordination with Port Tampa prior to and during receipts per PWS Para 2.1.2

37. Custody Transfer Boundaries

Question: Please provide custody transfer point drawings, pipeline and manifold operating interface information, ownership boundaries, line capacities, and applicable operating procedures governing product displacement activities.

Answer: Information will be provided on contract award.

38. Staffing Requirements

Question: Is the staffing model entirely performance-based and left to the offeror, or does the Government require minimum staffing by position, shift, or function beyond the specific positions identified in the PWS? Additionally, please clarify whether the Environmental Technician must be a dedicated full-time position or may be supported through regional or corporate environmental resources provided all PWS requirements are satisfied.

Answer: Staffing requirements can be found in PWS Para 1.8 1.11 and 1.12.

Environments position can be an extra duty.

39. Security Staffing Requirements

Question: Please confirm the minimum security staffing requirements during normal duty hours, non-duty hours, weekends, holidays, and special events.

Answer: Information about Guard Requirements can be found in PWS para 2.11 and Table 1.

40. Incumbent Workforce and CBA

Question: Please confirm whether the incumbent workforce is covered by a collective bargaining agreement. If so, please provide the applicable CBA, incumbent staffing roster by labor category, seniority and vacation obligations, Section 4(c) successor contractor requirements, average annual hours worked, overtime utilization, vacancy rates, shift coverage, and current vacancy status.

Answer: There is no Collective Bargaining Agreement for the incumbent contractor.

41. Transition and System Access

Question: Please clarify whether the transition period is separately funded or included within the fixed-price contract. Additionally, please provide expected timelines for base access, CAC/ECA issuance, APSR/Fuels Manager access, ADP/NAC processing, and related system onboarding activities.

Answer: There is no separately funded “transition period.” All associated costs should be included in the Firm Fixed-Price price proposal. Base access and CAC varies based on each applicant. Procedures for obtaining CAC are found in PWS appendix A

42. Cybersecurity Requirements

Question: Please clarify whether contract performance involves Controlled Unclassified Information or Covered Defense Information on contractor information systems and identify any required NIST 800-171, SPRS, CMMC, or related cybersecurity requirements for award and performance.

Answer: Yes, the contract involves CUI.

43. Environmental Compliance Requirements

Question: Please provide available environmental permits, plans, compliance requirements, recent inspection findings, known corrective actions, EESOH-MIS requirements, associated reporting obligations applicable to contract performance, and any known ongoing remediation activities, consent orders, enforcement actions, or environmental corrective actions that may affect contract performance.

Answer: Information will be provided on contract award

44. Spill Response Requirements

Question: Please clarify the contractor's responsibilities for emergency spill response activities and provide historical spill-response activity levels, OSRO utilization requirements, disposal requirements, and typical Government expectations regarding spill-response support.

Answer: PWS Para 2.10.5.3 updated for clarification

45. Laboratory Requirements

Question: Please confirm the required on-site laboratory capabilities, required testing equipment, available Government-furnished laboratory facilities and equipment, and responsibility for sample shipment costs associated with off-site testing.

Answer: Onsite testing capability will include Type C. Type A and B will be offsite and funded by DLA please see PWS Para 2.2.1 and 2.2.2

46. Flame-Resistant Clothing Requirements

Question: Please clarify which positions require NFPA 2112 flame-resistant clothing and whether all personnel require flame-resistant clothing for routine site access or emergency response duties.

Answer: NFPA 2112 will be required to enter Port Tampa facility to perform inspections and other duties outlined in the PWS para 1.6.2

47. Facility Condition and Government-Furnished Property

Question: Please provide any available facility condition information, recent inspection findings, known facility or equipment deficiencies expected to exist at turnover, and Government-Furnished Equipment/Government-Furnished Property information relevant to proposal preparation, including maintenance responsibility boundaries.

Answer: Updated PWS para 3.3 sub parts and appendix C property list.

48. Tank Inspection and Cleaning Requirements

Question: Please provide current tank inspection status, next scheduled inspection and cleaning dates, planned outage schedules, and clarification regarding responsibility for tank cleaning, temporary storage, product transfers, waste disposal, and related activities.

Answer: Updated PWS Appendix B, to reflect no contractor responsibility for tank cleanings or maintenance. Inspections and maintenance will be covered under the DLA Energy Tank CMP program.

49. Pipeline Pressure Testing

Question: Please clarify responsibility for annual pipeline pressure testing, including funding, execution responsibilities, prior testing procedures, and the results of recent tests.

Answer: Pipeline pressures check will be preformed by the Government. See PWS para 2.4.8.

50. Meter Calibration Responsibilities

Question: Please clarify responsibility for meter calibration and proving activities, including funding, scheduling, execution responsibility, current calibration status, and next due dates for custody transfer and issue meters.

Answer: Callibrations are covered under RMMR program, see PWS para C-2.4.5.

51. Fire Protection System Responsibilities

Question: Please clarify responsibility for annual fire protection system certification activities and provide recent inspection reports, certification records, and any open deficiencies.

52. Facility Drawings and Technical Data

Question: Please provide available as-built drawings, electrical one-line diagrams, utility drawings, pipeline alignment drawings, manifold drawings, tank drawings, and fire protection system drawings relevant to contract performance.

53. Planned Facility Projects and Outages

Question: Please identify any planned SRM, RMMR, tank outage, pipeline outage, environmental, utility, facility modernization, or other major projects expected during the ordering period that may affect contractor operations.

54. Radio Requirements

Question: Please provide the technical specifications, encryption requirements, approval process, and any equipment restrictions associated with radios required to operate on the MacDill AFB LMR system.

Answer: Updated PWS para 1.6, MacDill POC will be provided on contract award:

55. Vegetation Control Requirements.

Question: Please provide available maps and descriptions of contractor-maintained vegetation areas, pipeline rights-of-way, wetlands or restricted areas, and any known access limitations affecting vegetation management.

56. Truck Loading Demand and Peak Operations.

Question: Please provide average and peak truck loading demand, carrier arrival patterns, emergency loading requirements, and any recurring support requirements outside normal truck fill stand operating hours.

Answer: For planning purposes please see PWS Table 1 and 2.

57. Generator Operations and Qualifications

Question: Please clarify qualification requirements for personnel operating generators, switchgear, and related electrical systems, and provide available maintenance history and operational requirements.

Answer: According to PWS C-1.10, the Contractor must ensure that all Personnel assigned to all takss have the requisite knowledge and skills to meet the minimum performance standards and comply with all applicable Federal, State, and local laws and regulations. Employees will be trained during contract transition period per PWS para 1.3.

58. Pre-Proposal Conference

Question: The solicitation references a pre-proposal conference/site visit held for this requirement. Please provide a copy of any pre-proposal conference slides, briefing materials, sign-in sheets, site visit handouts, attendee questions, Government responses, or other materials provided or discussed during the pre-proposal conference/site visit so all offerors have equal access to the same information for proposal preparation.

Answer: See amendment 0002 for conference slides. No handouts were provided to the conference attendees.