Attach_B19.34_Rev_Amd_1.pdf

PDF 48 KB Posted

Attached to
DLA ENERGY BULK PETROLEUM PRODUCTS - JPTS - SPE60016R0712
Solicitation number
SPE60016R0712
Issued by

About this file

Amendment 0001 - Revised B19.34

View the file

Other files

File Type Posted
Summary_of_Awards_SPE60016R0712.pdf PDF
Amendment_0003.pdf PDF
Amendment_0002.pdf PDF
Attach_ENERGY_QAP_C16.08-13_Rev_Amd2.pdf PDF
Attach_52.216-9069_Rev_Amd_1.pdf PDF
Amendment_0001.pdf PDF
Attach_OSP_Rev_Amd_1.pdf PDF
SPE60016R0712_Solicitation_FBO.pdf PDF
ATTACHMENT_1_DLA_Energy_19.3_Dec_2013_.pdf PDF
ATTACHMENT_2_C_QAPS.pdf PDF
ATTACHMENT_3_E_QAPS.pdf PDF
OSP.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation SPE600-16-R-0712 Amendment 0001

A. The following update has been made in Section B:

(Note: No changes have been made to the prices or the evaluation factors. The only change is to paragraph (6) Upward ceiling on economic price adjustment)

B19.34 Economic Price Adjustment (Overseas Bulk)(DLA Energy Jan 2012) is deleted in its entirety and replaced with the following:

B19.34 ECONOMIC PRICE ADJUSTMENT (OVERSEAS BULK) (DLA ENERGY JAN 2012)

(a) WARRANTIES. The Contractor warrants that--

(1) The unit prices set forth in this offer and/or contract do not include allowances for any portion of the contingency covered by this contract provision; and

(2) The prices to be invoiced hereunder for listed items shall be computed in accordance with these escalation provisions.

(b) DEFINITIONS. As used throughout this contract provision, the term--

(1) Base unit price means the unit price set forth opposite the item in the Schedule.

(2) Reference price means the market price indicator set forth in the Table in (f) below with which the base unit price is to fluctuate. NOTE: The term market price indicator will be referred to hereafter as “reference price” in this contract provision.

(3) Date of delivery is defined as follows:

(i) FOR TANKER OR BARGE DELIVERIES.

(A) F.O.B. ORIGIN. The date and time vessel commences loading.

(B) F.O.B. DESTINATION. The date and time vessel commences discharging.

(ii) FOR PIPELINE DELIVERIES. The date and time product commences to move past the specified f.o.b. point.

(iii) FOR ALL OTHER TYPES OF DELIVERIES. The date product is received.

(c) ADJUSTMENTS.

(1) The Contractor shall give written notice to the Contracting Officer, Defense Logistics Agency Energy (DLA Energy), of any delivery and associated change in the reference price within 15 working days from the date thereof. Contractor failure to timely notify the Contracting Officer of any delivery and associated change in the reference price may result in late or incorrect payment of the relevant invoice.

(2) Subject to the conditions of this contract provision, the prices payable under this contract shall be the base unit price increased or decreased by the same number of cents, or fraction thereof, that the reference price shall have increased or decreased.

(3) An increase or decrease in any reference price published in a trade price service or in a commercial journal shall apply only to deliveries made on and after the effective date of the price change as stated in the publication.

(4) The Contracting Officer will issue a modification to this contract to reflect any change pursuant to this provision.

However, no increase in a contract unit price shall be executed pursuant to this provision until the increase in the applicable published reference price has been verified by the Contracting Officer.

(5) FAILURE TO DELIVER. Notwithstanding any other conditions of this contract provision, no upward adjustment shall apply to product scheduled under the contract to be delivered before the effective date of the adjustment, unless the Contractor’s failure to deliver according to the delivery schedule results from causes beyond the Contractor’s control and without its fault or negligence, within the meaning of paragraphs (f), Excusable Delays, and (m), Termination for Cause, of the CONTRACT TERMS AND CONDITIONS – COMMERCIAL ITEMS clause of this contract, in which case the contract shall be amended to make an equitable extension of the delivery schedule.

(6) UPWARD CEILING ON ECONOMIC PRICE ADJUSTMENT. The Contractor agrees that the total increase in any contract unit price pursuant to these economic price adjustment provisions shall not exceed 375% percent of the award price, except as provided hereafter.

(i) If at any time the Contractor has reason to believe that within the near future a price adjustment under the conditions of this contract provision will be required that will exceed the current contract ceiling price for any item, the Contractor shall promptly notify the Contracting Officer in writing of the expected increase. The notification shall include a revised ceiling the Contractor believes is sufficient to permit completion of remaining contract performance, along with appropriate explanation and documentation as required by the Contracting Officer.

Solicitation SPE600-16-R-0712 Amendment 0001

(ii) If an actual increase in the reference price would raise a contract unit price for an item above the current ceiling, the Contractor shall have no obligation under this contract to fill pending or future orders for such item, as of the effective date of the increase, unless the Contracting Officer issues a contract modification to raise the ceiling. If the contract ceiling will not be raised, the Contracting Officer shall so promptly notify the Contractor in writing.

(7) REVISION OF REFERENCE PRICE INDICATOR. In the event--

(i) Any applicable reference price is discontinued or its method of derivation is altered substantially; or

(ii) The Contracting Officer determines that the reference price consistently and substantially failed to reflect market conditions--the parties shall mutually agree upon an appropriate and comparable substitute for determining the price adjustments hereunder. The contract shall be modified to reflect such substitute effective on the date the indicator was discontinued, altered, or began to consistently and substantially fail to reflect market conditions. If the parties fail to agree on an appropriate substitute, the matter shall be resolved in accordance with paragraph (d), Disputes, of the CONTRACT TERMS AND CONDITIONS – COMMERCIAL ITEMS clause of this contract.

(8) CONVERSION FACTORS. If this contract provision requires quantity conversion for economic price adjustment purposes, the conversion factors for applicable products, as specified in the CONVERSION FACTORS provision, apply unless otherwise specified in the Schedule.

(d) EXAMINATION OF RECORDS. The Contractor agrees that the Contracting Officer or designated representatives shall have the right to examine the Contractor's books, records, documents, or other data the Contracting Officer deems necessary to verify Contractor adherence to the conditions of this contract provision.

(e) FINAL INVOICE. The Contractor shall include a statement on the final invoice that the amounts invoiced hereunder have applied all decreases required by this contract provision.

(f) TABLE.

I II III IV V

Heading under which Reference reference price is Location where price as of Name of published and reference price APRIL 5, 2016 Item no. publication name of product is applicable (excludes all taxes)

0002/0009 PLATT’S OILGRAM JET KERO CARGO SINGAPORE $1.128095

0010/0011 PRICE REPORT

NOTE: The reference price shall be determined on a monthly basis by calculating the simple average of all the high and low prices effective during the month. Such monthly averages shall become the reference price with which the contract price will be adjusted for deliveries occurring during the following month.

A. The following update has been made in Section B:
(Note: No changes have been made to the prices or the evaluation factors. The only change is to paragraph (6) Upward ceiling on economic price adjustment)
NOTE: The reference price shall be determined on a monthly basis by calculating the simple average of all the high and low prices effective during the month. Such monthly averages shall become the reference price with which the contract price will b...