Amendment_0003_Q&A.pdf

PDF 21 KB Posted

Attached to
NAS Rota, Spain GOCO Services
Solicitation number
SPE600-16-R-0516
Issued by

About this file

Amendment 0003 Q&A

View the file

Other files

File Type Posted
Amendment_0006_Answers_to_Q&As.pdf PDF
Amendment_0005_Revised_B-0001_B30.pdf PDF
Amendment_0004.pdf PDF
Contract_Question__3_Sample_Spreadsheet.pdf PDF
B-0001.pdf PDF
Pre-proposal_Sign-In_Sheet.pdf PDF
Amendment_0003.pdf PDF
Amendment_0002.pdf PDF
Amendment_0001.pdf PDF
PWS_ROTA_FINAL-_29_Nov_16.pdf PDF
ATTACHMENT_III_CONSENT_FORM.pdf PDF
ATTACHMENT_I_OSP.pdf PDF
Attachment_II_PPQ.pdf PDF
ATTACHMENT_IV_PWS.pdf PDF
RFP-SPE60016R0516_Rota_Final_Dec_22,_2016.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Technical question:

Question: Will the government consider providing historical data for unforeseen workloads as outlined in C-1.6.1, to enable us to provide more accurate pricing? If historical “unforeseen” workload data is not available, and unforeseen workloads require augmentation or overtime in order to meet program needs, how will the government compensate the contractor?

Answer: A slide presentation with historical information was given at the pre-proposal conference. Copies may be obtained via request from George.McKay@eu.navy.mil

Contract questions:

1. Question: If a new “Employee Agreement” is signed between the employees and the incumbent contractor prior to the start date of the contract, will a copy of the Agreement be made available? If not, will contractors be allowed to submit a request for equitable adjustment after award to revise their Final Pricing Offer?

Answer: No Equitable Adjustment will be allowed after award. The Government cannot offer advice on Spanish Labor Law. This is a firm-fixed price contract, and it is the offeror’s responsibility to research and obtain the information necessary in order to determine their offer price.

2. Question: In order to comply with applicable Spanish Labor Regulations, employees under the current contract have first right of refusal under the new contract. Could you provide the list and labor costs of all personnel currently working under the labor contract for the incumbent contractor?

Answer: It is the offeror’s responsibility to research and obtain the information necessary in order to determine their offer price. This is a performance based contract, therefore the Government does not dictate the number of personnel required.