SPBN262011_VehicleDenialBarriers_RFP_Signed~1.pdf

PDF 246 KB Posted

Attached to
ITB SPBN262011 Install Vehicle Denial Barriers (Otis ANGB, MA)
Solicitation number
BD-27-1069-MILDV-40000-133296
Issued by
Massachusetts

About this file

This Request for Proposal (RFP) issued by the Department of the Air Force's 102d Intelligence Wing and 102d Civil Engineer Squadron at Otis Air National Guard Base in Massachusetts solicits contractor services to install vehicle denial barriers and anti-terrorism physical security measures. The project is structured as a Base Bid covering approximately 1,000 linear feet of existing fence retrofitting with dual-cable high-tension arresting systems and concrete deadman block installation, with two optional scopes: Option 1 for installing approximately 150 linear feet of new steel cable guardrails to a parking entrance, and Option 2 for excavating and relocating existing concrete deadman blocks from incorrect locations along East Truck Road and Generals Boulevard. All contractors must field-verify site conditions, alignments, and material quantities prior to final design and procurement. The work must conform to Department of Defense Unified Facilities Criteria (UFC 4-022-03 for fencing and UFC 4-022-02 for vehicle barriers), International Building Code standards, and all applicable state and federal codes. Cable specifications require minimum 3/4-inch diameter high-strength steel cables with 200-foot anchoring intervals, concrete deadman blocks installed on the secure side of the fence, and posts embedded minimum 2 feet 6 inches below finished grade for guardrails. The RFP does not specify response dates, site visit schedules, bidders' conferences, or award dates within the provided documentation.

Proposals must be submitted in separate technical and price volumes with firm-fixed-price breakdowns for each bid item and option, including detailed material, labor, equipment, transportation, storage, and General & Administrative Overhead costs. Contractors must demonstrate past performance on Department of Defense crash-rated and high-tension cable projects and submit preliminary construction drawings, concrete and tensioning calculations, and environmental and accident prevention plans. All contractor personnel require Defense Biometric Identification System (DBIDS) vetting and background clearances submitted at least fourteen days before work commencement. The project site is located on the Joint Base Cape Cod over the Cape Cod Sole Source Aquifer, requiring strict environmental compliance including zero-tolerance spill policies, silt fencing during excavation, AF Form 103 Dig Permits before ground disturbance, and submission of Safety Data Sheets for all chemicals and hazardous substances with secondary containment capacity of 110 percent of fluid volume. All work must comply with OSHA regulations (29 CFR 1926) and Air Force Mishap Prevention Program requirements with site-specific Accident Prevention Plans and Job Hazard Analyses for high-risk tasks including cable tensioning, concrete pours, and excavation operations.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

102D INTELLIGENCE WING (ACC)

MASSACHUSETTS AIR NATIONAL GUARD

OTIS AIR NATIONAL GUARD BASE

Project Number / Subject: SPBN262011, INSTALL VEHICLE DENIAL BARRIERS 102d Intelligence Wing (102 IW), 102d Civil Engineer Squadron (102 CES) Otis Air National Guard Base, Joint Base Cape Cod, MA Location: Otis Air National Guard Base (ANGB), MA Date of Issue: Aug 2026

1. PROJECT OVERVIEW & GENERAL SCOPE

1.1 Objective

The 102d Intelligence Wing (102 IW) and the 102d Civil Engineer Squadron (102 CES) have a requirement to install anti-terrorism (AT) measures in various locations. Specifically, the physical security measures addressed in this Request for Proposal (RFP) will protect critical military assets and personnel against vehicle-borne threats. To accomplish this, the contractor shall provide all labor, engineering, equipment, materials, transportation, storage, General & Administrative Overhead (GAOH), and coordination required to install high-tension arresting cables and vehicle guard rails.

1.2 Total Physical Scope & Field Verification

The proposed work is divided into a Base Bid and two optional scopes, covering existing fence reinforcement, new barrier installation, and block relocation.

• Contractor Verification Mandate: All linear footages, physical locations, and material counts provided in this solicitation are approximate. The contractor shall field-verify all site conditions, alignments, and dimensions prior to final design, material procurement, and construction mobilization.

• Aesthetics and Integration Match: The new passive barriers must structurally and aesthetically match the physical profile, engineering type, height, and finish of the existing active and passive vehicle barriers on the installation's perimeter.

2. TECHNICAL SPECIFICATIONS & DESIGN STANDARDS

The Department of Defense (DoD) utilizes the Unified Facilities Criteria (UFC) as its building code, which refers to the latest version of the International Building Code (IBC). In addition to UFC guidance, the contractor shall adhere to all State, Federal, and local installation codes. Where State and Federal codes differ from UFC guidance, the UFC shall be the governing standard.

Unified Facilities Criteria resources can be accessed at the following official portal:

https://www.wbdg.org/dod/ufc

2.1 Base Bid (Section A): Existing Fence Retrofit - Steel Cable Reinforcing (Approx.

$1,000\text{ LF}$)

For the existing fence modification under the Base Bid (Section A), the contractor shall retrofit and reinforce the fence line using a dual-cable high-tension arresting system.

• Reference Standard: UFC 4-022-03, Security Fences and Gates (dated 1 October 2013).

o Section 2-11 (Fencing Reinforcement) shall govern the installation.

o Applicable drawings, notes, and construction details are located at the end of the UFC on page 66 of 83.

o Drawing numbers UFC-710, UFC-711, UFC-712, and UFC-713 show further requirements for fencing hardware, connection brackets, and tensioners.

• Cable Specifications: Utilize high-strength steel cables, each with a minimum diameter of 3/4 in.

• Anchoring System: Implement a 200 ft anchoring interval.

• Technical Constraints:

1. Deadman Blocks: Concrete deadman blocks shall be spaced at intervals no greater than 200 LF along the fence line.

2. Cable Placement: Cables must be installed on the designated ATTACK side of the perimeter fence.

3. Block Placement: Concrete deadman blocks must be installed on the INSIDE (secure side) of the perimeter fence.

4. Engineering Submittals: The contractor's design proposal must specify and verify cable size, vertical spacing, and structural tensioning calculations.

2.2 Option 1 (Section B): New Steel Cable Guardrails to Parking Entrance (Approx. 150 LF) https://www.wbdg.org/dod/ufc

For Section B, the contractor shall construct and install standard high-strength steel cable guardrail systems starting from the existing fence line and extending to the parking entrance.

• Cable Specifications: Utilize steel cables, each with a minimum diameter of $3/4\text{-in} vertical spacing between cables.

• Post and Foundation Requirements:

o All posts shall be embedded in a concrete foundation with a minimum depth of 2 ft 6 in below finished grade.

o Post spacing, steel grades, and tensioning must conform to AASHTO guidelines for highway cable rails.

• Standard Adequacy: In accordance with UFC 4-022-02, Selection and Application of Vehicle Barriers, standard highway-grade cable guardrails are sufficient and approved for use as passive vehicle denial barriers under this scope of work (https://www.wbdg.org/dod/ufc/ufc-4-022-02).

2.3 Option 2 (Section C): Replace/Relocate Existing Deadman Blocks

For Section C, previously installed concrete deadman blocks were incorrectly placed on the attack side or require repositioning.

• Scope of Work: The contractor shall carefully excavate, lift, transport, and reinstall the existing concrete deadman blocks from the ATTACK side to the INSIDE (secure side) of the perimeter fence line.

• Location Focus: This relocation work is focused along the fence lines bordering East Truck Rd and Generals Blvd.

• Reinstallation Standards: The relocated blocks must be anchored, aligned, and integrated into the high-tension dual-cable system in strict accordance with the standards outlined in Section 2.1. The contractor must ensure that the associated cables remain on the designated attack side, while the structural deadman blocks are securely set on the protected, inside of the fence.

3. BIDDING STRUCTURE & LINE ITEM OPTIONS

Contractors must provide firm-fixed-price proposals broken down by the specific items listed below. All physical measurements provided below are approximate and must be verified in the field by the contractor prior to submitting proposals.

https://www.wbdg.org/dod/ufc/ufc-4-022-02

Bid Item

Description Major Scope Components

Base Bid

Section A: Existing Fence Reinforcing

Retrofit steel cable reinforcing ( cables @ $3/4\text{-in}$) on existing fence; install concrete deadman blocks spaced on the secure side.

Option

Section B: Install Anti- Vehicle Guardrail to Parking Entrance

Install new -cable steel guardrail barrier with minimum $2\text{ ft } 6\text{ in}$ concrete post footings conforming to AASHTO highway guidelines.

Option

Section C:

Replace/Relocate Existing Deadman Blocks (East Truck Rd & Generals Blvd)

Approximate Length

Approx.

1,000 LF

(Contractor to Field-Verify)

Approx. 150 LF (Contractor to Field-Verify)

Contractor to Field-Verify

Excavate and relocate existing concrete deadman blocks from the Attack side to the Secure side of the fence; structurally integrate with dual-cable specifications.

4. CONTRACTOR SAFETY & BASE ACCESS REQUIREMENTS

4.1 Base Access and Vetting

Otis ANGB is a secure Department of Defense facility. All operations must comply with current security protocols:

• DBIDS Enrollment: All contractor personnel requiring entry must be successfully vetted and obtain credentials via the Defense Biometric Identification System

(DBIDS).

• Background Clearances: Complete access authorization forms must be submitted to the 102 IW Security Forces Squadron at least fourteen (14) days prior to the planned start of work.

• Vehicle and Equipment Search: All commercial construction vehicles, tool trucks, and heavy equipment are subject to physical inspection at the commercial gate and random inspections while on base.

4.2 Safety and Accident Prevention

• Safety Program Compliance: The contractor must establish, submit, and enforce a site-specific Accident Prevention Plan (APP) conforming to OSHA (29 CFR 1926) and DAFI 91-202, The US Air Force Mishap Prevention Program (https://static.e-publishing.af.mil/production/1/af_se/publication/dafi91-202/dafi91-202.pdf).

• Job Hazard Analyses (JHA): Detail high-risk tasks such as high-tension cable tensioning, heavy concrete pours, and excavation around active areas.

5. ENVIRONMENTAL PROTECTION & SOLE SOURCE AQUIFER COMPLIANCE

5.1 Groundwater Protection

Otis ANGB is situated on the Joint Base Cape Cod (JBCC) cantonment area, directly overlying the Cape Cod Sole Source Aquifer. This aquifer is the sole source of drinking water for the surrounding communities, demanding strict environmental adherence:

• Zero-Tolerance Spill Policy: The contractor shall operate with a zero-tolerance policy for fuel, hydraulic fluid, oil, or chemical leaks onto the soil. Silt fences and protective barriers must be utilized during all excavation work.

• Dig Permits (AF Form 103): Before initiating excavation or drilling for fence posts/deadman blocks, the contractor must obtain an approved AF Form 103 Dig Permit to prevent interference with underground utility systems or groundwater monitoring networks.

5.2 Safety Data Sheet (SDS) Submittals

• Approval Authority: The contractor shall submit comprehensive Safety Data Sheets (SDSs) for all chemicals, concrete additives, curing compounds, lubricants, and fuels intended for use on the installation.

• Containment: Any approved hazardous substances stored on-site must be housed inside secondary containment systems capable of holding 110% of the total fluid volume.

6. PROPOSAL SUBMISSION & POINT OF CONTACT

6.1 Technical and Price Proposal Requirements

Bidders must submit separate Technical and Price volumes:

https://static.e-publishing.af.mil/production/1/af_se/publication/dafi91-202/dafi91-202.pdf https://static.e-publishing.af.mil/production/1/af_se/publication/dafi91-202/dafi91-202.pdf

1. Technical Proposal: Must include preliminary construction drawings, concrete and tensioning calculations, past performance on similar DoD crash-rated/high-tension cable projects, and a preliminary Environmental and Accident Prevention Plan.

2. Price Proposal: Must include a complete breakdown of material, labor, equipment, transport, storage, and GAOH, itemized separately for the Base Bid, Option 1, and Option 2.

7. DOCUMENT REFERENCES

• DoD Unified Facilities Criteria (UFC) Portal: https://www.wbdg.org/dod/ufc

• UFC 4-022-02 Selection and Application of Vehicle Barriers:

https://www.wbdg.org/dod/ufc/ufc-4-022-02

• DAFI 91-202, The US Air Force Mishap Prevention Program: https://static.e-publishing.af.mil/production/1/af_se/publication/dafi91-202/dafi91-202.pdf https://www.wbdg.org/dod/ufc https://www.wbdg.org/dod/ufc/ufc-4-022-02 https://static.e-publishing.af.mil/production/1/af_se/publication/dafi91-202/dafi91-202.pdf https://static.e-publishing.af.mil/production/1/af_se/publication/dafi91-202/dafi91-202.pdf