SPBN262010_RepaveRoadPaveGravelRoad_RFP.pdf
PDF 252 KB Posted
- Attached to
- ITB SPBN262010 Road Repaving (Otis ANGB, MA)
- Solicitation number
- BD-27-1069-MILDV-40000-133287
- Issued by
- Massachusetts
About this file
This Request for Proposal (RFP) is issued by the Department of the Air Force, 102D Civil Engineer Squadron at Otis Air National Guard Base in Joint Base Cape Cod, Massachusetts, under Solicitation Number SPBN262010. The procurement seeks competitive proposals from qualified heavy civil and paving contractors to perform road milling, subgrade stabilization, roadway construction, and thermoplastic striping on base roadways. The Base Bid involves repaving approximately 2,500 linear feet of the main base arterial road with an estimated total area of 60,000 square feet (6,667 square yards), requiring a heavy-duty 4.0-inch pavement system to support periodic heavy military vehicle loads. Add-Alternate Option 1 includes construction of approximately 260 linear feet of new pavement over an existing gravel road with an estimated total area of 6,240 square feet (693 square yards), which requires excavation and removal of degraded asphalt patches prior to subgrade preparation. The RFP emphasizes that all provided distances, areas, dimensions, and measurements are approximate estimates, and contractors are solely responsible for conducting on-site field investigations and independent measurements prior to submitting final proposals. The Government will not adjust contract values post-award due to contractor failure to verify actual site dimensions.
The RFP specifies that contractors must provide all labor, supervision, materials, transportation, traffic controls, and specialized pavement equipment necessary for project execution. Work requirements include submission of a detailed Maintenance of Traffic plan for approval prior to mobilization, asphalt milling to uniform depth of 4.0 inches, subgrade stabilization to 95% Modified Proctor density, installation of two-lift asphalt concrete paving (2.0-inch binder course and 2.0-inch surface course using Superpave specifications), and application of high-visibility thermoplastic markings compliant with MassDOT and MUTCD standards. All construction must comply with DoD Unified Facilities Criteria, UFC standards, and UFGS specifications. Critical environmental requirements include strict adherence to sole-source aquifer protection protocols with designated refueling zones, mandatory commercial spill kits, and stormwater runoff controls. Contractors must submit project-specific Accident Prevention Plans and Activity Hazard Analyses, comply with USACE Safety and Health Requirements, and ensure all personnel obtain Defense Biometric Identification System (DBIDS) credentials with applications submitted 14 business days prior to mobilization. All contractor personnel must undergo criminal background checks, and construction vehicles must enter through designated gates with physical inspection. The RFP does not specify response deadlines, contract award dates, or contract term information in the provided document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
102D INTELLIGENCE WING (ACC)
MASSACHUSETTS AIR NATIONAL GUARD
OTIS AIR NATIONAL GUARD BASE
DEPARTMENT OF THE AIR FORCE
102D CIVIL ENGINEER SQUADRON (102 CES) | 102D INTELLIGENCE WING
OTIS AIR NATIONAL GUARD BASE (ANGB), JOINT BASE CAPE COD, MA
REQUEST FOR PROPOSAL (RFP)
SOLICITATION NUMBER: SPBN262010
PROJECT TITLE: Road Repaving and Gravel Road Paving Construction LOCATION: Otis ANGB, Joint Base Cape Cod, MA
SECTION 1: GENERAL PROJECT INFORMATION
1.1 Project Objective
The 102d Civil Engineer Squadron (102 CES) is seeking competitive proposals from qualified heavy civil and paving contractors to perform road milling, subgrade stabilization, roadway construction, and thermoplastic striping on base roadways.
This solicitation is structured with a Base Bid and an Add-Alternate Option:
• Base Bid (Main Roadway): Repaving of approximately 2,500 linear feet of the main base artery road. This is a lower-traffic route but is subject to occasional heavy military utility, logistical, transport, and emergency vehicles. It requires a heavy-duty 4.0-inch pavement system to support these periodic heavy wheel-loads.
• Add-Alternate Option 1 (Gravel Road Paving): Construction of approximately 260 linear feet of new pavement over an existing gravel road. This gravel segment contains patches of degraded, existing asphalt that must be fully excavated, removed, and disposed of prior to new subgrade preparation.
1.2 Approximate Quantities & Contractor Verification Disclaimer
The estimated physical parameters for this contract are as follows:
• Base Bid (Main Roadway): Approximately 2,500 linear feet in length with an average width of 24 feet, generating an estimated total area of approximately 60,000 square feet (6,667 square yards).
• Add-Alternate Option 1 (Gravel Road): Approximately 260 linear feet in length with an average width of 24 feet, generating an estimated total area of approximately 6,240 square feet (693 square yards).
CRITICAL NOTICE TO OFFERORS: All distances, areas, dimensions, and measurements provided in this solicitation are approximate estimates. It is the sole responsibility of the contractor to conduct an on-site field investigation, perform independent measurements, and verify all physical site conditions, linear footage, slopes, elevations, and utility locations prior to submitting a final proposal. The Government will not adjust contract values post-award due to a contractor's failure to verify actual site dimensions.
SECTION 2: STATEMENT OF WORK (SOW) & TECHNICAL SCOPE
The Contractor shall provide all labor, supervision, materials, transportation, traffic controls, and specialized pavement equipment necessary to execute the project.
2.1 BASE BID: Main Roadway Repaving (Approx. 2,500 LF)
Phase I: Site Setup and Maintenance of Traffic (MOT)
1. Traffic Control Plan: The contractor shall submit a detailed Maintenance of Traffic (MOT) plan to the 102 CES Project Manager (PM) for approval prior to mobilization.
2. Lane Management: Because the road is a lower-traffic arterial route, the contractor may utilize alternating single-lane traffic configurations or full road closures with pre-approved detour routes to accelerate construction.
3. Safety Devices: All signage, barricades, and electronic message boards must comply with the Federal Highway Administration (FHWA) Manual on Uniform Traffic Control Devices (MUTCD), accessible online at: (https://mutcd.fhwa.dot.gov)
4. Emergency Vehicles: Uninterrupted emergency vehicle access must be maintained at all times.
Phase II: Asphalt Milling and Subgrade Prep
1. Asphalt Milling: Mill the existing deteriorated asphalt layer to a uniform depth of 4.0 inches across the entire project alignment.
https://mutcd.fhwa.dot.gov/
2. Debris Hauling: All milled asphalt debris (Reclaimed Asphalt Pavement / RAP) is the property of the contractor and must be hauled off-base and legally disposed of in accordance with environmental regulations.
3. Subgrade Inspection: Following milling, the contractor and the 102 CES PM shall visually inspect the exposed subgrade. Any localized subgrade soft spots or structural failures must be excavated, backfilled with clean gravel aggregate, compacted to 95% Modified Proctor density, and proof-rolled.
Phase III: Asphalt Concrete Paving (Heavy Loading Spec)
The new pavement structure must be installed in two distinct, high-durability lifts:
1. Tack Coat: Apply an emulsified asphalt tack coat to the prepped subgrade or milled interface to ensure a strong structural bond.
2. Binder Course: Lay and compact a 2.0-inch thick (finished depth) Asphalt Binder Course (Superpave intermediate mix, nominal maximum aggregate size of 19 mm or MassDOT equivalent).
3. Surface Course: Lay and compact a 2.0-inch thick (finished depth) Asphalt Surface/Wearing Course (Superpave surface mix, nominal maximum aggregate size of 12.5 mm or MassDOT equivalent), resulting in a total compacted HMA thickness of 4.0 inches.
4. Grading & Slopes: Establish a standard 2.0% crown or cross-slope to ensure rapid surface drainage and prevent hydroplaning or standing water.
Phase IV: High-Durability Markings
1. Cure Time: Allow the new asphalt surface to cure for a minimum of 7 to 14 days before applying permanent markings.
2. Temporary Paint: Apply temporary fast-drying waterborne reflective paint immediately after paving to maintain safe traffic flow.
3. Permanent Thermoplastic: Apply high-visibility, retroreflective thermoplastic markings in accordance with MassDOT and MUTCD standards. Striping tasks include:
o Double-solid yellow center lines (approximately 2,500 linear feet).
o White outer fog lines (approximately 5,000 linear feet).
o Solid white stop bars and directional arrows at intersections.
2.2 ADD-ALTERNATE OPTION 1: Gravel Road Paving (Approx. 260 LF)
Phase I: Asphalt Demolition & Excavation
1. Asphalt Removal: Locate, excavate, and break up all degraded asphalt patches embedded in the existing gravel roadway.
2. Disposal: All demolished asphalt material must be collected, loaded, hauled off-base, and legally disposed of by the contractor.
3. Rough Grading: Excavate and rough-grade the existing gravel base to accommodate a new 4.0-inch thick asphalt pavement profile while maintaining flush transitions to connecting roadways.
Phase II: Subgrade Compaction & Base Prep
1. Base Assessment: Proof-roll the existing gravel base using a minimum 10-ton vibratory roller to identify soft spots.
2. Compaction: Compact the gravel subgrade base to a minimum of 95% Modified Proctor density. Ensure the base has proper pitch (1.5% to 2.0% cross-slope) to shed water off the roadway surface.
3. Stabilization: Apply a bituminous prime coat over the prepared gravel base prior to laying asphalt to prevent base moisture migration.
Phase III: Asphalt Paving (Heavy Loading Spec)
The road paving must match the heavy-duty two-lift roadway specification:
1. Binder Course: Lay and compact a 2.0-inch thick (finished depth) Asphalt Binder Course (Superpave intermediate mix, nominal maximum aggregate size of 19 mm or MassDOT equivalent).
2. Surface Course: Lay and compact a 2.0-inch thick (finished depth) Asphalt Surface/Wearing Course (Superpave surface mix, nominal maximum aggregate size of 12.5 mm or MassDOT equivalent), resulting in a total compacted asphalt depth of
4.0 inches.
3. Shoulder Backing: Install compacted dense gravel shoulder backing (minimum 12 inches wide) along the uncurbed edges of the new road to prevent edge-cracking and wheel-drop hazards.
Phase IV: Markings
1. Permanent Thermoplastic: Striping tasks for this segment include solid white outer fog lines (approximately 520 linear feet) and double-yellow center lines (approximately 260 linear feet) to match MUTCD guidelines.
SECTION 3: GOVERNING CODES, STANDARDS, & REFS
All design and construction must comply with the most up-to-date versions of the following criteria:
• DoD Unified Facilities Criteria (UFC) Public Library:
(https://www.wbdg.org/dod/ufc)
• DoD General Building Code: UFC 1-200-01 DoD Building Code (https://www.wbdg.org/dod/ufc/ufc-1-200-01)
• Pavement Design Standard: UFC 3-250-01 Pavement Design for Roads and Streets (https://www.wbdg.org/dod/ufc/ufc-3-250-01)
• Unified Facilities Guide Specifications (UFGS) Pavement Markings: UFGS 32 17
23.16 Athletic, Pavement and Runway Markings
(https://www.wbdg.org/ffc/dod/ufgs/ufgs-32-17-23.16)
• Air Force Corporate Facility Standards (AFCFS): AFCFS Pavement and Site Details Guide (https://afcfs.wbdg.org)
SECTION 4: ENVIRONMENTAL PROTECTION AND POLLUTION PREVENTION
4.1 Sensitive Sole-Source Aquifer Protection
Otis ANGB and Joint Base Cape Cod (JBCC) are located directly above the Cape Cod sole-source aquifer, which is highly vulnerable to surface contamination. The contractor shall strictly adhere to environmental regulations to prevent groundwater contamination:
1. Refueling Zones: Equipment refueling, maintenance, and fluid changes are strictly prohibited within the project alignment. All refueling must occur in designated, impermeable containment areas approved by the 102 CES Environmental Office.
2. Spill Response: The contractor must maintain commercial-grade spill kits on-site at all times during active construction. In the event of any petroleum, fuel, or chemical spill, the contractor shall immediately halt work, initiate containment, and notify the 102 CES PM and JBCC Fire Department.
https://www.wbdg.org/dod/ufc https://www.wbdg.org/dod/ufc/ufc-1-200-01 https://www.wbdg.org/dod/ufc/ufc-3-250-01 https://www.wbdg.org/ffc/dod/ufgs/ufgs-32-17-23.16 https://afcfs.wbdg.org/
3. Environmental Standards: Contractors must comply with the Joint Base Cape Cod Environmental Management Commission (EMC) Environmental Performance Standards, which can be referenced online at: (https://www.mass.gov/service-details/environmental-management-commission-emc)
4.2 Stormwater Runoff Control (SWPPP)
1. Inlet Protection: The contractor shall install sediment filter inserts, hay bales, or geotextile fabric covers over all adjacent stormwater catch basins, drainage ditches, and curb inlets prior to starting milling, excavation, or paving operations.
2. Milling Dust Mitigation: Power sweepers must utilize active water-spray dust suppression systems during all milling and sweeping operations to prevent dust and fine particulates from entering the atmosphere or nearby drainage channels.
3. Erosion Controls for Excavation: For the gravel road paving option, the contractor shall place sediment socks or silt fencing along unpaved slopes to contain run-off during excavation and grading phases.
4.3 Asphalt Milling & Waste Management
1. Off-Base Disposal: All milled asphalt (RAP) and demolished asphalt patches must be hauled off-base and disposed of at a licensed commercial recycling facility.
Dumping or unauthorized stockpiling of asphalt waste on military property is strictly prohibited.
2. Regulations: Scrap asphalt disposal must follow MassDOT Solid and Hazardous Waste Management guidelines, found online at:
(https://www.mass.gov/lists/massdot-environmental-handbooks-and-guidance-manuals)
SECTION 5: CONTRACTOR SAFETY & BASE ACCESS
5.1 Safety Mandates
1. Safety Standard: All construction activities must comply with the USACE Safety and Health Requirements Manual, EM 385-1-1 (https://www.publications.usace.army.mil/portals/76/publications/engineermanual s/em_385-1-1.pdf) and UFGS 01 35 26 Governmental Safety Requirements (https://www.wbdg.org/dod/ufgs/ufgs-01-35-26).
https://www.mass.gov/service-details/environmental-management-commission-emc https://www.mass.gov/service-details/environmental-management-commission-emc https://www.mass.gov/lists/massdot-environmental-handbooks-and-guidance-manuals https://www.mass.gov/lists/massdot-environmental-handbooks-and-guidance-manuals https://www.publications.usace.army.mil/portals/76/publications/engineermanuals/em_385-1-1.pdf https://www.publications.usace.army.mil/portals/76/publications/engineermanuals/em_385-1-1.pdf https://www.wbdg.org/dod/ufgs/ufgs-01-35-26
2. Submittals: The contractor must submit a project-specific Accident Prevention Plan (APP) and Activity Hazard Analysis (AHA) to the 102 CES Safety Officer for approval prior to mobilization.
3. Personal Protective Equipment (PPE): All personnel within the work zone must wear ANSI Class II/III high-visibility safety vests, steel-to-toe boots, hard hats, and safety glasses.
5.2 Base Access Protocols
1. Credential Vetting: All contractor personnel must undergo criminal background checks to obtain Defense Biometric Identification System (DBIDS) credentials.
Contractor Access Applications must be submitted 14 business days prior to mobilization. Detail on DBIDS can be found online at:
(https://www.cnic.navy.mil/om/dbids.html)
2. Commercial Vehicle Gate: All construction vehicles and equipment deliveries must enter through the vehicle search area (Gibbons Gate) for physical inspection.
Drivers must present a valid Commercial Driver’s License (CDL), vehicle registration, and active commercial insurance.
3. Escort Requirements: Un-vetted personnel or delivery drivers who do not possess DBIDS credentials must be escorted by a badged contractor representative at all times.