SP7000-24-Q-0014 00001.pdf

PDF 655 KB Posted

Attached to
Assembly of Shelving Racks Federal contract opportunity
Solicitation number
SP7000-24-Q-0014
Issued by
Defense Logistics Agency

About this file

This document is an amendment to a federal solicitation, SP7000-24-Q-0014, for the assembly of shelving racks. The amendment extends the closing date for offers to June 24, 2024 at 2:00 PM. It also provides responses to 22 questions related to the work, including details on the size and specifications of the existing and new racking system, required equipment, and availability of site visits. The original solicitation is for a one-time requirement to remove and install a new racking system for the Defense Logistics Agency (DLA) within 30 days of award. The scope includes removing 54 cross beams and 10 uprights, installing 10 new uprights, 72 cross beams, and wire decking on the bottom two rows. The new racking materials have been purchased and are on-site, except for the bolts needed to secure the uprights to the floor.

View the file

Other files for this federal contract opportunity

Other files attached to Assembly of Shelving Racks, newest first.
File Type Posted
SP7000-24-Q-0014 0002.pdf PDF
Photo-7.jpg JPG image
Photo-9.jpg JPG image
Photo-11.jpg JPG image
Photo-8.jpg JPG image
Photo-12.jpg JPG image
Photo-3.jpg JPG image
Photo-6.jpg JPG image
Photo-5.jpg JPG image
Photo-2.jpg JPG image
Photo-1.jpg JPG image
Photo-10.jpg JPG image
Photo-4.jpg JPG image
Attachment 2 - PERFORMANCE WORK STATEMENT.pdf PDF
Attachment 3 - Procurex Reverse Auction Instructions.pdf PDF
SP7000-24-Q-0014.pdf PDF
Attachment 1 - Full Text Provisions (Vendor COMPLETION Required).pdf PDF
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION

NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

CONTINUATION SHEET REFERENCE NO. OF DOCUMENT BEING CONTINUED:

SP7000-24-Q-0014 0001

PAGE 2 OF 2 PAGES

The closing date of SP7000-24-Q-0014 is extended to 24 June 2024 at 14:00.

1) What is the height of the uprights? 25 ft (H) x 4 ft (D)

2) What is the length of the beams? 9 ft

3) Is a scissor lift needed? Yes, scissor lift would be recommended.

4) Is a forklift needed? Yes

5) Will ladders be sufficient for installation? Scissor lift would be recommended due to the height of the racks.

6) Do ladders, forklifts, and scissor lift need to be provided or are they on site to be used? They will need to be provided.

7) What size are the old uprights? 25 ft (H) x 3 ½ ft (D)

8) What size are the old beams? 9 ft

9) What size are the new uprights? 25 ft (H) x 4 ft (D)

10) How many shelf levels is each bay? 4

11) How much weight does each shelf level need to hold? 1200 LBS

12) Can you provide picture or layout of old system? See attached

13) Can you provide picture or layout of new system? The new layout will mirror the previous layout.

14) Does the offeror need to include procurement of new racking materials, or will it be provided? The new racking material has been purchased and is on-site (minus bolts for uprights to floor).

15) Are there drawings and pictures of the work area available? See attached.

16) What does the area look like? See attached.

17) Are site visits available? Yes, we can schedule a site visit M-F from 0700 to 1400 CST.

18) What size cross beams and uprights are required to be demolished? Uprights are 25 ft (H) x 3 ½ ft (D) and cross beams are 9 ft wide.

19) What size uprights, cross beams, and wire decking are being installed? Uprights to be installed are 25 ft (H) x 4 ft

(D). Same cross beams need to be installed.

20) Will equipment be needed to demo and install? Yes

21) What material is being installed and demolished? DLA material is to be taken down and installed.

22) What are the manufacturer’s guidelines for installation? Uprights and cross beams have been purchased through

Granger and Uline. The uprights were manufactured by Husky Rack and Wire

SF30 AMEND
SF1449
topmostSubform[0]:
Page1[0]:
AmendmentNo[0]: 00001
Code[0]: SP7000
Code[1]:
AccountingData[0]: N/A
A13[0]:
C13[0]:
D13[0]:
NameandTitleSigner[0]:
NameandTitleOfficer[0]: TINA M. GRUJIC
Description[0]: The purpose of this amendment is to extend the closing date of solicitation SP7000-24-Q-0014 and provide responses to all the questions received.
FacilityCode[0]:
Code[2]: SP7000
IssuedBy[0]: DCSO-PH HARRISBURG

5404 J AVE BLDG 404

NEW CUMBERLAND PA 17070-5059

NameandAddress[0]:
AdministeredBy[0]: David Purvis

david.1.purvis@dla.mil

ContractIDCode[0]: SP7000-24-Q-0014
ReqNumber[0]:
AmendmentNo[1]: SP7000-24-Q-0014
ModificationNo[0]:
ProjectNo[0]:
Page[0]: 1
Pages[0]: 2
EffectiveDate[0]: 12 June 2024
Dated9B[0]: 06/01/2024
Dated10B[0]:
CheckBox9[0]: 1
CheckBox10[0]: Off
CheckBox11[0]: 1
CheckBox13A[0]: Off
CheckBox13B[0]: Off
CheckBox13C[0]: Off
CheckBox13D[0]: Off
IsNot[0]: Off
Is[0]: 1
Extended[0]: 1
NotExtended[0]: Off
2024-06-11T14:29:00-0400
GRUJIC.TINA.M.1049385729
DateSigned[0]:
DateSigned[1]: 6/11/24
Copies[0]: 1
CopiesReturned[0]: 1

File details come from the government source that posted it. Updated .