QA_Matrix_B98CeilingStripping.xlsx

XLSX spreadsheet 19 KB Posted

Attached to
DSCR Building 98 Paint Stripping
Solicitation number
SP470326Q0009
Issued by

About this file

The file is a Question and Answer (Q&A) Matrix for a federal solicitation for lead-paint stripping services at Defense Supply Center Richmond (DSCR) Building 98. The solicitation (SP470326Q0009) is a Request for Quote (RFQ) set aside for small businesses in the Toxic Chemical Remediation industry, with a NAICS code of 562910 and a size standard of 1,000 employees. The contract will be a firm-fixed price award with a 120-day period of performance, expected to be funded in FY26.

Key details include a site visit scheduled for December 2, 2025, at 10 am, with questions due by December 5, 2025, and quotes due by December 12, 2025. The Q&A matrix addresses specific technical questions about the project, including confirmation that paint stripping is limited to ceiling surfaces, clarification on equipment to remain in place, ceiling height (25-26 feet), and workspace occupancy status. The award will be made to the lowest-priced, technically acceptable offeror, with contractors required to be within a 120-mile radius of DSCR and registered in the System for Award Management (SAM).

View the file

Other files

File Type Posted
QA_Matrix_B98CeilingStripping.xlsx XLSX spreadsheet
Photos.zip ZIP file
SF1442_SP470326Q0009.pdf PDF
Attachment 1 - SOW.pdf PDF
Attachment 2 - Wage Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

QuestionFileSectionQuestionGovernment ResponseResponse from:
1Rafters and Purlins
Please confirm whether the rafters and purlins are included within the scope of ceiling lead-paint stripping, or if the work is limited only to the primary ceiling surfacesNo, the stripping of paint will be restricted to solely the ceiling.
2Equipment to Remain and Be Covered

The SOW notes that equipment not removed from the building shall be covered to prevent exposure to lead.

Could you please specify which existing equipment is expected to remain in place and must be protected?The existing metal shelving, the metal cage, the implant rooms (bathroom, office, communication room), and the desk will remain in the building.
3Structure Above In-Plant Buildings / Access and Safety
There appears to be a structure on top of the in-plant buildings within Building 98. Please clarify what this structure consists of and advise whether it is designed to support worker access and can be used as a walking/working surface, or if it should be treated as not structurally safe for laborers to walk on.The three implant rooms (bathroom, office, communication room) do seem to have a ceiling that can be utilized as a walking surface. Please see attached photos.
4Ceiling Height
Please provide the approximate average ceiling height for the areas included in the scope, and if available, the range of minimum and maximum heights.The height of the ceiling is uniform throughout the building, for the most part. It ranges from roughly 25' to 26'.
5Please provide the Photos21 photos will be uploaded to SAM
6Will the room be vacant for the work?The room will not be vacant. But fortunately, all the content that can be moved will be moved to whichever section the contractor is not working on; the contractor would have to section off whatever area they are working in.
7
8
9
10

File details come from the government source that posted it. Updated .