Revised Section 01 11 00 Summary of Work
View the file
Other files for this federal contract opportunity
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01 11 00 Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
10/18
PART 1 GENERAL
1.1 SUBMITTALS
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
1.2.2 Location
1.3 CONTRACT DRAWINGS
1.4 WORK RESCHEDULING
1.5 OCCUPANCY OF PREMISES
1.6 EXISTING WORK
1.7 ON-SITE PERMITS
1.7.1 Utility Outage Requests and Utility Connection Requests
1.7.2 Borrow, Excavation, Welding, and Burning Permits
1.8 LOCATION OF UNDERGROUND UTILITIES
1.8.1 Notification Prior to Excavation
1.9 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
1.9.1 Delivery Schedule
1.9.2 Delivery Location
1.10 GOVERNMENT-INSTALLED WORK
1.11 NAVY AND MARINE CORPS (NMCI) COORDINATION REQUIREMENTS
1.11.1 NMCI Contractor Access
1.12 SALVAGE MATERIAL AND EQUIPMENT
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 11 00 Page 2
SECTION 01 11 00
SUMMARY OF WORK
07/2019
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals G
Utility Outage Requests
Utility Connection Requests
Borrow Permits
Excavation
Permits Welding
Permits Burning
Permits
Salvage Plan;
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The contractor shall furnish all plant, labor, equipment, materials, supplies and supervision required in performing all operations to perform the following maintenance and repair work to complete this project:
• Replacement of total (30) exterior and interior doors, frames, handicapped operators, closures & other hardware in vestibule and kitchen walls of Pods A, B & C in Building 20 (DSCC);
• Replacement of total (10) exterior doors, frames, handicapped operators, closures & other hardware in vestibule walls of Pods A, B & C in Building 21(DFAS);
• Contractor shall remove all magnetic and electronic security devices, wires and electronic devices from
SECTION 01 11 00 Page 3 existing doors & framing systems prior to deconstruct existing doors and framing systems.
• Contractor shall reinstall all magnetic and electronic security devices, wires and electronic devices to new doors & framing systems.
• Contractor shall perform tests to ensure proper operation of all handicapped operators and electromagnetic lock devices.
• The contractor shall perform all operations in conjunction with this project in strict accordance with specifications & revised drawings # 3-1689, sheets 1 through 5, dated July 23, 2019.
1.2.2 Location
The work is located in Building 20 (DSCC) & 21 (DFAS) at the DSCC Complex, Columbus, Ohio. The approximate location is shown on the drawings.
1.3 CONTRACT DRAWINGS
The following drawings accompany this specification and are a part thereof.
Drawing No. 3-1689
Sheets 1 through 5
Electronic set of contract drawings, maps, and specifications will be furnished to the Contractor without charge. Reference publications will not be furnished. Immediately check furnished drawings and notify the Government of any discrepancies.
1.4 WORK RESCHEDULING
Normal duty hours for work are from 7:00 A.M. to 4:00 P.M., Monday through Friday. Requests for additional work requires written approval from the Contracting Officer 7 days in advance of the proposed work period.
1.5 OCCUPANCY OF PREMISES
NOT USED
1.6 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury
SECTION 01 11 00 Page 4 or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.7 ON-SITE PERMITS
1.7.1 Borrow, Excavation, Welding, and Burning Permits
1.8 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities. Verify existing utility locations indicated on contract drawings, within area of work.
1.8.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work.
1.9 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
NONE
1.10 GOVERNMENT-INSTALLED WORK
NONE.
1.11 NAVY AND MARINE CORPS (NMCI) COORDINATION REQUIREMENTS
1.12 SALVAGE MATERIAL AND EQUIPMENT
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --