Questions and Answers 1 to 19
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_0002_to_SP453016R0001.pdf | ||
| Amendment_0001_to_SP453016R0001.pdf | ||
| Attchmt_01_-_Schedule_of_Prices_PROPOSAL_SHEET_-_REVISED_4-22-16.xlsx | XLSX spreadsheet | |
| RFP_SP453016R0001_pgs_1_to_99.pdf | ||
| Attchmt_13_Facility_Profile_Sheet.docx | DOCX document | |
| Attchmt_14_Transportation_Profile_Sheet.docx | DOCX document | |
| Attchmt_01_-_Schedule_of_Prices_PROPOSAL_SHEET.xlsx | XLSX spreadsheet | |
| Attchmts_2_to_21_except_13_and_14.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT NO. 0001 SP4530-16-R-0001
Japan Scrap
No. CONTRACTOR QUESTION GOVERNMENT ANSWER
1 There is an indication about the container in the Performance Work Statement. (a) Section 3.0 para 3.1, any specific type (size, material etc.) is preferred? (b) Or any type is good if the container is covered at all times to prevent rainwater/snow?
(a) No, no specific type is preferred.
(b) Any type of container is acceptable as long as it can be covered at all times to prevent the collection of rainwater and/or snow.
2 Does the contractor provide all needed tools and consumable supplies? Yes.
3 (a) When the contractor provides all needed tools and consumable supplies, can the contractor claim the cost for them? (b) Or do we need to include all cost in the CLIN 0001MA?
(a) and (b) Yes, the contractor may claim their cost for tools and consumable supplies by including the costs in the management of scrap collection site CLIN (i.e. CLIN 0001MA for Misawa).
4 (a) Can we carry in our heavy equipment (e.g. backhoe) to perform our work?
(b) Is there anything we can’t bring in?
(a) Yes.
(b) Coordination with the local POC/COR may be required for specialized equipment.
5 The law of waste disposal has revised, and it is said that prime contractor must have permission of the applicable prefecture’s collection transportation work as for the prime contractor even we appoint subcontractor. Does the prime contractor need to have a permission of the collection transportation work from Aomori prefecture for this project?
In accordance with PWS Section 5.0, the contractor shall comply with all Japan national, prefectural and local environmental laws and regulations governing the requirements of this contract. It is the prime contractor's responsibility to check with the Aomori prefecture regulatory office.
6 PWS 27.4 Time of Performance: Holidays (Page41):
Could we take both national holidays for the new terms?
In the current contract, we can take only US national holidays.
Please clarify these differences.
Yes, both U.S. and Japan national holidays are observed. The U.S. and Japan national holidays are listed in PWS Section 27.4. The contractor may adjust the Japanese national holiday schedule as described in the last paragraph of 27.4.
7 PWS 1.5 Contractor Responsibilities (Page 16 & 17):
(c) At DLA Okinawa/Sagami provision shows that US Government is responsible for xxxxx for placing materials into contractor-provided containers. We propose that the provision should indicate "both Government personnel and contractor may place materials into containers" because we, contractor sometimes place materials into the containers by ourselves in case that we hasten to carry them during time constraint.
(i) shows same condition, therefore, please consider that above proposal in this provision.
A sentence will be added to PWS Section 1.5(c) and 1.5(d)(i) which states, "The contractor may place materials into contractor-provided containers with prior approval from the COR."
QUESTIONS AND ANSWERS
SP4530-16-R-0001, JAPAN SCRAP
No. CONTRACTOR QUESTION GOVERNMENT ANSWER
QUESTIONS AND ANSWERS
SP4530-16-R-0001, JAPAN SCRAP
8 PWS 7.2 Off Site Demil/Deman (Page 25):
We acknowledge DEMIL/DEMAN is performed at on site and off site work.
However, the clin corresponding to the work is only one item.
We request you to create two clins for on-site and off-site. It would be better to separate price by each and you would take profit in case of on-site.
Otherwise, you may owe additional cost (transport fee) even in on-site work.
Majority of Demil and Deman work will be performed by the contractor at a DLA Disposition Services collection site. On occasion, Demil or Deman work may be requested by DLA to be performed at a FCS. The Demil and Deman CLINs (i.e. 0044_B and 0043_D) include the cost for Demil and Deman work performed at a FCS within 100 km radius of the appropriate DLA Disposition Services collection site. Refer to PWS Section 7.1(b). A sentence will be added to 7.1(b) which states, "The contractor may request for a new negotiated CLIN for Demil or Deman work requested outside of the 100 km radius."
9 Schedule of Price:
-(a)Iwakuni Base Period and 2nd Option Period indicate 002IA A06 Cardboard, but 1st Option Period does not show the clin. Please clarify it.
-(b) Regarding to 013OA Stainless Steel Scrap-SCL S00, the estimated quantity for Base/1st and 2nd is different. Base/1st is 50,000lbs but 2nd option is 5,000lbs. Is it correct?
-(c) Quantity for some clins are different between each period. 026OA is 17,000lbs in Base but 25,000lbs in 2nd. There seems to be same situation in other clins. Please make sure if it is correct number or not.
Estimated order quantities vary for certain CLINs in different ordering periods, particularly for Forward Collection Sites. Estimated order quantities are based on Site POC forecasts.
10 Do you have any entry example of Standard From 1449 or easy-to-understand guidance?
(We suppose to complete blocks 12, 17, 23, 24, & 30,)
a) What is the “DISCOUNT TERM”?
b) Do we have to entry all bid items in section 19 through 24?
Guidance: On Standard Form 1449, the offeror shall complete only Blocks 12, 17 and 30. Do not complete Blocks 23 and 24.
(a) Discount Term refers to any discount offered for early payment of invoices. See FAR 52.212-4(i) PAYMENT located on page 49.
(b) No. Leave Blocks 19 to 24 blank.
11 Definition About CLlN No.07 (Copper wire & Cable clean) Actual “Ichigoudousen(Pika) “ is No.1 in the attached file “Copper-Related Types” therefore, we suggest changing the expression of “Ichigoudousen (Pika) it can be misunderstand the definition of copper types.
There is no exact index in the Shigen Shinpou publication for CLIN 0007, Insulated Copper Wire and Cable. DLA has chosen the "Ichigoudousen (Pika)" index rate to represent CLIN 0007.
Contractors shall take this into consideration when submitting their proposed unit price for CLIN 0007.
12 There is a possibility that Industrial waste treatment law is applied about television in Okinawa near future, when presenting the cost of television, whether you are sure you want presented better in consideration of the fact?
This is a firm-fixed-price contract for 18 months with the possiblity of two additional 18-month option periods. The unit prices proposed by the contractor for each 18-month period will be fixed once the contract is awarded. It is the contractor's decision on how they want to strategize their unit pricing.
No. CONTRACTOR QUESTION GOVERNMENT ANSWER
QUESTIONS AND ANSWERS
SP4530-16-R-0001, JAPAN SCRAP
13 Description SF1449 (pages 1 to 99) Page on 79 about the ORCA website, is it actually the System for award Management (SAM) instead ORCA?
Yes. SAM consolidated the capabilities of various separate applications, one of which was the Online Representations and Certifications Application
(ORCA).
14 In Industrial waste treatment law, Business who was discharged industrial waste, industrial waste was discharged as a general rule but must be treated with their own responsibility, if you can not own processing, the processing skilled in the art that have the permission of the industrial waste processing industry you can entrust the processing.
If the discharge operators entrust the processing of industrial waste, there are rules that must be followed. This is called the rule a consignment basis. The consignment basis, entered into and of exhaust operators contract that clarifies the industrial waste treatment company and each other's roles and responsibilities of contractors, as industrial waste is properly transport of contract, industrial waste or stroke have been disposed of we like to see by using things management form the (manifest) has obliged.
It should be noted that, until the industrial waste discharge operators which was discharged in the business field is transportation, industrial waste or scattered in accordance with the storage criteria, there is a take measures obligation that does not have bad smell.
According to Industrial waste treatment law, we suggest that contractor (we) should:
a) Issue of manifest contractor is paid
b) Fill in the contractor's name and address to business entry column. (There is no problem because the industrial waste to be handled in the field of contractor.)
By that, it can be entrusted to the collection and transportation of skill in the art, as well as industrial waste disposer skilled in the art without violating the law.
Question is: Is it possible to change as a) and b)?
Please continue to use the appropriate DLA Disposition Services site name in the block on the manifest for the Activity Name of the Originator and the appropriate military installation name in the block on the manifest for the Activity Name of the Industrial Waste Location.
15 About CLIN P7100J:
We have already had the liability insurance and occupational accidents comprehensive insurance. Do we need to put the unit price on CLIN P7100J?
Yes, offerors must include a unit price (or percentage for CAT 1 CLINs) for every CLIN in the Schedule of Prices they propose on. Refer to PWS Section 30.0 for information on Defense Base Act Insurance.
No. CONTRACTOR QUESTION GOVERNMENT ANSWER
QUESTIONS AND ANSWERS
SP4530-16-R-0001, JAPAN SCRAP
16 About Forward collection site:
It is difficult to decide the fixed unit price for forward collection site. Some item needs rough terrain crane or other heavy equipment to loading items. We think that it requires certain conditions in setting a fixed unit price.
a) How much the size of the maximum item we have to pick up from forward collection site?
b) How much weight at the maximum we have to pick up?
c) Are there any suggestions you can give to contractor?
For example, need re- estimate if the item is over4,400 LBS.
In accordance with PWS Section 2.3, FCS Tengan Anchorage may require heavy lift equipment to break down items into its basic content and to transport. Other FCSs will rarely require heavy lift equipment. Majority of material from FCS Tengan Anchorage will be rubber hoses, consisting of 75% rubber and 25% metal/steel.
(a) Rubber hoses could weigh as much as 3,400 lbs.
Contractor-supplied crane and ability to cut the rubber hoses into shorter lengths to fit onto their trucks may be required. Contractor shall take this into consideration when submitting their unit prices for FCS Tengan Anchorage CLINs.
(b) Actual weight depends on how much scrap FCS Tengan Anchorage generates.
(c) Contractor shall work with the COR to schedule reasonable-sized pick-ups.
17 Total amounts of two categories(positive and negative) for each period It indicates the amount on the bottom line of each period of schedule of price by calculating category1 + category2. But the amount does not show the correct amount because category2 includes some positive items such as vehicles (CLIN No.036xx).
These positive amounts should be removed from category2 and added to category1, then the correct balance of positive and negative group would be shown on the list.
Please consider the figure.
Category 1 CLINs are for items with a Shigen Shinpou Index rate, therefore, the unit price will always be positive. Category 2 CLINs are for all other items, therefore, the unit price could be positive or negative depending on what the offeror wants to propose.
When entering a positive unit price for a Category 2 CLIN, you must enter ity with a negative sign "-" in front of the number. For example, if you want to propose a unit price of positive 100 yen, you must enter -100. All positive amounts should end up being red font in color. Negative amounts are black.
Refer to PWS Section 1.3(h)(1) and (2).
18 Regarding clin no.2002SA for A06 Cardboard in 2nd option period of Sagami Yard, the column of index and total amount do not change even if we input % of index while other clins are well.
It seems to be freezed or locked. Please check it.
Thank you for bringing this to our attention. There was a formula error for CLIN 2002SA. A corrected Schedule of Prices PROPOSAL SHEET will be provided.
Sheet1