SP3300-27-Q-0011 - Amendment 0001.docx

DOCX document 47 KB Posted

Attached to
Cross Connection Hazard Assessment
Solicitation number
SP330027Q0011
Issued by

About this file

This is Amendment 0001 to Request for Quote SP330027Q0011, issued by the Defense Logistics Agency (DLA) Distribution on November 16, 2026, extending the quote deadline and adding supporting documentation and clarifications.

The solicitation requires a Cross Connection Hazard Assessment for the DLA Distribution facility in San Joaquin, California. The scope includes evaluating approximately 55 backflow prevention devices across approximately 43 buildings to assess cross-connection control hazards in accordance with California's Cross-Connection Control Policy Handbook. Work must be performed by a Certified Cross-Connection Control Program Specialist meeting AWWA requirements. Key deliverables include a draft Hazard Assessment report due March 1, 2027, and a final report due April 30, 2027, with the overall period of performance from December 14, 2026, through June 14, 2027. The assessment is limited to inspection, records review, and hazard assessment; backflow prevention assemblies are tested annually by certified testers, with results provided upon award. Contractor personnel will be escorted by knowledgeable facility representatives during onsite work, with access restricted to 8:00 AM–3:00 PM, Monday through Friday, with 24-hour notice required. A site visit is scheduled for December 2, 2027, at 9:00 AM PST. All quotes must be submitted electronically to Thomas.semones@dla.mil with subject line "SP330027Q0011 Quotation - [Company Name]" by 12:00 PM Eastern Standard Time on December 7, 2026. Amendment 0001 adds Attachment 1 (Schedule of Supplies or Services and Prices), Attachment 2 (Performance Work Statement), Attachment 3 (Wage Determination 2015-5653, Rev. 28), and Attachment 4 (Deliverables Schedule). DFARS cybersecurity requirements including CMMC Level 1 apply, and deliverables must include appropriate CUI markings where applicable.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SP330027Q0011

Amendment 0001

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

PAGE
1 of 7
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
4. REQUISITION/PURCHASE NO.
5. PROJECT NO. (If applicable)
0001
11/16/2026
6. ISSUED BY
CODE
SP3300
7. ADMINISTERED BY (If other than Item 6) CODE

DEFENSE LOGISTICS AGENCY

DLA DISTRIBUTION

430 MIFFLIN AVENUE, SUITE 3102A

NEW CUMBERLAND, PA 17070-5007

POC: Tom Semones, Thomas.semones@dla.mil

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code)

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

SP330027Q0011

CODE:
FACILITY CODE:
X
10B. DATED (SEE ITEM 13)

11/6/2026

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15 and returning 1 copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A
THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
B
THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C
THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D
OTHER (Specify type of modification and authority.

E. IMPORTANT: Contractor is not, X is required to sign this document and return 1 copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

SEE ATTACHED PAGES

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15a. NAME AND TITLE OF SIGNER (Type or print)
16a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
15C. DATE SIGNED
16B. UNITED STATES OF AMERICA
16C. DATE SIGNED

BY_________________________________________

BY_________________________________________

(Signature of person authorized to sign)

(Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITION NOT USABLE

30-105
STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

1. The purpose of this amendment is to provide answers to vendor questions, extend the due date for quotes and add a site visit.

2. Amendment 0001 is hereby incorporated into Request for Quote SP330027Q0011 and shall become a part of any resultant contract.

3. Vendors are advised to review all revised documents.

4. SP330027Q0011, Addenda to FAR 52.212-1. Page 12, Paragraph 1 is revised as follows:

FROM:

1. All quotes must be received electronically via email at: Thomas.semones@dla.mil, Subject: SP330027Q0011 Quotation – “Quoter’s Company Name.” Quotations must be received by 12:00 PM Eastern Standard Time on November 23, 2026 to be considered for award.

TO:

1. All quotes must be received electronically via email at: Thomas.semones@dla.mil, Subject: SP330027Q0011 Quotation – “Quoter’s Company Name.” Quotations must be received by 12:00 PM Eastern Standard Time on December 7, 2026 to be considered for award.

5. Attachment 1 – Schedule of Supplies or Services and Prices is hereby added.

6. Tab A-3 PWS Cross Connection Hazard Assessment is renamed Attachment 2 – Performance Work Statement.

7. Attachment 3 – Wage Determination 2015-5653 is hereby added.

8. Attachment 4 – Deliverables Schedule is hereby added.

9. RFQ SP330027Q0011 has been revised and replaced in its entirety.

10. Site Visit. A site visit has been scheduled for Wednesday December 2, 2027 at 9:00AM PST. If you are interested in attending please contact Jimmy Hall at jimmy.hall@dla.mil and Ed McNair at Edward.mcnair@dla.mil.

11. Answers to vendor questions are provided as follows:

Question 1. Is a preliminary site walkthrough permitted? If so, please provide the available date/time, registration process, required attendee information, and site contact.

Answer 1. A site visit will be held on Wednesday, December 2, 2027 at 9:00AM PST.

Question 2. Are campus maps, building square footage/use information, restricted-area details, water-distribution or plumbing drawings, treatment schematics, and information on non-potable systems available?

Answer 2. Yes. Detailed maps, drawings, and other pertinent information will be provided to the contractor upon award.

Question 3. Are existing backflow-device inventory, recent test reports, prior cross-connection surveys, or outstanding deficiency notices available?

Answer 3. Yes. The information will be provided to the contractor upon award.

Question 4. Does the assessment include assembly testing, operational testing, concealed-piping tracing, corrective work, or water shutdowns, or is it limited to accessible physical inspection, records review, hazard assessment, and recommendations?

Answer 4. The backflow prevention assemblies are tested annually by certified backflow prevention assembly testers, and the results will be provided to the contractor upon award. The cross-connection control specialist may or may not decide to consider these testing results during the evaluation of the protectiveness of each backflow prevention assembly.

Question 5. What security clearance, background check, badging, escort, safety training, photography, workhour, and occupied-building access requirements apply? Will a knowledgeable facility representative accompany the survey team? Are there any escort requirements or limits on site access hours we should account for when estimating field days?

Answer 5. A routine security background check will be conducted for all survey and support personnel. Contractor personnel will be always escorted by knowledgeable facility representative while on site. Onsite access is limited to 8am – 3pm, Monday through Friday.

Question 6. Is there a required Excel/report template or location convention, and who will review the draft? Should we plan for one comment/revision cycle only, with no follow-up site visit unless requested?

Answer 6. There is no required template. DLA Environmental Management will review the draft and provide comments. DLA anticipates one comment/revision cycle with no follow-up site.

Question 7. Are there preferred fieldwork dates or interim milestones within the stated performance period?

Answer 7. DLA requests submitting the draft Hazard Assessment report by March 1, 2027, and final Hazard Assessment report by April 30, 2027.

Question 8. What is the approximate number of backflow devices and are there any available water-system drawings.

Answer 8. 55

Question 9. Is device testing required or only inspection and assessment.

Answer 9. The backflow prevention assemblies are tested annually by certified backflow prevention assembly testers, and the results will be provided to the contractor upon award. The cross-connection control specialist may or may not decide to consider these testing results during the evaluation of the protectiveness of each backflow prevention assembly.

Question 10. Scope for pricing: Are building floor areas and an estimated count of existing backflow assemblies available? Does the device inspection under PWS 3.3 include functional testing, or only inspection and condition assessment?

Answer 10. Detailed maps, drawings, and other pertinent information will be provided to the contractor upon award.

The backflow prevention assemblies are tested annually by certified backflow prevention assembly testers, and the results will be provided to the contractor upon award. The cross-connection control specialist may or may not decide to consider these testing results during the evaluation of the protectiveness of each backflow prevention assembly.

Question 11. What hours, escorts/building access, pass/badge lead times, and photo restrictions apply? What tank/pump access will the Government provide, and should the entrance address use Christman or Chrisman Road?

Answer 11. Contractor personnel will be always escorted by knowledgeable facility representatives while on site. Onsite access is limited to 8am – 3pm, Monday through Friday with a 24-hour lead time. DLA will request camera pass for you and provide access to all applicable areas/equipment. Entrance to the facility is at Chrisman/Valpico Rd.

Question 12. Does section 5 permit recognized tester certification alone for the full survey, or must the lead be a specialist? Please confirm accepted California credentials, any professional license, UPC edition, and California/military standards.

Answer 12. Cross-Connection Specialists that meet the AWWA’s Certified Cross-Connection Control Program Specialist requirements and is qualified to perform Hazard Assessments, Cross-Connection Surveys and Shut-down Tests must review or conduct the Hazard Assessment and certify the findings.

Question 13. Does scope include functional/differential-pressure testing or sampling, or only visual inspection, hazard assessment, and recommendations? Are tank entry/climbing, confined-space work, intrusive inspection, shutdowns, repairs, and installation excluded?

Answer 13. The scope of the Hazard Assessment includes all considerations outlined in the state’s Cross-Connection Control Policy Handbook to evaluate the potential for backflow into the distribution system.

Question 14. Building Inventory and Plumbing Plans: Is an inventory of the 43 buildings available, including building uses and approximate square footage? Are plumbing plans, blueprints, or water distribution drawings available identified with potable water connections and equipment? Can you provide the 43-building roster, sizes/uses, assembly/connection counts, prior inventory/test records, and water-distribution/as-built drawings? If unavailable, is a pre-quote visit possible?

Answer 14. Detailed maps, drawings, and other pertinent information will be provided to the contractor upon award. No pre-bid walkthrough is planned.

Question 15. Section 4.1 requires an inventory of existing backflow prevention devices and assemblies. Does the Government have an existing inventory identifying their locations, types, and quantities that could be provided to bidders? Are there any escort requirements or limits on site access hours we should account for when estimating field days?

Answer 15. An inventory of existing backflow prevention assemblies will be provided to the contractor upon award. Contractor personnel will be always escorted by knowledgeable facility representatives while on site. Onsite access is limited to 8am – 3pm, Monday through Friday with a 24-hour lead time.

Question 16. Building Access: Will Government personnel facilitate access to all 43 buildings, including mechanical rooms, commercial kitchens, laundry facilities, boiler rooms, and other areas containing equipment connected to the potable water system?

Answer 16. Contractor personnel will be escorted by knowledgeable facility representatives who will provide access to all applicable areas/equipment.

Question 17. Backflow Assembly Testing: Section 3.3 requires determining the "current condition" of existing backflow prevention devices and assemblies. Since determining the operational condition of a testable assembly requires performance testing, please confirm whether field testing of all existing testable assemblies is required.

Answer 17. The backflow prevention assemblies are tested annually by certified backflow prevention assembly testers, and the results will be provided to the contractor upon award. The cross-connection control specialist may or may not decide to consider these testing results during the evaluation of the protectiveness of each backflow prevention assembly.

Question 18. Performance Schedule: Beyond the 15-business-day government review period in PWS Section 4.2, are there specific deadlines within December 1, 2026, through May 31, 2027, performance period for completing onsite assessments and submitting draft and final reports?

Answer 18. DLA requests submitting the draft Hazard Assessment report by March 1, 2027, and final Hazard Assessment report by April 30, 2027.

Question 19. Alternative Water Sources: Is recycled water, reclaimed water, untreated groundwater, or other non-potable water systems utilized? If so, are distribution maps or plumbing diagrams available identifying these systems and their connections or potential interfaces with the potable water system?

Answer 19. Non-potable water systems are not utilized.

Question 20. Section 6 gives December 1, 2026 through May 31, 2027, while PWS 6.2 still says “[Insert Number] days” after award.

Answer 20: The anticipated period of performance is December 14, 2026 through June 14, 2027

Question 21. The clause list includes FAR 52.222-41, -42 and -43, but we do not see a wage determination. Please provide the applicable determination and revision or confirm if an exemption applies. Please provide any applicable wage determination/labor categories or exemption determination for listed 52.222-41/-42/-43.

Answer 21. Wage Determination 2015-5653, Rev No. 28, dated 8/27/2026 is hereby included.

Question 22. Does FAR 52.219-14 or another limitation on subcontracting apply to this small-business purchase? We do not see a limitation in the posted clause list.

Answer 22. FAR Clause 52.219-14 is not applicable to this requirement

Question 23. Besides the quote markings in Section 13, will Government-furnished records or assessment deliverables contain CUI or covered defense information?

Answer 23. Deliverables should contain the appropriate CUI markings.

Question 24. Please identify the required exchange method and any pre-award assessment requirement under DFARS 252.204-7012 and 252.240-7997.

Answer 24. Exchanges of information should be in accordance with the appropriate clause and there are no required pre-award assessments

Question 25. PDF pp.5–6 incorporate 252.204-7012 and 252.240-7997; p.10 includes 252.204-7008/7024. Please provide the operative assessment/deviation text and confirm required NIST/SPRS assessments/postings and timing.

Answer 25. DFARS 252.240-7997 is revised to add (DEVIATION 2026 O0025) (FEB 2026)

Question 26. Will drawings, photos, inventories, or reports contain covered defense information/CUI requiring contractor-system safeguards?

Answer 26. Deliverables should contain the appropriate CUI markings.

Question 27. Is a CMMC level or Government-system-only handling arrangement required?

Answer 27. Level 1 is required.

Question 28. Within the prescribed three files, where should signed SF1449 and amendment acknowledgements go? Please confirm quote-specific representations beyond SAM and schedule fields.

Answer 28. Block 28 was not checked so a signed copy of the SF1449 is not required.

Question 29. Sections 2, 7 and 13 require Attachment 1, including its SAM tab, but the public package contains only the solicitation PDF and PWS. Please provide the Excel workbook and confirm the correct CLIN 0001 quantity and unit. Page 4 currently shows 92,500.000 MO.

Answer 29. Attachment 1 is included in this amendment. The 92,500.00 was a plug number to process the RFQ in the contract writing system. It has no relevance to the requirement. Follow the pricing structure in Attachment 1. Please make sure you fill out the SAM tab.

Question 30. Are insurance minimums or subcontracting/performance-allocation requirements applicable?

Answer 30. No.

12. All other terms and conditions remain unchanged and in full force and effect.

File details come from the government source that posted it. Updated .