This is an Amendment of Solicitation (Standard Form 30) issued by DLA Distribution for solicitation SP330027Q0002, dated October 8, 2026, with an effective date of October 15, 2026. The amendment is issued by DLA Distribution Acquisition Operations, J7 in New Cumberland, Pennsylvania, with the point of contact being Michael French at michael.s.french@dla.mil.

The amendment addresses vendor questions and provides clarifications regarding pipe specifications and access. Specifically, it confirms that the manhole opening is 36 inches in diameter and provides pictures of the pipe access area for reference in the attached file "A3 – Pictures." The amendment also clarifies that the 80 PSI pressure specification refers to internal pressure when the pipe is in use, while external pressure represents only normal forces experienced by a buried pipe. The closing date for receipt of offers is extended to October 16, 2026 at 2:00 PM EDT. Offerors must acknowledge receipt of this amendment by completing items 8 and 15 and returning copies of the amendment, by acknowledging receipt on each copy of the offer submitted, or by separate letter or electronic communication that includes reference to the solicitation and amendment numbers, with receipt required prior to the specified closing date and time.

View the file

Other files

File Type Posted
A3 - Pictures.zip ZIP file
SP3300-27-Q-0002.pdf PDF
A3 - Questions and Answers.pdf PDF
A1 - Statement of Work - DDSP Pipe Repair.pdf PDF
A2 - Wage Determination 2015-4245 Rev33.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

SP3300

SEE CONTINUATION PAGE(S)

DLA Distribution Acquisition Operations, J7 Mifflin Avenue, Bldg 5430 New Cumberland, PA 17070

POC: Michael French michael.s.french@dla.mil

SP330027Q0002

1 2

10/15/2026

10/08/2026

SP330027Q0002

AMD0001

The purpose of this amendment is the following:

1. The following vendor questions are answered:

a. Q: What type of manhole access is there? What is the barrel diameter?

A: The manhole opening is 36”. See “A3 – Pictures” for more information about the manhole access and area around the pipe to be lined.

b. Q: Is the 80 PSI of pressure on the pipe internal or external?

A: 80 PSI is in reference to the internal pressure when in use. The external pressure of the pipe is only normal forces experienced by a buried pipe.

2. Pictures of the pipe access are attached for reference. Please see attached file “A3 – Pictures”.

3. The closing date is extended to 10/16/2026 at 2:00 PM EDT.

4. This amendment makes no other changes.