Amendment 0001 Heat Chamber Oven POP ext QA.pdf
PDF 70 KB Posted
- Attached to
- Heat Treat Oven Federal contract opportunity
- Solicitation number
- sp330020q5038
- Issued by
- Defense Logistics Agency Distribution
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Post Award Notice 20F0882.pdf | ||
| SITE VISIT ROSTER 27Aug20.pdf | ||
| RFQ chamber oven Synopsis Solicitation.pdf | ||
| Attachment 1 Statement of Work for Heat Treat Oven.pdf | ||
| Attachment 2 Env Checklist for Heat Treat Oven.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DDJC MATOC Requirement Heat Chamber Oven
Amendment 0001
Amendment 0001 is incorporated into the Notice to Offers RFQ for project “Heat Chamber Oven”, DLA Distribution San Joaquin and shall become part of any resulting task order issued.
Amendment 0001 is being issued to increase the period of performance from 150 to 210 days and answer vendor questions below.
Vendor Questions:
Question 1: Can The QC Manager, SSHO and Superintendent be one person?
Answer 1: Yes.
Question 2: Requesting that the period of performance be changed from 150 calendar days to 210 calendar days due to the unknown lead times on material due to COVID-19 impact.
Answer 2: Yes, per this Amendment the performance period has changed.
All other terms and conditions remain unchanged.
END OF AMENDMENT 0001