Division 01 Special Requirements

FORM 4288

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION

DDJC UPGRADE HIGH VOLTAGE SUBSTATION RELAYS Division 1 - General Requirements

CONTRACTOR

A C T I V I T Y

N O

R A N S M I T T

L

S P E

DESCRIPTION OF ITEM SUBMITTED

R A G R A

H

G

V

C T L A O S R S I A F / I E C A R T E I V O W N R

CONTRACTOR SCHEDULE DATES CONTRACTOR

ACTION

APPROVING AUTHORITY

MAILED TO

CONTR/

DATE RCD

FROM

APPR AUTH

REMARKS

SUBMIT

APPROVAL

NEEDED BY

MATERIAL

T I

D

DATE OF

DATE FWD

TO APPR

AUTH

DATE RCD

CONTR

TO OTHER

REVIEWER

DATE RCD

FROM OTH

T I

(a) (b) (c ) (d) (e) (f) (g) (h) (I) (j) (k) (l) (m) (n) (o) (p) (q) (r )

011400 WORK RESTRICTIONS

SD-01 PRECONSTRUCTION SUBMITTALS

Special Access Determination Form 1.4.1.5 G

013201 PROJECT SCHEDULE

SD-01 PRECONSTRUCTION SUBMITTALS

Construction Project Schedule 3.3 G

013300 SUBMITTAL PROCEDURES

SD-01 PRECONSTRUCTION SUBMITTALS

Submittal Register 1.11 G

013529 SAFETY AND OCCUPATIONAL HEALTH REQTS.

SD-01 PRECONSTRUCTION SUBMITTALS

Accident Prevention Plan (APP) 1.6 G Injury Prevention Plan G Activity Hazard Analysis (AHA) 1.7 G Crane/Fork Lift plan 1.6 G

SD-06 TEST REPORTS

Accident Reports 1.11.1 G Monthly Exposure Reports 1.11.3 G Crane/Fork Lift Report 1.11.4 G

SD-07 CERTIFICATES

Hot Work Permit 1.12 G

014500 CONTRACTOR QUALITY CONTROL

SD-01 PRECONSTRUCTION SUBMITTALS

Contractor Quality Control Plan 3.2 G

Division 01 Special Requirements

DDJC UPGRADE HIGH VOLTAGE SUBSTATION RELAYS Division 1 - General R i t

T I V I

A N S M I T T

R A G R A

V

C T L A O S R S I A F / I E C A R T E I V O W N R

CONTRACTOR SCHEDULE DATES CONTRACTOR

MAILED TO

CONTR/

DATE RCD

APPR AUTH

APPROVAL

MATERIAL

T I

TO APPR

AUTH

DATE RCD

TO OTHER

DATE RCD

FROM OTH

T I

(a) (b) (c ) (d) (e) (f) (g) (h) (I) (j) (k) (l) (m) (n) (o) (p) (q) (r )

015719 ENVIRONMENTAL PROTECTION

SD-01 PRECONSTRUCTION SUBMITTALS

Environmental Protection Plan 1.7 G

SD-11 CLOSEOUT SUBMITTALS

017800 PROJECT CLOSEOUT

SD-02 SHOP DRAWINGS

As-Built Drawings 1.2.1 G

SD-03 PRODUCT DATA

As-Built Record of Equipment and Material. 1.2.2 G Warranty Management Plan 1.3.1 G Final Cleaning 1.6 G

SD-11 CLOSEOUT SUBMITTALS

Record Drawings 1.2.1 G Post construction Survey 1.6.1 G

Page 3/3

DDJC UPGRADE HIGH VOLTAGE SUBSTATION RELAYS Division 26 - Electrical

T I V I

A N

S M I T T

R

A

G

R

A

CONTRACT

OR

ACTION O

APPROV

AL

NEEDED

BY

MATERI

AL

NEEDED

BY

T I

DATE

OF

ACTIO

FWD

TO

APPR

AUTH

DATE

RCD

FWD TO

OTHER

REVIEW

ER

RCD

FROM

OTH

REVIEW

ER

T I

OF

ACTIO

N

V C T L A O S R S I A F / I E C A R T E I V O W N R

CONTR/

DATE

FROM

APPR

AUTH

(a) (b) (c ) (d) (e) (f) (g) (h) (I) (j) (k) (l) (m) (n) (o) (p) (q) (r )

ELECTRICAL

260500 SD 02 Product Data Conduit 1.3 G Wires and cables 1.3 G

010110 SD 03 Solar PV design 1.1.1.1.p 263100 SD 02 Interconnection diagram 1.4 SD 03 Installation diagram 1.4 SD 03 Product data 1.4 SD 05 Design data 1.4 SD 05 Test report 1.4 SD 07 Certificates 1.4 SD 08 Manufacturer’s instructions 1.4 SD 10 Operation and maintenance data 1.4 Letter of conformance 2.2. j 481450 Same as section 263100 1.3