tjc0831 Typewritten Text

REPLACE SOLAR PHOTO VOLTAIC & WATER HEATER BUILDING 100 DDJC

tjc0831 Typewritten Text G1

DAK0013

Typewritten Text

PROJECT LOCATION

DAK0013

Line

B L A

C K

V

E A

T C

H

S P

E C

I A

L

P

R O

J E

C T

S

C

O R

P

O V

E R

L A

N D

P

A R

K

K

A N

S A

S tjc0831 Typewritten Text

REPLACE SOLAR PHOTO VOLTAIC & WATER HEATER BUILDING 100 DDJC

tjc0831 Typewritten Text

DRWG # E1

DAK0013

Typewritten Text

BUILDING ELECTRICAL SYSTEM & SOLAR PV INTERCONNECTION PANEL HDP

DAK0013

Line

Rectangle

TO DDJCT-B201A

SHEET 1 OF 1

CBL-B100-2-4D-1

Demand 20.24 kVA

(1) 1/0 AWG/kcmil

Copper , 3-1/C , 600 V

20.0 ft

CBL-B100-2-4D-3

Demand 20.24 kVA

(1) 500 AWG/kcmil Copper , 4-1/C , 600 V

6.0 ft

CBL-B100-WH XFMR0

Demand 4.34 kVA

(1) 1/0 AWG/kcmil

Copper , 3-1/C+G , 600 V

4.0 ft

CBL-B100-LDP-2

Demand 51.41 kVA

(1) 350 AWG/kcmil

Copper , 4-1/C , 600 V

4.0 ft

CBL-0679

Demand 20.24 kVA

(1) 750 AWG/kcmil

Copper , 3-1/C+G , 600 V

0.1 ft

BUS-B100-2-4D(LINE SIDE)

208.0V

S

P

XF2-B100-T-2-4D

112.5 kVA, NL 480 V - 208 V

3.7000 %

Demand 20.24 kVA

SCH-B100-100E-10

Demand 1.63

SCH-B100-WH-1

Demand 4.34

SCH-B100-2H

Demand 6.82

SCH-B100-1H

Demand 4.70

SCH-B100-H

Demand 10.01

SCH-B100-2-3D

Demand 0.73

SCH-B100-2-2D

Demand 0.65

SCH-B100-100

Demand 2.43

SCH-B100-2-1D

Demand 7.04

SCH-B100-2-4D

Demand 20.24

SCH-B100-K SECT II

Demand 3.62

SCH-B100-K SECT I

Demand 9.59

SCH-B100-M

Demand 2.30

SCH-B100-2L

Demand 1.86

SCH-B100-1L

Demand 3.02

SCH-B100-PNL L

Demand 0.00

SCH-B100-LDP

Demand 51.41

SCH-B100-HDP

Demand 97.51

BUS-B100-PNL L

208.0V

CBL-B100-PNL L

Demand 0.00 kVA

(1) 6 AWG/kcmil

Copper , 3-1/C+G , 600 V

85.0 ft

CB-B100-PNL L

70.0 A

BUS-B100-100E-10

208.0V

CBL-B100-100E-10

Demand 1.63 kVA

(1) 6 AWG/kcmil

Copper , 3-1/C+G , 600 V

188.0 ft

CB-B100-WH-1

225.0 A

BUS-B100-WH-1

208.0V

S

P

XF2-B100-WAREHOUSE XFMR

112.5 kVA, NL

480 V - 208 V

3.7000 % Demand 4.34 kVA

CBL-B100-WH XFMR

Demand 4.34 kVA

(1) 2 AWG/kcmil

Copper , 3-1/C , 600 V

120.0 ft

CB-B100-WH XFMR

100.0 A

BUS-B100-2-4D

208.0V

CB-B100-2-4D-2

400.0 A

CB-B100-100-2

100.0 A

BUS-B100-100

208.0V

CBL-B100-100

Demand 2.43 kVA

(1) 1 AWG/kcmil

Copper , 3-1/C+G , 600 V

195.0 ft

CB-B100-100-1

100.0 A

CB-B100-2-3D-2

100.0 A

BUS-B100-2-3D

208.0V

CBL-B100-2-3D

Demand 0.73 kVA

(1) 2 AWG/kcmil

Copper , 3-1/C+G , 600 V

175.0 ft

CB-B100-2-3D-1

20.0 A

CB-B100-2-2D-2

225.0 A

BUS-B100-2-2D

208.0V

CBL-B100-2-2D

Demand 0.65 kVA

(1) 4/0 AWG/kcmil

Copper , 3-1/C+G , 600 V

160.0 ft

CB-B100-2-2D-1

20.0 A

CB-B100-2-1D-2

225.0 A

BUS-B100-2-1D

208.0V

CBL-B100-2-1D

Demand 7.04 kVA

(1) 4/0 AWG/kcmil

Copper , 3-1/C+G , 600 V

180.0 ft

CB-B100-2-1D-1

100.0 A

BUS-B100-K SECT II

208.0V

CBL-B100-K SECT II

Demand 3.62 kVA

(1) 1/0 AWG/kcmil

Copper , 3-1/C+G , 600 V

75.0 ft

CB-B100-K SECT II

150.0 A

BUS-B100-K SECT I

208.0V

CBL-B100-K SECT I

Demand 9.59 kVA

(1) 1/0 AWG/kcmil

Copper , 3-1/C+G , 600 V

70.0 ft

CB-B100-K SECT I

150.0 A

BUS-B100-M

208.0V

CBL-B100-M

Demand 2.30 kVA

(1) 6 AWG/kcmil

Copper , 3-1/C+G , 600 V

20.0 ft

CB-B100-M

50.0 A

BUS-B100-2L

208.0V

CBL-B100-2L

Demand 1.86 kVA

(1) 6 AWG/kcmil

Copper , 3-1/C+G , 600 V

260.0 ft

CB-B100-2L

70.0 A

BUS-B100-2H

480.0V

CBL-B100-2H

Demand 6.82 kVA

(1) 4 AWG/kcmil

Copper , 3-1/C+G , 600 V

270.0 ft

CB-B100-2H

60.0 A

BUS-B100-1L

208.0V

CBL-B100-1L

Demand 3.02 kVA

(1) 6 AWG/kcmil

Copper , 3-1/C+G , 600 V

245.0 ft

CB-B100-1L

70.0 A

BUS-B100-1H

480.0V

CBL-B100-1H

Demand 4.70 kVA

(1) 6 AWG/kcmil

Copper , 3-1/C+G , 600 V

250.0 ft

CB-B100-1H

100.0 A

BUS-B100-H

480.0V

CBL-B100-H

Demand 10.01 kVA

(1) 6 AWG/kcmil

Copper , 3-1/C+G , 600 V

110.0 ft

CB-B100-H

70.0 A

BUS-B100-LDP

208.0V

S

P

XF2-B100-TRANSFORMER T1

112.5 kVA, NL

480 V - 208 V

3.7000 % Demand 51.41 kVA

CBL-B100-LDP-1

Demand 51.41 kVA

(1) 2/0 AWG/kcmil

Copper , 3-1/C , 600 V

4.0 ft

CB-B100-LDP

150.0 A

BUS-B100-HDP

480.0V

CB-B100-HDP

500.0 A

CBL-0579

Demand 97.51 kVA

(1) 500 AWG/kcmil Copper , 3-1/C , 600 V

125.0 ft

BUS-B100-HDP (LINE SIDE)

480.0V

CBL-0650

Demand 97.51 kVA

(1) 750 AWG/kcmil

Copper , 4-1/C , 600 V

0.1 ft

BUS-B100-WH-1 (LINE SIDE)

208.0V

CBL-0673

Demand 4.34 kVA

(1) 750 AWG/kcmil

Copper , 4-1/C , 600 V

0.1 ft

CB-B100-2-4D-1

175.0 A

CBL-B100-2-4D-2

Demand 20.24 kVA

(1) 2 AWG/kcmil

Copper , 3-1/C , 600 V

8.0 ft

BUS-B100-2-1D (LINE SIDE)

208.0V

CBL-0712

Demand 7.04 kVA

(1) 750 AWG/kcmil

Copper , 4-1/C , 600 V

0.1 ft

BUS-B100-100 (LINE SIDE)

208.0V

CBL-0713

Demand 2.43 kVA

(1) 750 AWG/kcmil

Copper , 4-1/C , 600 V

0.1 ft

BLACK & VEATCH

SPECIAL PROJECTS CORP

OVERLAND PARK, KANSAS

ARC FLASH ANALYSIS

DDJC TRACY

DDJCT-B100 SHEET 5 OF 5

SINGLE LINE DIAGRAM

EXISTING

June 26, 2013

DAK0013

Typewritten Text

REPLACE SOLAR PHOTOVOLTAIC & WATER HEATER BUILDING 100 DDJC

DAK0013

Typewritten Text E 2

DAK0013

Rectangle

DAK0013

Typewritten Text

DRWG # E 2

BUILDING ELECTRIC PANEL HDP

SINGLE LINE

55'-6.2"

9'-0.4"

1'

5'-1.4"

14'-1.4" 3'-10.6" 9'

S.

C

H

IS

M

AN

R

OA

D N

TRUE

NORTH

55'-6.2"

9'-0.4"

1'

5'-1.4"

14'-1.4" 3'-10.6" 9' iBOS

TYPICAL

SEE NOTE 1

SUNPACK-6M

SEE NOTE 2

RTU

TYPICAL

4' MAINTENANCE

SETBACK

TYPICAL

4' FIRE SETBACK

TYPICAL

DETAIL A & B

202'-3.8"

221'-1.2"

296'-5.7"

9'-0.4"

RL-1

RO

OF

L

AY

OU

T

DRAWING NUMBER

CHECKED BY: CT

DRAWN BY: MCL

JOB No:

REV DWG DATE

COGENRA SOLAR

365 E. MIDDLE FIELD RD.

MOUNTAIN VIEW, CA 94043

(P) 650-230-3400

(F) 650-967-2445

A INITIAL 12/16/11

SCALE: NTS

SHEET:

S.

C H

RI

SM

AN

R

D

TR

AC

Y, C

A

B

TR

AC

Y

AR

M Y

D

EP

OT

GENERAL SHEET NOTES

REFERENCE SHEET NOTES

A. ALL CONSTRUCTION AND

WORKMANSHIP TO CONFORM TO

ALL 2011 NEC AND LOCAL

BUILDING CODES.

B. THE CONTRACTOR SHALL VERIFY

EXISTING DIMENSIONS,

ELEVATIONS, AND CONDITIONS

PRIOR TO STARTING

CONSTRUCTION. PRIOR TO

CONTINUING WORK, NOTIFY

COMPREHENSIVE ENGINEERING

OF ANY DEVIATIONS FROM THE

PLAN WHICH ARE NECESSITATED

BY FIELD CONDITIONS

DIFFERENT THAN THOSE

INDICATED ON PLAN.

1. iBOS IS LOCATED ON WEST SIDE

OF ARRAY TO MINIMIZE THE

CONDUIT AND WIRE LENGTH

RUNS TO MECHANICAL ROOM.

2. ARRAY SIZE IS 1 QTY 2X6

SUNPACK-12M FOR TOTAL OF 12

MODULES. PV SYSTEM SIZE IS

5.16 KW DC.

3. COGENRA SUNPACK-6M

ORIENTATED FACING 180° SOUTH

AZIMUTH.

DETAIL A: SUNPACK-12M

TRACY ARMY DEPOT DETAIL B: 12 MODULE RACKING

Joe B Rectangle

Joe B Rectangle

Joe B Text Box New location

Joe B Line

Joe B Line

Joe B Text Box AS-Builts 4/24/2013

Joe B Text Box Parshall Construction

DAK0013

Typewritten Text

REPLACE SOLAR PHOTOVOLTAIC & WATER HEATER BUILDING 100 DDJC

DAK0013

Typewritten Text

DRWG # PV1

DAK0013

Rectangle

DAK0013

Rectangle

DAK0013

Polygon

DAK0013

Typewritten Text

DEMOLISH AND REMOVE

NORMALLY CLOSED

M2

M2

M2

M2

<E> CW(S)

M2

M2

SOLAR SUPPLY & RETURN 1" DIA

TR

AC

Y

AR

M Y

D

EP

OT

SO

LA

R

CO

G

EN

ER

AT

IO

N P

RO

JE

CT

S.

C

H

RI

SM

AN

R D

TR

AC

Y, C A

GENERAL SHEET NOTES

REFERENCE SHEET NOTES

MECH-1

SO

LA

R

TH

ER

M

AL

RO

OF

P

IP

E

LA

YO

UT

PIPING IS DRAWN DIAGRAMMATICALLY FOR

CLARITY AND DOES NOT SHOW EVERY OFFSET,

BEND, AND 90. THE INSTALLING CONTRACTOR IS

TO CONFIRM THE ROUTING BASED ON FIELD

CONDITIONS AND ROUTE ACCORDINGLY TO BEST

SUIT FIELD CONDITIONS.

VERIFY ALL EXISTING CONDITIONS AND NOTIFY

ENGINEER OF ANY DISCREPANCIES FOUND.

FIELD INSTALLED EQUIPMENT SHALL NOT CARRY

THE WEIGHT OF THE PIPING, SUPPORT

ACCORDINGLY.

ALL WORK TO BE IN ACCORDANCE

UNIFORM SOLAR ENERGY CODE - 2009

CALIFORNIA MECHANICAL CODE - 2010

CALIFORNIA PLUMBING CODE - 2010

CALIFORNIA ELECTRICAL CODE -2010

NFPA 70 -2011

CONTRACTOR SHALL HAND OVER A FULLY

FUCNTIONAL AND OPERABLE SYSTEM TO THE

CUSTOMER.

A.

B.

C.

D.

E.

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

ROUTE SUPPLY AND RETURN PIPING TO SOLAR

MODULES. PIPING SHALL MEET ASTM B88

TYPE M, HARD DRAWN, FITTINGS SHALL MEET

ASTM B16.

BUILDING CITY WATER AND DOMESTIC HOT

WATER SHALL MEET NSF 61, IN ADDITION TO

MEETING ASTM B88 TYPE L HARD DRAWN,

FITTINGS SHALL BE ASTM B16.

INSULATE AND JACKET ALL NEW PIPING.

INSULATION THICKNESS SHALL MEET THE

FOLLOWING;

PIPE 1 INCH OR LESS = 1/2 INCH

PIPE 1-1/4 TO 2 INCH = 1 INCH

PIPE 2.5 TO 4 = 1-1/2 INCH

INSULATION INSTALLED OUTDOOR SHALL HAVE

ALUMINUM JACKETING WITH THE SEAM

INSTALLED ON THE LOWER HALF OF THE PIPE

AND SEALED TO PROTECT FROM WATER

DAMAGE.

SOLAR THERMAL WATER SHALL BE CLEARLY

IDENTIFIED WITH BLACK LETTERS AND

YELLOW BACKGROUND AND SHALL READ

“CAUTION: NON-POTABLE WATER, DO NOT

DRINK” LETTER SIZING SHALL FOLLOW UPC

TABLE 6-1.

MAXIMUM PIPE SUPPORT SPACING

1-1/2 INCH & SMALLER SHALL NOT EXCEED

6FT. 2 INCH & LARGER SHALL NOT EXCEED 10

FT.

MAINTAIN MIN 4 FT CLEARANCE FROM ANY

PARAPET WALL.

PROVIDE ETHERNET CAT 5 CABLE FROM

BUILDING OWNER TO FIRST iBOS UNIT.

CO-ORDINATE WITH OWNER'S I.T.

ADMINISTRATOR FOR A I.P. ADDRESS.ROUTE

CAT 5 TO ROOF TOP iBOS UNIT.

SUPPLY AIR VENTS AT ALL SYSTEM HIGH

POINTS AND DRAINS AT ALL SYSTEM LOW

POINTS

CLEAN, PURGE, AND FILL SYSTEM WITH 20%

PROPYLENE GLYCOL BY VOLUME.

CHECKED BY:

DRAWN BY: AC

JOB No: TRACY DEPOT

SCALE: 1/8" = 1'

DRAWING NUMBER

A

REV DATE

100% CD 12/29/2011

For Reference Only

TJC0908

Text Box

TJC0908

Line

TJC0908

Text Box N

Joe B Text Box See sheet Roof Layout for revised location

Joe B Text Box As-Builts 4/24/2013

Joe B Text Box Parshall Construction

DAK0013

Typewritten Text

REPLACE SOLAR PHOTOVOLTAIC & WATER HEATER BUILDING 100 DDJC

DAK0013

Typewritten Text

DRWG # PV2

DAK0013

Rectangle

DAK0013

Typewritten Text

SEE DRWG# PV1 FOR NEW LOCATION

LEVEL INDICATOR

SOLAR HEAT EXCHANGER IN

DOMESTIC HEAT EXCAHNGER IN

DOMESTIC HEAT

SOLAR HEAT EXCHANGER OUT

EXCHANGERS OUT

MANUAL AIR VENT (TYP X 2)

SOLAR HEAT EXCHANGER

(TYP x1)

SEE EQUIPEMENT SCEDULE

DOMESTIC HEAT EXCHANGER

(TYP x2)

SEE EQUIPEMENT SCHEDULE

(TYP x4)

DRAIN/PURGE

MANUAL AIR VENTS

(TYP x2)

P.O.C.

<E> WATER HEATER

<E> CW(S), VERIFY SIZE IN FEILD

N.C.

DOMESTIC HOT WATER

CITY WATER TO

FROM SOLAR TANK HEAT EXCHANGER

TANK HEAT EXCHANGER

P.O.C.

<E> RE-CIRC PUMP

MAKE-UP WATER

<E> DHW (S)

TB

L

TB

L

TB

N

TB

G

N D

TB

L

TB

L

TB

N

TB

G

N D

TB

L

TB

L

TB

N

TB

G

N D

INPUT POWER

208/240VAC

15 AMP MAX

OUTPUT POWER

208/240VAC

5 AMP MAX

OUTPUT POWER

208/240VAC

5 AMP MAX

SOLAR BOOSTER PUMP

BUILDING POWER CONNECTION

D C

CO

M

D C

CO

M

D C

CO

M

D C

CO

M 24

+V D

C

+V D

C

BO

OS

TE

R

TB

G

N D

BOOSTER PUMP START STOP SIGNAL

& ROUTER RESET SINGAL

24 AWG 2 PAIR

8 PORT SWITCH

TO/FROM

M

ASTER iBOS

CAT 5 ETHERNET CABLE

NOT USED

PUMP#1 PUMP#2

COMMUNICATION BOX

JUNIPER VPN GATEWAY

CAT 5 ETHERNET CABLE

TO/FROM

BLD

G

MFGREQUIPEMENT TAG MODEL POWEROPERATING WIEGHT

TK

SR

PS

SOLAR TANK

SOLAR RECEIVERS

HAASE

COGENRA SUNDECK

iBOS

T413-22

UN-PRESSUREIZED SOLAR TANKS - HEAT EXCHANGERS PER TANK

CONNECTION SIZE NOTES

DN40 BST TO

1-1/2 INCH MPT W/ ADAPTER

VOLUME

4750 LBS 560 GAL NONE

208-240V iBOS CONNECTS TO SOLAR RECEIVERS USING SUPPLIED

CORRUGATED STAINLESS STEEL TUBING

SOLAR THERMAL

PUMP STATION

3/4 INCH (S) & (R)

(2) DOMESTIC WATER HX MODEL (B4)

(1) SOLAR HX (MODEL S4)

HEAT TRANSFER FLUID & POTABLE WATER SEPARATED BY VENTED

TANK STORAGE WATER (DOUBLE WALL HEAT EXCHANGER)

SOLAR

SOLAR

COGENRA CONTAINS UL 508 RATED CONTROLS ENCLOSURE

SEE ELECTRICAL DWGS FOR DETAILS 3/4 INCH NPT (S) &1 INCH (R)

SEE ELECL

DWGS

75 LBS

300 LBS 0.9 GAL

1.0 GAL 1PH/60HZ

CM COMMUNICATION

BOX SOLAR

COGENRA COMM BOX NONE 25 LBS NONE

208-240V

1PH/60HZ

UL 508 RATED CONTROLS ENCLOSURE

CONTROLS SOLAR BOOSTER PUMP

PRESSURE RELEIF

AIR

SEPERATOR

P.O.C.

PRUGE FILL

FLOW &

TEMP

PRES &

TEMP

(TYP 2)

EXPAN

SION

TAN

K

SOLAR RETURNS 3/4" NPT

SOLAR SUPPLY & RETURN 1" NPT

2.1 G

AL

SOLAR SUPPLY 1" NPTP.O.C.

UL 508 LISTED CONTROLS CABINET

CALCIUM SILICATE INSERT

B-LINE DURA BLOCK OR EQUAL

EXISTING ROOF

W/ PRE-GALVANIZED STEEL OR ALUMINUM JACKETING

SOLAR SUPPLY & RETURN

(SEE ROOF LAYOUT FOR SIZING)

SOLAR AC CONDUIT

W/ P1000 STRUT OR EQUAL

EITHERNET & CONTROLS

ROOF SUPPORT

TR

AC

Y

AR

M Y

D

EP

OT

SO

LA

R

CO

G

EN

ER

AT

IO

N P

RO

JE

CT

S.

C

H

RI

SM

AN

R D

TR

AC

Y, C A

CALCIUM SILICATE INSERT

W/ PRE-GALVANIZED STEEL OR ALUMINUM JACKETING

SOLAR SUPPLY & RETURN

(SEE ROOF LAYOUT FOR SIZING)

SOLAR AC CONDUIT

P1000 STRUT OR EQUAL

EITHERNET & CONTROLS

STRUCTURAL MEMBER, SSD

SOLAR RACK SUPPORT

GENERAL SHEET NOTES

REFERENCE SHEET NOTES

M-2

M

EC

H D

ET

AI

LS

DRAWING NUMBER

CHECKED BY:

DRAWN BY: AC

REV DWG DATE

COGENRA SOLAR

365 E. MIDDLE FIELD RD.

MOUNTAIN VIEW, CA 94043

(P) 650-230-3400

(F) 650-967-2445

A 100% 12/29/11

SCALE: NOTED

1. ROUTE IBOS PRESSURE RELIEF TO

WITHIN 6 INCHES OF ROOF.

2. SUPPLY MANUAL AIR VENTS AT

SYSTEM HIGH POINTS AND DRAINS AT

SYSTEM LOW POINTS.

3. PROVIDE ISOLATION VALVES SO

SOLAR TANK CAN BE ISOLATED AND

BY-PASSED.

4. FURNISH AND INSTALL SOLAR TANKS

AS SCHEMATICALLY SHOWN IN DETAIL

#1.

5. SEAL ALL BUILDING & ROOF

PENETRATIONS.

6. ALL NEW HYDRONIC PIPING SHALL BE

PRESSURE TESTED TO A PRESSURE

NOT LESS THAN 100 PSI. THIS

PRESSURE SHALL BE MAINTAINED

FOR AT LEAST 30 MINS. REQUIRED

TESTING SHALL BE DONE IN THE

PRESENCE OF THE INSPECTOR OF

THE AHJ IF REQUIRED. PIPING TO BE

PRESSURE TESTED MUST REMAIN

UN-INSULATED UNTIL AFTER

PRESSURE TESTING IS COMPLETED.

7. PROVIDE STRUT SUPPORTS FOR THE

SUPPLY & RETURN PIPING TO THE

STORAGE TANKS AS SHOWN IN

DETAIL #5&6.

A. PIPING IS DRAWN DIAGRAMMATICALLY

FOR CLARITY AND DOES NOT SHOW

EVERY OFFSET, BEND, AND 90. THE

INSTALLING CONTRACTOR IS TO CONFIRM

THE ROUTING BASED ON FIELD

CONDITIONS AND ROUTE ACCORDINGLY

TO BEST SUIT FIELD CONDITIONS.

B. VERIFY ALL EXISTING CONDITIONS AND

NOTIFY ENGINEER OF ANY

DISCREPANCIES FOUND.

C. FIELD INSTALLED EQUIPMENT SHALL NOT

CARRY THE WEIGHT OF THE PIPING,

SUPPORT ACCORDINGLY.

D. ALL WORK TO BE IN ACCORDANCE WITH:

UNIFORM SOLAR CODE - 2010

CALIFORNIA MECHANICAL CODE - 2010

CALIFORNIA PLUMBING CODE - 2010

NPFA 70 - 2011

SCALE: NOT TO SCALE1 2

3 4

SCALE: NOT TO SCALESCALE: NOT TO SCALE

SCALE: NOT TO SCALE

6SCALE: NOT TO SCALE

For Reference Only

Joe B Text Box

GAL

Joe B Text Box Trendsetter

Joe B Text Box As-Builts 4/24/13

Joe B Text Box Parshall Construction

DAK0013

Typewritten Text

REPLACE SOLAR PHOTOVOLTAIC & WATER HEATER BUILDING 100 DDJC

DAK0013

Typewritten Text

DRWG # PV3

DAK0013

Rectangle

MAIN SERVICE PANEL

600A, 3PH, 4W,

480Y/277

TO BE CONFIRMED

EXISTING

GROUNDING

ELECTRODE

SEE NOTE 6

30 A BACKFED BREAKER

SEE NOTE 4

Cogenra Design Calculations (See Note 5)

Project Name: Facebook Building #18 Address: Network Circle, Menlo Park, CA

System Components Component Units Manufactucter and Model Number

1. Photovoltaic Modules 12 Congenra 1 Qty SunPack-12M

2. Inverters 1 SMA Sunnyboy 5000US

3. AC Disconnect SW 1 Square D HU361RB 30 A

Module Specs: Inverter Specs: SunPack 12M Strings:

Isc = 13.1 A Max AC Out = 24 A Mods per string = 12 Voc = 43.9 V CEC eff.= 95.5% # of Strings = 1 Imp = 12.2 A AC output= 208 V Vmp = 35.2 V

STC= 430 W

GENERAL SHEET NOTES

REFERENCE SHEET NOTES

SL-1

SI

N

G

LE

L

IN

E

TR

AC

Y

AR

M

Y D

EP

OT

SO

UT

H

C H

RI

SM

AN

R

D

TR

AC

Y, C

A

CHECKED BY: CT

DRAWN BY: MCL

JOB No:

SCALE: NTS

DRAWING NUMBER

12/16/2011A

REV DATE

.B

INITIAL

TITLE

C:\Users\miller.lai\Downloads\Cogenra-LogoM-RGB.png

Joe B Text Box 277V

Joe B Text Box Breaker # 1

Joe B Text Box 2 # 8 thhn, 1 # 10 Thhn in 3/4" EMT

Joe B Text Box

Joe B Line

Joe B Line

Joe B Text Box Rated maximum power-point current 12.2 A Rated maximum power-point voltage 422.4 V Maximum system voltage 526.8 V Short circuit current 13.1 V

Joe B Text Box Tracy DDJC

Joe B Text Box Panel "HDP"

Joe B Text Box As-Builts 4/24/13

Joe B Text Box Parshall Construction

DAK0013

Typewritten Text

REPLACE SOLAR PHOTOVOLTAIC & WATER HEATER BUILDING 100 DDJC

DAK0013

Rectangle

WG #

DAK0013

Sticky Note

DAK0013

Typewritten Text

DRWG # PV4

DAK0013

Polygon

DAK0013

Typewritten Text

DEMOLISH AND REMOVE

DAK0013

Line

DAK0013

Polygon

DAK0013

Line

DAK0013

Rectangle

MECHANICAL EQUIPMENT SCHEDULE

DRAWING NUMBER

REV DWG DATE

A INITIAL

365 E. MIDDLEFIELD RD.

MOUNTAIN VIEW, CA 94043

(P) 650-230-3400

(F) 650-967-2445

SO

LA

R

CO

-G

EN

ER

AT

IO

N

S

YS

TE

M

IN

ST

AL

LA

TI

ON

T

RA

CY

A

RM

Y

D

EP

OT

SO

UT

H C

H

RI

SM

AN

R

OA

D T

RA

CY

C A, B MISSING

PARTS

M

EC

H

AN

IC

AL

D

ET

AI

LS

M-200

GENERAL SHEET NOTES

REFERENCE SHEET NOTES

DAK0013

Typewritten Text

REPLACE SOLAR PHOTOVOLTAIC & WATER HEATER BUILDING 100 DDJC

DAK0013

Rectangle

DAK0013

Typewritten Text

DRWG # PV5

DAK0013

Polygon

DAK0013

Typewritten Text

DEMOLISH AND REMOVE

Drawing Report

10/6/2015 Page 1

Section: Tracy DD Bldgs.

Page: E-4910_1 - Tracy Defense Depot - Bldg. 100 - South Section Lower / Upper Area

13' 6"

50' 0"

90' 6"

300' 6"

296' 6"

N.I.C.

Lower Area

Upper Area

N.I.B.

135' 0"

Walkpads

Walkpads

70' 6"

Legend Description SF LF EA

Roof Area (613 sqs) 61,292.750 Cricket 1' Base Flashing / Expansion Joint 70.500 1' Counter Flashing 316.500 1' Base Flashing 1,258.000 Walkpads 1,060.000 Roof Drain 35.000

Julio.Ponce Rectangle

Julio.Ponce Rectangle

Julio.Ponce Line

DAK0013

Rectangle

DAK0013

Typewritten Text

DRWG # S1

DAK0013

Rectangle

DAK0013

Typewritten Text

EXISTING ROOF LAYOUT

DAK0013

Rectangle

DAK0013

Rectangle

DAK0013

Typewritten Text

REPLACE SOLAR PHOTOVOLTAIC & WATER HEATER BUILDING 100 DDJC

DAK0013

Typewritten Text

NEW SOLAR PV SYSTEM TO BE INSTALLED ON UPPER ROOF AREA

DAK0013

FOR REFERENCE ONLY

DRWG # S2

DAK0013

Rectangle

DAK0013

Typewritten Text

REPLACE SOLAR PHOTOVOLTAIC & WATER HEATER BUILDING 100 DDJC

DAK0013

Rectangle

DAK0013

BUILDING 100 ROOF DETAILS

DAK0013

Typewritten Text

DRWG # S3

DAK0013

BUILDING 100 ROOF DETAILS

E 1 Panel HDP Location
E 2 Panel HDP SinleLine
G 1 General Project Location
PV 1 Existing Solar PV and Water Heater Asbuilt Drawing1
PV 2 Existing Solar PV and Water Heater Asbuilt Drawing2
PV 3 Existing Solar PV and Water Heater Asbuilt Drawing3
PV 4 Existing Solar PV and Water Heater Asbuilt Drawing4
PV 5 Existing Solar PV and Water Heater Asbuilt Drawing5
S 1 RoofLayout
S 2 Roof Structure 1
S 3 Roof Structure 2