Amendment 0002
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bldg 51 Combined Dwgs.pdf | ||
| Bldg 50 Combined Dwgs.pdf | ||
| Bldg 55 Combined Dwgs.pdf | ||
| Amendment 0001 SP310008B5002.pdf | ||
| Bldg 56 Combined Dwgs.pdf | ||
| Site Visit Attendance Sheet.pdf | ||
| ITEMS DISCUSSED AT THE PREPROPOSAL CONFERENCE.doc | DOC document | |
| SP3100-08-B-5002.pdf | ||
| Bldg 51 Combined Dwgs.pdf | ||
| Security Attachments A through E.pdf | ||
| Bldg 55 Combined Dwgs.pdf | ||
| Specs Combined.pdf | ||
| Davis Bacon Wage Determination.htm | HTM file | |
| Bldg 56 Combined Dwgs.pdf | ||
| Bldg 50 Combined Dwgs.pdf | ||
| SF25A | — | |
| SF25 | — | |
| SF24 - Bid Bond.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 11)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
SP3100-08-B-5002
Amendment 0002 Amendment 0002 is hereby incorporated into solicitation SP3100-08-B-5002 and shall become part of any resultant contract.
Amendment 0002 is being issued to provide answers to vendor questions.
Received: Friday, May 2, 2008
Question 1: Are we correct in saying that all existing painted lines are to remain with the exception of removal of RED paint located at a few exit area locations? These exits are symbolized by the dashed lines on the drawings. Therefore, are we correct to say that paint removal should only be minor and that all other locations, we are to paint over existing lines?
Answer 1: Correct, Clarify, the existing painted lines at the exit aisle vary in color and are not red only as noted above. The requirement is to remove all lines at the exit aisles regardless of the color.
Question 2: The drawings indicate the stencil numbers at the perimeter of the bays which are specified as “Stencil Number Grid”. These stencil numbers appear to be located outside of the building envelope.
Are we to assume that we are/are not going to paint all of these stencil numbers at that location outside of the building envelope?
Answer 2: No numbers are required to be painted outside the building envelope. Clarify, where the stencil grid crosses the proposed painted lines a stencil number as numbered on the grid is to be provided.
Question 3: All floor plan sheets indicate the existence of an “invisible grid” on the floor plans which appears to be just for guidance for interior stencil work. Are we to assume that there is no painting of any of these “light-colored lines”? Are they for guidance only?
Answer 3: Correct, grid lines are for guidance for painting the stencil numbers only.
Question 4: Are heavy fans acceptable to assist with the removal of fumes while performing all of the work? Can they also be located in a few strategic locations that enable the inside air to be routed through an existing exit door or window?
Answer 4: Ventilation requirements shall be per specifications 09900 1.5 Safety and Health. Contractor can use fans to assist but the requirements set in the specifications shall still be met. Power for the fans shall be provided by the contractor and keep in mind no gasoline powered equipment is permitted in any of the buildings. As far as the locations of fans, the contractor shall submit a plan showing the locations prior to starting work and the plan shall be approved by the Government.
Question 5: How much time will be required for notice to the government if there are government materials or other government storage in the way of our production? Approximately how long will it take for the government to act on the said removals upon notification?
Answer 5: Five business days as noted on drawing A-001, General Note No. 12. Contractor shall schedule all work according to the 5 day business notice on General Note No. 12.
All other terms and conditions remain unchanged.
END OF AMENDMENT 0002
| 2007-08-15 Amend 001 Drawings.pdf |
| 2007-08-15 Amend 001 drawings Combined.pdf |
| 2007-08-15 Amend 001 drawings Combined.pdf |
| 2007-08-15 C-001.pdf |
| C-202.pdf |
| C-501.pdf |
| C-502.pdf |
| C-503.pdf |
| P-C-2.pdf |
| 2007-08-15 Drawings Combined.pdf |
| 001.pdf |
| 202.pdf |
| 501.pdf |
| 2007-08-21 Combined Drawings.pdf |
| G-001.pdf |
| A-101.pdf |
| A-501.pdf |
| IDCode: |
| Page: 1 |
| Pages: 2 |
| AmendNo: 0002 |
| EffDate: 05 May 2008 |
| ReqNo: |
| ProjNo: |
| IssCode: SP3100 |
| IssuedBy: DEFENSE DISTRIBUTION CENTER |
ACQUISITION OPERATION DDC-AB
2001 MISSION DR BLDG 81
NEW CUMBERLAND PA 17070-5001
| AdmCode: DAKADM |
| AdminBy: DONNA KAUTZ |
717-770-6563 FX 717-770-7591
donna.kautz@dla.mil
| ContName: |
| ContStrt: |
| ContCnty: |
| ContSt: |
| ContZIP: |
| Code: |
| FacCode: |
| SolAmdNo: SP3100-08-B-5002 |
| AmendDate: 09 APR 2008 |
| ModNo: |
| ModDate: 05 JUL 20 |
| NoCopies: 1 |
| Amended: Yes |
| ApprData: |
| ChgeOrder: |
| Modify: Off |
| SuppAuth: |
| OthrSpec: |
| Require: Off |
| Copies: |
| Descript: See Page 2. |
| SignName: |
| SignTitl: |
| ContDate: |
| CoName: |
| CoTitle: |
| CODate: |
| SolChgYs: Yes |
| SolChgNo: Off |
| OffrExt: Off |
| OffrNoEx: No |
| ChgeOrd: Off |
| SuppAgre: Off |
| ModOthr: Off |
| NoReq: Off |
File details come from the government source that posted it. Updated .