AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

K PAGE 1 OF 2

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

0001 19 May 15 N/A

6.

ISSUED BY CODE

DLA ENERGY-AE

SP0600

7. ADMINISTERED BY (If other than Item 6) CODE

SP0600

8725 JOHN J. KINGMAN RD STE 4950

FT BELVOIR VA 22060-6222

BUYER/SYMBOL: CHELSEY HARRISON/DLA ENERGY-FEABB

PHONE: (703) 767-9457; FAX (703) 767-2382

8. NAME AND ADDRESS OF CONTRACTOR (NO., street,city,county,State,and ZIP Code)

X 9a. AMENDMENT OF SOLICITATION NO.

Notice of Opportunity/ SP0600-15-R-0414

9b. DATED (SEE ITEM 11) 07 May 15

10a. MODIFICATION OF CONTRACT/ORDER NO

DUNS: CAGE:

10b. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

[ X ]The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers [] is extended, [ X ] is not extended Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15, and returning 1 copies of the amendment;(b) By acknowledging receipt of this amendment on each copy of the offer submitted; or(c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b)

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

OTHER (Specify type of modification and authority) E. IMPORTANT: Contractor [] is not, [ ] is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

JB Charleston, Notice of Opportunity SP0600-15-R-0414

Response to a Request for Information from industry.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

16A. NAME OF CONTRACTING OFFICER

15B. NAME OF CONTRACTOR/OFFEROR

BY

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

BY

(Signature of Contracting Officer)

16C.DATE SIGNED

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV. 10-83)

PREVIOUS EDITION UNUSABLE Prescribed by GSA

SP0600-15-R-0414

Amendment 0001

The purpose of this amendment is to provide a response to RFI 001 received from industry for the Notice of Opportunity, SP0600-15-R-0414:

FIRST: The following RFI 001 has been received from industry and is addressed as follows:

RFI 001: Please clarify whether or not the required "EMCS line item cost estimate for each of the four (4) projects submitted under Factor 1" and the associated price per point, controller and the front-end should include markups.

RFI 001 RESPONSE: Yes, the EMCS line item cost estimate for each of the four (4) projects submitted under Factor 1 illustrating the cost for the associated price per point, controller and the front-end should include markups. ESCOs shall distinguish for each item each element of direct costs as well as their applied overhead, profit and any other indirect costs that were included. ESCOs shall also distinguish in their cost presentation for each project all costs associated with subcontractor efforts.

SECOND: All other terms and conditions remain as previously stated.