Solicitation-SP060014R0201.pdf
PDF 4 MB Posted
- Solicitation number
- SP0600-14-R-0201
- Issued by
-
Defense Logistics Agency Energy
About this file
Solicitation__SP060014R0201
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_-_0001.pdf | ||
| Amendment_-_0001.pdf | ||
| OSP-SP060014R0201.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 1449 (10-95)
Prescribed by GSAFAR (48 CPR) 53.212
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
1. REQUISITION NUMBER
2. CONTRACT NO.
3.AWARD/EFFECTIVE
DATE
4. ORDER NUMBER
5. SOLICITATION NUMBER
SP0600-14-R-0201
6. SOLICITATION ISSUE
DATE : 9 December 2013
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME: Jastar Singh EMAIL: DLAE-PCB@dla.mil
b. TELEPHONE NUMBER (no collect calls)
(703) 767-9509
8. OFFER DUE DATE/
20 December 2013
3:00 P.M. Ft. Belvoir
9. ISSUED BY CODE SP0600 10. THIS ACQUISITION IS 11. DELIVERY FOR
FOB
12. DISCOUNT TERMS
DLA-Energy 8725 John J. Kingman Rd., Suite 4950 Fort Belvoir, VA 22060-6222
UNRESTRICTED
SET ASIDE % FOR
DESTINATION
UNLESS BLOCK IS
MARKED
SEE SCHEDULE
Buyer/Symbol: Jastar Singh/DLA Energy FEPDB SMALL BUSINESS
HUBZONE SMALL
BUSINESS
8(A)
13a. THIS CONTRACT IS RATED ORDER
UNDER DPAS (15 CFR 700)
Phone: (703)767-9509 13b. RATING
Email: DLAE-PCB@dla.mil
NAICS: 324110
14. METHOD OF SOLICITATION Full and Open
P.P: 1.99U AFGHANISTAN
SIZE STANDARD:
RFQ IFB RFP
15. DELIVER TO CODE 16. ADMINISTERED BY CODE SP0600
See Clause B-0001 B1.05
Same as Block 9
17a. CONTRACTOR /
OFFEROR CODE
FACILITY
CODE
18a. PAYMENT WILL BE MADE BY CODE 19R2AA
DUNS:
TELEPHONE NO
FAX NO.
JUAN J. FERNANDEZ
US EMBASSY, FMO
KABUL, AFGHANISTAN
FERNANDEJJ@STATE.GOV
AFGHANISTAN, APO AE 09806
93(0)700 107 846
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS
IN OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK BELOW IS
CHECKED SEE ADDENDUM
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
SEE CLAUSE B-0001 B1.05
Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA
26. TOTAL AWARD AMOUNT (For Govt. Use Only)
ESTIMATED: $
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA ARE ARE NOT ATTACHED., 27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED.
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN ___1__ COPIES
TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER ALL ITEMS
SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL SHEETS
SUBJECT TO THE TERMS AND CONDITIONS AND CONDITIONS SPECIFIED HEREIN.
29. AWARD OF CONTRACT: REF. ____________OFFER DATED ___________
YOUR OFFER ON SOLICITATION _____________, INCLUDING ANY ADDITIONS
OR CHANGES WHICH ARE SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT)
30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT)
JONATHAN MOORE
31c. DATE SIGNED
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED
32b. SIGNATURE OF AUTHORIZED GOVT.
REPRESENTATIVE
32c. DATE
SIGNED
32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE
32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
33. SHIP NUMBER
34. VOUCHER NUMBER 35. AMOUNT VERIFIED
CORRECT FOR
36. PAYMENT
COMPLETE PARTIAL FINAL
37. CHECK NUMBER
PARTIAL FINAL
38. S/R ACCOUNT NUMBER
39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT 42a. RECEIVED BY (Print)
41b. SIGNATURE AND TITLE OF CERTIFYING
41c. DATE 42b. RECEIVED AT (Location)
42c. DATE REC’D (YY/MM/DD)
42d. TOTAL CONTAINERS mailto:FERNANDEJJ@state.gov
FPH1448
Text Box
SP0600-14-1088
FPH1448
Typewritten Text
FPH1448
Typewritten Text
FPH1448
Typewritten Text
RFP: SP0600-14-R-0201
B-0001 B1.05 SUPPLIES TO BE FURNISHED (OVERSEAS PC&S) (ALASKA/HAWAII) (DLA ENERGY JAN 2012)
B-0002 B19.02 ECONOMIC PRICE ADJUSTMENT (OVERSEAS) (DLA ENERGY JAN 2012)
SECTION C DESCRIPTION/SPECIFICATIONS/PERFORMANCE WORK STATEMENT
C-0001 C1 SPECIFICATIONS (DLA ENERGY JAN 2012)
C-0002 C16.18-25 GASOLINE, AUTOMOTIVE, UNLEADED (AFGHANISTAN/PAKISTAN) (DLA ENERGY AUG 2010) .. 9 C-0003 C16.26-14 FUEL OIL, DIESEL (GOST 305-82) SUMMER (L) AND WINTER (Z) GRADES(PC&S)(EURASIA) (DLA
ENERGY MAR 2008)
SECTION E INSPECTION AND ACCEPTANCE
FAR 52.211-16 VARIATION IN QUANTITY (APR 1984)
FAR 52.246-2 INSPECTION OF SUPPLIES -- FIXED-PRICE (AUG. 1996)
DLAD 52.246-9029 INSPECTION AND ACCEPTANCE POINTS (APR 2010)
E-0001 E1 CONTRACTOR INSPECTION RESPONSIBILITIES (DLA ENERGY SEP 2013)
E-0002 E21.01 POINT OF INSPECTION (DLA ENERGY APR 2010)
E-0003 E22 LIST OF INSPECTION OFFICES FOR DLA ENERGY CONTRACTS (DLA ENERGY JUL 2013)
E-0004 E35 NONCONFORMING SUPPLIES AND SERVICES (DLA ENERGY DEC 2011)
E-0005 E37 SOURCE RESTRICTION AND SOURCE INSPECTION (PC&S) (DLA ENERGY DEC 2011)
SECTION F DELIVERIES AND PERFORMANCE
FAR 52.247-34 F.O.B. DESTINATION (NOV 1991)
5152.225-5905 CONTRACT DELIVERY REQUIREMENTS (AUG 2011)
F-0001 F1.01-1 DELIVERY CONDITIONS FOR TRANSPORT TRUCKS, TRUCKS AND TRAILERS, AND TANK
WAGONS (DLA ENERGY JAN 2012)
F-0002 F1.05 GENERAL SHIPPING CONDITIONS (DLA ENERGY OCT 1997)
F-0003 F1.09-8 DETERMINATION OF INVOICE QUANTITY (PC&S) (MIDDLE EAST) (DLA ENERGY SEP 2005) F-0004 F3.03 NOTIFICATION OF CHANGE IN TRANSPORTATION COMPANY (PC&S) (DLA ENERGY APR 2005)
F-0005 F4 DELIVERY AND ORDERING PERIODS (DLA ENERGY JUN 2002)
F-0006 F30.01 ORDERING AND PAYING OFFICERS (OVERSEAS PC&S) (DLA ENERGY APR 1998)
F-0007 F51 SHIPMENT AND ROUTING (OVERSEAS) (DLA ENERGY NOV 2005)
FAR 52.204-7 SYSTEM FOR AWARD MANAGEMENT (JUL 2013)
FAR 52.229-6 TAXES -- FOREIGN FIXED-PRICE CONTRACTS (FEB 2013)
FAR 52.232-17 INTEREST (OCT 2010)
FAR 52.216-21 REQUIREMENTS (OCT 1995)
FAR 52.216-18 ORDERING (OCT 1995)
FAR 52.232-35 DESIGNATION OF OFFICE FOR GOVERNMENT RECEIPT OF ELECTRONIC FUNDS TRANSFER
INFORMATION (JUL 2013)
G-0001 G3 INVOICE NUMBERING REQUIREMENTS (DLA ENERGY AUG 1998)
G-0006 G150.07-2 SUBMISSION OF INVOICES FOR PAYMENT (OVERSEAS PC&S) (DLA ENERGY JAN 2012)
SECTION I CONTRACT CLAUSES
FAR 52.212-4 CONTRACT TERMS AND CONDITIONS - COMMERCIAL ITEMS (PC&S) (NON-PORTS INTERNET
APPLICATION) (DLA ENERGY SEP 2013) (TAILORED)
FAR 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE
ORDERS -- COMMERCIAL ITEMS (SEP 2013)
DFARS 252.225-7043 ANTITERRORISM/FORCE PROTECTION FOR DEFENSE CONTRACTORS OUTSIDE THE UNITED
STATES (MAR 2006)
DFARS 252.225-7993 PROHIBITION ON CONTRACTING WITH THE ENEMY IN THE UNITED STATES CENTRAL COMMAND
THEATER OF OPERATIONS (DEVIATION 2012-O0005)(JAN 2012)
DFARS 252.225-7994 ADDITIONAL ACCESS TO CONTRACTOR AND SUBCONTRACTOR RECORDS IN THE UNITED STATES
CENTRAL COMMAND THEATER OF OPERATIONS (DEVIATION 2012-O0005) (JAN 2012)
DFARS 252.225-7995 CONTRACTOR PERSONNEL PERFORMING IN THE UNITED STATES CENTRAL COMMAND AREA OF
RESPONSIBILITY (DEVIATION 2011-O0004) (APR 2011)
252.229-7999 TAXES - FOREIGN CONTRACTS IN AFGHANISTAN (DEVIATION 2013-00016) (JULY 2013) 252.232-7999 NOTIFICATION OF PAYMENT IN LOCAL CURRENCY (AFGHANISTAN) (APR 2013) (DEVIATION 2013-
O0011)
DLAD 52.212-9000 CHANGES MILITARY READINESS (NOV 2011)
5152.225-5902 FITNESS FOR DUTY AND MEDICAL/DENTAL CARE LIMITATIONS (DEC 2011)
5152.225-5903 COMPLIANCE WITH LAWS AND REGULATIONS (DEC 2011)
5152.225-5907 MEDICAL SCREENING AND VACCINATION REQUIREMENTS FOR CONTRACTOR EMPLOYEES
OPERATING IN THE CENTCOM AREA OF RESPONSIBILITY (AOR) (DEC 2011)
252.225-7998 CONTRACTOR DEMOBILIZATION (DEVIATION 2013-O0017) (AUGUST 2013)
5152.225-5915 CONTRACTOR ACCOUNTABILITY AND PERSONNEL RECOVERY (AUG 2011)
5152.225-5914 COMMODITY SHIPPING INSTRUCTIONS (AUG 2011)
Table of Contents
5152.232-5900 PAYMENT IN LOCAL CURRENCY (DEC 2011)
I-0001 I1.01 DEFINITIONS (DLA ENERGY JUN 2009)
I-0002 I11.01-2 ADMINISTRATIVE COST OF TERMINATION FOR CAUSE COMMERCIAL ITEMS (DLA ENERGY
FEB 1996)
I-0003 I186 PROTECTION OF GOVERNMENT PROPERTY AND SPILL PREVENTION (DLA ENERGY FEB 2009) I-0004 I190.06 MATERIAL SAFETY DATA SHEETS - COMMERCIAL ITEMS (DLA ENERGY APR 2006)
I-0005 I209.09 EXTENSION PROVISIONS (DLA ENERGY JAN 2012)
I-0006 I209.18 OPTION TO EXTEND THE TERM OF THE CONTRACT (DLA ENERGY JAN 2012)
I-0007 I385 NOTIFICATION OF CONTRACTING OFFICER IN THE EVENT OF DISCOVERY OF EVIDENCE
OFFRAUD UNDER THE CONTRACT (DLA ENERGY JUL 2008)
SECTION J LIST OF ATTACHMENTS
SECTION K - REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF OFFERORS OR QUOTERS
FAR 52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS-COMMERCIAL ITEMS (AUG 2013) DFARS 252.209-7001 DISCLOSURE OF OWNERSHIP OR CONTROL BY THE GOVERNMENT OF A TERRORIST COUNTRY
(JAN 2009)
DFARS 252.212-7000 OFFEROR REPRESENTATIONS AND CERTIFICATIONS--COMMERCIAL ITEMS (JUN 2005)
DFARS 252.225-7020 TRADE AGREEMENTS CERTIFICATE (JAN 2005)
K-0001 K15 RELEASE OF PRICES (DLA ENERGY MAR 2009)
K-0002 K45.01 FACSIMILE OR ELECTRONIC INVOICING (DLA ENERGY JAN 2012)
K-0003 K86 FOREIGN TAXES (DLA ENERGY JAN 2012)
SECTION L INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERS OR QUOTERS
FAR 52.212-1 INSTRUCTIONS TO OFFERORS COMMERCIAL ITEMS (PC&S) (TAILORED) (DLA ENERGY) (JUL 2013) 66
FAR 52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE (APR 1991)
FAR 52.214-35 SUBMISSION OF OFFERS IN U.S. CURRENCY (TAILORED)(APR 1991)
FAR 52.216-1 TYPE OF CONTRACT (APR 1984)
FAR 52.232-38 SUBMISSION OF ELECTRONIC FUNDS TRANSFER INFORMATION WITH OFFER (JUL 2013)
DLAD 52.233-9000 AGENCY PROTESTS (NOV 2011)
DLAD 52.233-9001 DISPUTES: AGREEMENT TO USE ALTERNATIVE DISPUTE RESOLUTION (NOV 2011)
L-0001 L2.11-4 E-MAIL PROPOSALS (DLA ENERGY OCT 2010)
L-0002 L54 SITE VISIT (DLA ENERGY OCT 1992)
L-0003 L117 NOTIFICATION OF TRANSPORTATION COMPANY TO BE UTILIZED IN THE DELIVERY OF
PRODUCT (PC&S) (DLA ENERGY JAN 2012)
SECTION M EVALUATION FACTORS FOR AWARD
52.215-9023 REVERSE AUCTION (OCT 2013)
M-0001 M3.01 EVALUATION OF OFFERS WHERE UNCOMMON ESCALATORS ARE USED (DLA ENERGY JAN 1998)
M-0002 M55 CONVERSION FACTORS (DLA ENERGY MAR 2007)
M-0003 M72.03-3. 100 EVALUATION FACTORS FOR BEST OVERALL VALUE (PC&S) (AFGHANISTAN) (DLA ENERGY NOV
2013)
B-0001 B1.05 SUPPLIES TO BE FURNISHED (OVERSEAS PC&S) (ALASKA/HAWAII) (DLA ENERGY JAN 2012)
(a) The supplies to be furnished during the period specified in the REQUIREMENTS clause, the delivery points, methods of delivery, and estimated quantities are shown below. The quantities shown are best estimates of required quantities only. Unless otherwise specified, the total quantity ordered and required to be delivered may be greater than or less than such quantities. The Government agrees to order from the Contractor and the Contractor shall, if ordered, deliver during the contract period all items awarded under this contract. The prices paid shall be the unit prices specified in subsequent price change modifications issued in accordance with the ECONOMIC PRICE ADJUSTMENT contract provision.
(b) In an emergency, oral orders may be issued and must be confirmed in writing by a Standard Form 1449 or DD Form 1155 within 24 hours.
(c) Offers shall not be submitted for quantities less than the estimated quantities specified below for each line item.
Offers submitted for less than the estimated quantities will not be considered for award, except for items specifically designated as a 2 -year requirement.
BASE YEARS:
SUPPLIES, DELIVERY POINTS, REQUIREMENT
ITEMS AND METHOD OF DELIVERY ESTIMATED QUANTITY PRICE
100 US EMBASSY, KABUL, AFGHANISTAN
KABUL AF, DS, DEPARTMENT OF STATE
DELIVERY FEDAAC: 19R2AA
BILLING FEDAAC: 19R2AA
ORDERING OFFICE: 01193706644525
ORDERING FEDAAC: 19R2AA
PAYMENT OFFICE: JUAN J. FERNANDEZ
AMERICAN EMBASSY, FMO, KABUL,
AFGHANISTAN DPO, AE 09806
FERNANDEJJ@state.gov
100-KD DIESEL FUEL (SPEC GOST 305-82) NSN: 9140- 01-492-7612 5,632,446 USG $________
OR COMMERCIAL EQUIVALENT
FOB TANK TRUCK (FOBTT), US EMBASSY
FUEL TRUCK WILL PICK-UP FUEL FROM
CONTRACTOR’S FACILITY DURING REGULAR WORDAYS
AND HOURS (SUNDAY – THURSDAY, 0800-1630).
TRUCK SIZES: 3,000 USG GRAVITY DRAIN, 5,500 USG GRAVITY DRAIN,
9,000 USG GRAVITY DRAIN. THE CONTRACTOR MUST BE ABLE TO MAKE
EMERGENCY ISSUES AT ANY TIME. LOADING RACK TICKET REQUIRED FOR EACH LOAD.
THIS FUEL IS NOT CAPITALIZED
NOTE: Contractor facility loading point must be within Kabul City Limits
100-KD1 DIESEL FUEL (SPEC GOST 305-82) NSN: 9140-01-492-7612 1,600,000 USG $________
TANK TRUCK (TT) INTO 1/6,000 GALLON TANK. THE CONTRACTOR
TO DELIVER FUEL TO EMBASSY FUEL STATION DURING REGULAR
WORKDAYS AND HOURS (SUNDAY-THURSDAY), 0800-1630).
THE CONTRACTOR MUST BE ABLE TO MAKE EMERGENCY DELIVERIES AT ANY TIME.
EXTERNAL CONNECTION IS A 2” FEMALE CAM AND GROOVE.
MULTIPLE METER DELIVERY TICKET REQUIRED.
100-PG UNLEADED, AUTOMOTIVE GASOLINE NSN: 9130-01-526-4844 104,000 USG $________
TANK WAGON (TW) INTO 1/6,000 GALLON TANK.
CONTRACTOR TO DELIVER FUEL TO EMBASSY FUEL STATION
DURING REGULAR WORKDAYS AND HOURS (SUNDAY-THURSDAY),
0800-1630). HOWEVER CONTRACTOR MUST BE ABLE TO MAKE
EMERGENCY DELIVERIES AT ANY TIME.
EXTERNAL CONNECTION IS A 2” FEMALE CAM AND GROOVE.
MULTIPLE METER DELIVERY TICKET REQUIRED.
ITEMS AND METHOD OF DELIVERY ESTIMATED QUANTITY PRICE
101 U.S. CONSULATE, HERAT BAGHE-E-MALAT ROAD OS, DS AFGHANISTAN
DELIVERY FEDAAC: 19R2AA
ORDERING FEDAAC: 19R2AA
ORDERING OFFICE: 0793-370-942
PAYING OFFICE: FINANCIAL MANAGEMENT OFFICE,
U.S. EMBASSY KABUL, AFGHANISTAN
SCHUCHJ@STATE.GOV
JOHN SCHUCH, GSO, U.S. CONSULATE, HEART
101-KD DIESEL FUEL (SPEC GOST 305-82) 2,028,000 USG $_________
TANK TRUCK (TT), W/PUMP & METER
INTO TWO ABOVE THE GROUND TANKS WITH REMOTE FILL
POINTS, ONE SERVES THE GENERATOR THE OTHER THE BOILER.
REFILL METHOD IS GRAVITY FEED WITH A CAM LOCK CONNECTION.
TRUCKS NEEDS TO PROVIDE A STANDARD EUROPEAN-STYLE LOCKING
MECHANISM TO CONNECT WITH REMEOTE FILL POINTS.
METERED DELIVERY TICKET REQUIRED
DELIVERY HOURS: 0830-1630 SUNDAY THRU THURSDAY
THE CONTRACTOR MUST BE ABLE TO MAKE EMERGENCY DELIVERIES AT ANY TIME.
OPTION - I
ITEMS AND METHOD OF DELIVERY ESTIMATED QUANTITY PRICE
100 US EMBASSY, KABUL, AFGHANISTAN
KABUL AF, DS, DEPARTMENT OF STATE
DELIVERY FEDAAC: 19R2AA
BILLING FEDAAC: 19R2AA
ORDERING OFFICE: 01193706644525
ORDERING FEDAAC: 19R2AA
PAYMENT OFFICE: JUAN J. FERNANDEZ
AMERICAN EMBASSY, FMO, KABUL,
AFGHANISTAN DPO, AE 09806
FERNANDEJJ@state.gov
100-KD DIESEL FUEL (SPEC GOST 305-82) NSN: 9140- 01-492-7612 3,766,026 USG $________
FOB TANK TRUCK (FOBTT), US EMBASSY
FUEL TRUCK WILL PICK-UP FUEL FROM
CONTRACTOR’S FACILITY DURING REGULAR WORDAYS
AND HOURS (SUNDAY – THURSDAY, 0800-1630).
TRUCK SIZES: 3,000 USG GRAVITY DRAIN, 5,500 USG GRAVITY DRAIN,
9,000 USG GRAVITY DRAIN. THE CONTRACTOR MUST BE ABLE TO MAKE
EMERGENCY ISSUES AT ANY TIME. LOADING RACK TICKET REQUIRED FOR EACH LOAD.
NOTE: Contractor facility loading point must be within Kabul City Limits
100-KD1 DIESEL FUEL (SPEC GOST 305-82) NSN: 9140-01-492-7612 800,000 USG $________
TANK TRUCK (TT) INTO 1/6,000 GALLON TANK. THE CONTRACTOR
TO DELIVER FUEL TO EMBASSY FUEL STATION DURING REGULAR
WORKDAYS AND HOURS (SUNDAY-THURSDAY), 0800-1630).
THE CONTRACTOR MUST BE ABLE TO MAKE EMERGENCY DELIVERIES AT ANY TIME.
EXTERNAL CONNECTION IS A 2” FEMALE CAM AND GROOVE.
MULTIPLE METER DELIVERY TICKET REQUIRED.
ITEMS AND METHOD OF DELIVERY ESTIMATED QUANTITY PRICE
100-PG UNLEADED, AUTOMOTIVE GASOLINE NSN: 9130-01-526-4844 52,000 USG $________
TANK WAGON (TW) INTO 1/6,000 GALLON TANK.
CONTRACTOR TO DELIVER FUEL TO EMBASSY FUEL STATION
DURING REGULAR WORKDAYS AND HOURS (SUNDAY-THURSDAY),
0800-1630). HOWEVER CONTRACTOR MUST BE ABLE TO MAKE
EMERGENCY DELIVERIES AT ANY TIME.
EXTERNAL CONNECTION IS A 2” FEMALE CAM AND GROOVE.
MULTIPLE METER DELIVERY TICKET REQUIRED.
101 U.S. CONSULATE, HERAT BAGHE-E-MALAT ROAD OS, DS AFGHANISTAN
DELIVERY FEDAAC: 19R2AA
ORDERING FEDAAC: 19R2AA
ORDERING OFFICE: 0793-370-942
PAYING OFFICE: FINANCIAL MANAGEMENT OFFICE,
U.S. EMBASSY KABUL, AFGHANISTAN
ERIC FLAXMAN, U.S. CONSULATE, HERAT
flaxmaneg@state.gov
101-KD DIESEL FUEL (SPEC GOST 305-82) 1,014,000 USG $_________
TANK TRUCK (TT), W/PUMP & METER
INTO TWO ABOVE THE GROUND TANKS WITH REMOTE FILL
POINTS, ONE SERVES THE GENERATOR THE OTHER THE BOILER.
REFILL METHOD IS GRAVITY FEED WITH A CAM LOCK CONNECTION.
TRUCKS NEEDS TO PROVIDE A STANDARD EUROPEAN-STYLE LOCKING
MECHANISM TO CONNECT WITH REMEOTE FILL POINTS.
METERED DELIVERY TICKET REQUIRED
DELIVERY HOURS: 0830-1630 SUNDAY THRU THURSDAY
THE CONTRACTOR MUST BE ABLE TO MAKE EMERGENCY DELIVERIES AT ANY TIME.
General Notes:
1. For contract line items (CLINS) 101-KD1 and 100-PG, Contractor will be delivering fuel to the U.S. Embassy, Kabul, Afghanistan.
2. CLINS 100-KD, 100-KD1, and 100-PG shall be sourced from Western or Northern supply routes into Afghanistan.
3. The contractor selected for award shall be ready to deliver fuel in accordance with the contract requirement by 01 MAY 2014.
4. Offerors submitting proposals that include the use of Armed Private Security Companies will not be considered for an award.
5. Contractor shall coordinate any need for use of armed private security through the Afghan Ministry of Interior (MOI).
6. Force protection requirements are in full effect under this contract at all times. There may be excessive wait times outside the gates of all U.S. Government locations. This may include mandatory “cool down” periods of 24 hours or more. Detention charges should be accounted for in contract price as any claims for detention will not be paid.
7. DO NOT include any taxes in the offered prices for which the U.S. Government is tax exempt.
8. If an offer price is submitted on any one of the diesel items, an offer price must be submitted on each of the other items.
DLA ENERGY intends to award these diesel items together on an “All or None” basis.
9. DLA ENERGY anticipates the possibility of making multiple awards for each of the above line items.
10. Offerors submitting electronic responses to this solicitation must limit email size to 10MB for a single email. Emails over 10MB may not be delivered because of server restriction on mail size for delivery.
11. Exceptions: Any exceptions the offeror takes to the terms and conditions of the solicitation must be submitted with the offer.
Offerors shall submit all exceptions taken in list format. Only exceptions detailed in the offer will be treated as exceptions to the terms and conditions of the solicitation. Any exceptions taken by the offeror will be considered by the Government and either accepted or rejected. Exceptions that are accepted by the Government will be incorporated into any resultant contract; exceptions that are rejected by the Government must be withdrawn by the offeror or the offer will be rejected. If the offeror does not take any exceptions, completion of blocks 12, 17 through 24, and 30 of the SF 1449 signifies the offeror’s agreement to the terms and conditions contained in the solicitation.
mailto:flaxmaneg@state.gov
B-0002 B19.02 ECONOMIC PRICE ADJUSTMENT (OVERSEAS) (DLA ENERGY JAN 2012)
(a) WARRANTIES. The Contractor warrants that--
(1) The unit prices set forth in the Schedule do not include allowances for any portion of the contingency covered by this contract provision; and
(2) The prices to be invoiced hereunder shall be computed in accordance with the provisions of this contract.
(b) DEFINITIONS. As used throughout this contract provision, the term--
(1) Award price means the unit price offered by the Contractor and set forth opposite the item in the Schedule.
(2) Reference price means the market price, this is either published in an independent publication or supplied by the Contractor, with which the award price is to fluctuate. The reference price should be a market price for the same or similar product(s) as the item being purchased.
(3) Date of delivery means--
(i) FOR TANKER OR BARGE DELIVERIES.
(A) F.O.B. ORIGIN. The date and time vessel commences loading;
(B) F.O.B. DESTINATION. The date and time vessel commences discharging;
(ii) FOR PIPELINE DELIVERIES. The date and time product commences to move past the specified f.o.b. point; and
(iii) FOR ALL OTHER TYPES OF DELIVERIES. The date product is received.
(c) ADJUSTMENTS. The prices payable under this contract shall be the award price increased or decreased by the amount, determined according to the following formula that the reference price shall have increased or decreased, to and including the date of delivery.
(1) The amount of increase or decrease in the award price shall be based on the same number of cents, or fraction thereof, that the reference price increases or decreases per like unit of measure.
(2) The reference price with which the award price for the listed item is to fluctuate (and which is more fully defined in the Table below) is-- [ ] (i) The low price published in ________________________________________________________.
(Name of publication)
[X] (ii) The average of the prices published in _________PLATTS OILGRAM__________________ (Name of publication)
[ ] (iii) The established price posted by_________________________________________________ and (Name of company) published in _________________________________________________________ (name of publication)
(3) COMMERCIAL. For price adjustments utilizing commercial publications such as Platts Oilgram, etc., the reference price in effect on the date of delivery shall be that item’s reference price that is in effect for the dates in the Table below.
If an effective date is not cited in a publication, then the date of publication shall apply. An increase or decrease in any reference price published in a trade price service or in a commercial journal shall apply only to deliveries made on or after the effective date of such trade price service or commercial journal. In the event of a holiday for which an effective date is not used, the latest effective price(s) prior to the effective date shall be used. NOTE: Platts issues corrections to its published prices on a regular basis. Platts posts corrections to its website (www.platts.com) for its subscribers. If a correction to a reference price is found on the Platts website, all of the items that use that reference price will be corrected. DLA Energy will correct any other reference prices, as notice of the correction is received. DLA Energy will work with the pricing services to determine the appropriate price, whenever an offeror or contractor can show that the price referenced should be reviewed.
(4) NONCOMMERCIAL (NOTIFICATION). For price adjustments utilizing a reference price indicator other than commercial publications such as Platts Oilgram, the Contractor shall notify the Contracting Officer of any changes in the reference price in writing within 15 calendar days from the date thereof.
(i) INCREASES. Any increase in unit price as a result of an increase in reference price shall apply only to deliveries made on or after the date of receipt by the Contracting Officer of a written notification from the Contractor of such increase. However, the prices payable under this contract shall in no event exceed the Contractor’s posted or established selling price in effect on the date of delivery for the product supplied in the form of delivery made at the point of delivery. Also, no http://www.platts.com/ notification incorporating an increase in a contract unit price shall be executed pursuant to this contract provision until the increase has been verified by the Contracting Officer.
(ii) DECREASES. If the Contractor fails to notify the Contracting Officer of any decrease in the reference price, within the allotted 15 day period, such decrease shall apply to all deliveries made on or after the effective date of such decrease. However, if any overpayment is made to the Contractor as a result of the Contractor’s failure to give timely notice to the Contracting Officer of any decrease in the established price, the Contractor shall be charged interest on such overpayment from the date of the overpayment to the date of reimbursement by the Contractor for the overpayment in accordance with the Disputes paragraph of the CONTRACT TERMS AND CONDITIONS – COMMERICAL ITEMS clause of this contract.
(5) Where the reference price is the Contractor’s established price (see (c)(2)(iii) above), the Contractor warrants that the product selected is one for which, except for modification required by the specifications of this contract, the Contractor has an established price. Such price is the net price after applying any applicable standard trade discounts offered by the Contractor for its catalog, list, or schedule price. The Contractor further warrants that, as of the current date, any differences between the unit prices of the line items identified in the Schedule and the Contractor's established price for like quantities of the nearest commercial equivalents of such contract items are due to compliance with contract specifications and to compliance with any requirements that this contract may contain for preservation, packaging, and packing beyond standard commercial practice.
(d) MODIFICATIONS. Any resultant price changes shall be provided via notification through contract modifications and/or postings to the DLA Energy web page at http://www.desc.dla.mil under the heading Vendor Resources and then Product Price Adjustments.
(e) FAILURE TO DELIVER. Notwithstanding any other conditions of this contract provision, no upward adjustment shall apply to product scheduled under the contract to be delivered before the effective date of the adjustment, unless the Contractor’s failure to deliver according to the delivery schedule results from causes beyond the Contractor’s control and without its fault or negligence, within the meaning of the Excusable Delays and Termination for Cause paragraphs of the CONTRACT TERMS AND CONDITONS – COMMERCIAL ITEMS clause of the this contract in which case the contract shall be amended to make an equitable extension of the delivery schedule.
(f) UPWARD CEILING ON ECONOMIC PRICE ADJUSTMENT. The Contractor agrees that the total increase in any contract unit price pursuant to these economic price adjustment provisions shall not exceed 375 percent of the award price, except as provided hereafter:
(1) If at any time the Contractor has reason to believe that within the near future a price adjustment under the conditions of this contract provision will be required that will exceed the current contract ceiling price for any item, the Contractor shall promptly notify the Contracting Officer in writing of the expected increase. The notification shall include a revised ceiling the Contractor believes is sufficient to permit completion of remaining contract performance, along with appropriate explanation and documentation as required by the Contracting Officer.
(2) If an actual increase in the reference price would raise a contract unit price for an item above the current ceiling, the Contractor shall have no obligation under this contract to fill pending or future orders for such item, as of the effective date of the increase, unless the Contracting Officer issues a contract modification to raise the ceiling. If the contract ceiling will not be raised, the Contracting Officer shall so promptly notify the Contractor in writing.
(g) REVISION OF REFERENCE PRICE INDICATOR. In the event—
(1) Any applicable reference price is discontinued or its method of derivation is altered substantially;
(2) The reference price is an average of published or posted prices, and any one price ceases to be published or posted;
(3) The reference price is published in a trade price service or commercial journal and such publication ceases to publish said reference price or changes its method of quoting prices; or
(4) The Contracting Officer determines that the reference price consistently and substantially failed to reflect market conditions— the parties shall mutually agree upon an appropriate and comparable substitute for determining the price adjustment described hereunder. The contract shall be modified to reflect such substitute effective on the date the indicator was discontinued, altered, or began to consistently and substantially fail to reflect market conditions. If the parties fail to agree on an appropriate substitute, the matter shall be resolved in accordance with the Disputes paragraph of the CONTRACT TERMS AND CONDITIONS – COMMERCIAL ITEMS clause of this contract.
(h) CONVERSION FACTORS. If this contract provision requires quantity conversion for economic price adjustment purposes, the conversion factors for applicable products, as specified in the CONVERSION FACTORS contract provision, apply unless otherwise specified in the Schedule.
http://www.desc.dla.mil/
(i) EXAMINATION OF RECORDS. The Contractor agrees that the Contracting Officer or designated representatives shall have the right to examine the Contractor’s books, records, documents, or other data the Contracting Officer deems necessary to verify Contractor adherence to the provisions of this contract provision.
(j) FINAL INVOICE. The Contractor shall include a statement on the final invoice that the amounts invoiced hereunder have applied all decreases required by this contract provision.
(k) TABLE.
I II III IV V VI VII
Name of If company - Reference Max Price company/ name of product; Method of price payable under publication If publication - delivery as of this contract (identify heading under applicable 1 NOV 2013 (includes any Item No. by number which reference Location where to the (date) tax included (listed from (c)(2) price is published reference price reference (exclude in the award items) above) and name of product is applicable price all taxes price .
100-KD PLATTS GASOIL FOB Arab Gulf CARGO $2.886038 See Paragraph (f) above 100-KD1 PLATTS GASOIL FOB Arab Gulf CARGO $2.886038 See Paragraph (f) above 100-PG PLATTS PREM UNLD FOB Arab Gulf CARGO $2.654880 See Paragraph (f) Above 101-KD PLATTS GASOIL FOB Arab Gulf CARGO $2.886038 See Paragraph (f) above
NOTE: Contractor shall notify the Embassy of the new price(s) on the 1st of each month in order to allow the Embassy to obligate funds.
Product prices will escalate monthly based on the average of high and low assessments contained in the Platt’s publication of each month in which deliveries are made. Therefore, the effective price for the period of the 1st through the 30th /31st will be the average of the high and low assessments for the previous month’s assessments posted on the 1st of each month. Saturdays and Sundays shall be considered as Platt’s non-publication days. If assessments are not posted by Platt’s during the period that delivery was made due to a holiday or another occurrence, only the posted assessments for that period will be used in the calculation.
SECTION C – DESCRIPTION/SPECIFICATIONS/PERFORMANCE WORK STATEMENT
C-0001 C1 SPECIFICATIONS (DLA ENERGY JAN 2012)
Product to be supplied shall fully meet the requirements of the applicable specification(s) as indicated in the Supply Schedule, except as modified elsewhere in this contract. Unless otherwise indicated by the Contractor, prior to award and in accordance with the EVALUATION OF OFFERS contract provision, the product offered will be assumed to fully meet the applicable specification(s).
C-0002 C16.18-25 GASOLINE, AUTOMOTIVE, UNLEADED (AFGHANISTAN/PAKISTAN) (DLA ENERGY
AUG 2010)
Product shall conform to the following requirements:
TEST TEST METHOD TEST LIMIT
1. Color Visual Bluish Green/Pinkish
2. Appearance Visual Clear and free from water and suspended impurities
3. Distillation ASTM D 86 I.B.P C Report 10% Vol. Rec. @ C Max. 70 50% Vol. Rec. @ C Max. 125
90% Vol. Rec. @ C Max. 180 End Point Max. 205 Residue, Vol. % Max. 2
4. Reid Vapor Pressure @ 37.8C, Kpa (psi) ASTM D 323 Summer grade (Mar – Oct) Max. 62 (9) Winter grade (Nov – Feb) Max. 69 (10)
5. Existent gum (solvent washed), mg/100 ml ASTM D 381 Max. 4
6. Oxidation Stability (Induction Period), minutes ASTM D 525 Min. 240
7. Sulphur (Total), Wt. % ASTM D 1266 or Max. 0.1% ASTM D 4294 or
ASTM D 2622
8. Lead content g/Liter ASTM D 3341 or Max. 0.005
ASTM D 2547
9. Copper strip corrosion 3hr @ 50C ASTM D 130 Max. 1
10. Octane Number (Research) ASTM D 2699 Min. 87
11. Specific Gravity @ 15C (60F) ASTM D 1298 Max. 0.74
12. Dr. Test ASTM D 4952 Negative
13. Odour Marketable
C-0003 C16.26-14 FUEL OIL, DIESEL (GOST 305-82) SUMMER (L) AND WINTER (Z) GRADES
(PC&S)(EURASIA) (DLA ENERGY MAR 2008)
(a) The diesel fuel oil shall conform to the requirements of GOST 305-82 Specification Diesel Fuel, Second Edition, dated August 1983, with Amendment 1, approved April 1983, as modified below.
(1) The Contractor shall submit an English language version of the GOST 305-82 specification to the DLA Energy Contracting Officer as part of their offer submission package and the Contractor shall be required to provide fuel conforming to this version of the specification. In the event of a dispute, this English language version of GOST 305-82 shall govern.
(2) Notwithstanding the provisions contained in any notes or revisions to GOST 305-82, any deviations from the norm for the required grade must be agreed to in writing by the DLA Energy Contracting Officer
(3) The Contractor shall immediately notify the DLA Energy Contracting Officer in writing of any later revisions to GOST 305-82 that may affect the Contractor’s ability to supply fuel conforming to the requirements of this contract.
(b) Where GOST 305-82 provides for multiple courses of action, DLA Energy’s choice of options is provided below. For seasonal variations in specification, fuel must meet the specification applicable to the date the fuel is delivered.
(1) The solidification (pour) point shall not exceed the maximum acceptable values for the moderate climate zone. The fuel offered and delivered shall meet the following Seasonal Solidification (Pour) Point requirements as stated below:
Solidification (Pour) Point, oC GOST 20287-74 Amd P5.2 March 1 to October 31 (Grade L, Summer Diesel, Moderate Climate Zone) Max. -10 November 1 to February 29 (Grade Z, Winter Diesel, Moderate Climate Zone) Max. -25
(2) The cloud point shall not exceed the maximum acceptable values for the moderate climate zone. The fuel offered and delivered shall meet the following Seasonal Cloud Point requirements as stated below:
Cloud Point, oC GOST 6356-75 March 1 to October 31 (Grade L, Summer Diesel, Moderate Climate Zone) Max. -5 November 1 to February 29 (Grade Z, Winter Diesel, Moderate Climate Zone) Max. -15
(3) The flash point shall not be lower than the minimum acceptable values for general purpose diesel engines.
(4) Diesel fuel oil complying with either fuel type I (0.2) or fuel type II (0.5) limits for percent mass fraction of sulfur is acceptable.
(c) WORKMANSHIP AND APPEARANCE REQUIREMENT. The fuel shall be clear and bright and free of visible water and particulates at 25 degrees Celsius or ambient temperature, whichever is higher, per ASTM D 4176, procedure 1.
If the sample has no visible particulates, but is otherwise not “clear and bright” and/or contains free water per ASTM D 4176, procedure 1, then the product must meet the requirements of ASTM D 2709, 0.05 percent volume of water and sediment, maximum. If the sample fails ASTM D 4176, procedure 1, because it contains visible sediment or particulate matter, then the product must meet the requirement of IP 415 or ASTM D 6217, 24 milligrams per kilogram, maximum.
(d) REPORTS. The Contractor shall submit a copy of the latest full specification analysis from the supplying refinery for each batch of product lifted. Either English or Russian versions of this analysis are acceptable. This documentation shall be submitted to-
ATTN: DLA Energy-QT, ROOM 2954
DEFENSE LOGISTICS AGENCY ENERGY
8725 JOHN J. KINGMAN ROAD, SUITE 4950
FORT BELVOIR VA 22060-6222
SECTION E – INSPECTION AND ACCEPTANCE
FAR 52.211-16 VARIATION IN QUANTITY (APR 1984)
(a) A variation in the quantity of any item called for by this contract will not be accepted unless the variation has been caused by conditions of loading, shipping, or packing, or allowances in manufacturing processes, and then only to the extent, if any, specified in paragraph (b) of this clause.
(b) The permissible variation shall be limited to:
10 Percent increase
10 Percent decrease
THIS INCREASE OR DECREASE SHALL APPLY TO THE QUANTITY STATED IN EACH INDIVIDUAL DELIVERY ORDER.
FAR 52.246-2 INSPECTION OF SUPPLIES -- FIXED-PRICE (AUG. 1996)
(a) Definition. “Supplies,” as used in this clause, includes but is not limited to raw materials, components, intermediate assemblies, end products, and lots of supplies.
(b) The Contractor shall provide and maintain an inspection system acceptable to the Government covering supplies under this contract and shall tender to the Government for acceptance only supplies that have been inspected in accordance with the inspection system and have been found by the Contractor to be in conformity with contract requirements. As part of the system, the Contractor shall prepare records evidencing all inspections made under the system and the outcome. These records shall be kept complete and made available to the Government during contract performance and for as long afterwards as the contract requires. The Government may perform reviews and evaluations as reasonably necessary to ascertain compliance with this paragraph. These reviews and evaluations shall be conducted in a manner that will not unduly delay the contract work. The right of review, whether exercised or not, does not relieve the Contractor of the obligations under the contract.
(c) The Government has the right to inspect and test all supplies called for by the contract, to the extent practicable, at all places and times, including the period of manufacture, and in any event before acceptance. The Government shall perform inspections and tests in a manner that will not unduly delay the work. The Government assumes no contractual obligation to perform any inspection and test for the benefit of the Contractor unless specifically set forth elsewhere in this contract.
(d) If the Government performs inspection or test on the premises of the Contractor or a subcontractor, the Contractor shall furnish, and shall require subcontractors to furnish, at no increase in contract price, all reasonable facilities and assistance for the safe and convenient performance of these duties. Except as otherwise provided in the contract, the Government shall bear the expense of Government inspections or tests made at other than the Contractor’s or subcontractor’s premises; provided, that in case of rejection, the Government shall not be liable for any reduction in the value of inspection or test samples.
(e)
(1) When supplies are not ready at the time specified by the Contractor for inspection or test, the Contracting Officer may charge to the Contractor the additional cost of inspection or test.
(2) The Contracting Officer may also charge the Contractor for any additional cost of inspection or test when prior rejection makes reinspection or retest necessary.
(f) The Government has the right either to reject or to require correction of nonconforming supplies. Supplies are nonconforming when they are defective in material or workmanship or are otherwise not in conformity with contract requirements. The Government may reject nonconforming supplies with or without disposition instructions.
(g) The Contractor shall remove supplies rejected or required to be corrected. However, the Contracting Officer may require or permit correction in place, promptly after notice, by and at the expense of the Contractor. The Contractor shall not tender for acceptance corrected or rejected supplies without disclosing the former rejection or requirement for correction, and, when required, shall disclose the corrective action taken.
(h) If the Contractor fails to promptly remove, replace, or correct rejected supplies that are required to be removed or to be replaced or corrected, the Government may either
(1) by contract or otherwise, remove, replace, or correct the supplies and charge the cost to the Contractor or
(2) terminate the contract for default.
(i)Unless the Contractor corrects or replaces the supplies within the delivery schedule, the Contracting Officer may require their delivery and make an equitable price reduction. Failure to agree to a price reduction shall be a dispute.
(1) If this contract provides for the performance of Government quality assurance at source, and if requested by the Government, the Contractor shall furnish advance notification of the time --
(i) When Contractor inspection or tests will be performed in accordance with the terms and conditions of the contract; and
(ii) When the supplies will be ready for Government inspection.
(2) The Government’s request shall specify the period and method of the advance notification and the Government representative to whom it shall be furnished. Requests shall not require more than 2 workdays of advance notification if the Government representative is in residence in the Contractor’s plant, nor more than 7 workdays in other instances.
(j) The Government shall accept or reject supplies as promptly as practicable after delivery, unless otherwise provided in the contract. Government failure to inspect and accept or reject the supplies shall not relieve the Contractor from responsibility, nor impose liability on the Government, for nonconforming supplies.
(k) Inspections and tests by the Government do not relieve the Contractor of responsibility for defects or other failures to meet contract requirements discovered before acceptance. Acceptance shall be conclusive, except for latent defects, fraud, gross mistakes amounting to fraud, or as otherwise provided in the contract.
(l) If acceptance is not conclusive for any of the reasons in paragraph (k) hereof, the Government, in addition to any other rights and remedies provided by law, or under other provisions of this contract, shall have the right to require the Contractor
(1) at no increase in contract price, to correct or replace the defective or nonconforming supplies at the original point of delivery or at the Contractor’s plant at the Contracting Officer’s election, and in accordance with a reasonable delivery schedule as may be agreed upon between the Contractor and the Contracting Officer; provided, that the Contracting Officer may require a reduction in contract price if the Contractor fails to meet such delivery schedule, or
(2) within a reasonable time after receipt by the Contractor of notice of defects or nonconformance, to repay such portion of the initial contract prices, or, if it is established, the redetermined prices of this contract, as is equitable under the circumstances if the Contracting Officer elects not to require correction or replacement. When supplies are returned to the Contractor, the Contractor shall bear the transportation costs from the original point of delivery to the Contractor’s plant and return to the original point when that point is not the Contractor’s plant. If the Contractor fails to perform or act as required in (1) or (2) above and does not cure such failure within a period of 10 days (or such longer period as the Contracting Officer may authorize in writing) after receipt of notice from the Contracting Officer specifying such failure, the Government shall have the right by contract or otherwise to replace or correct such supplies and equitably reduce the initial contract prices, or, if it is established, the redetermined prices of this contract.
DLAD 52.246-9029 INSPECTION AND ACCEPTANCE POINTS (APR 2010)
(a) Inspection and Acceptance are:
Inspection point: [X] Destination [X] Origin [ ] Elsewhere Acceptance point: [X] Destination [X] Origin
E-0001 E1 CONTRACTOR INSPECTION RESPONSIBILITIES (DLA ENERGY SEP 2013)
(a) This contract provision applies to:
(1) All aviation fuel, lubricating oil, and additive shipments.
(2) All Bulk and Posts, Camps, and Stations non-aviation fuel shipments via pipeline or waterborne transport.
(b) QUALITY CONTROL PLAN.
(1) The Contractor is required to provide and maintain an inspection system, and a written description (Quality Control Plan (QCP)) of that system, acceptable to the Government. The Contractor has the option to provide and maintain an inspection system that, as a minimum, incorporates the requirements of ISO9001, Quality Management Systems. If the Contractor chooses to comply with the ISO9001 quality system requirements and format, all the specific Quality Assurance Provisions of this contract must be included in the resulting ISO9001 document that will serve as the QCP. A copy of the QCP, in English, shall be presented to the Government Quality Assurance Representative (QAR) for their review and acceptance prior to commencement of production or services. An acceptable QCP is required prior to Government inspection and acceptance of supplies or services. The QCP shall be reviewed and updated when deemed necessary by the Contractor or the Government, to include changes necessary to prevent the recurrence of quality problems. The Contractor must sign and date the original QCP, as well as each subsequent revision. Revisions shall also be presented to the QAR for review and acceptance prior to implementation. When acceptable to the Government, the original QCP, and any revisions, shall be signed and dated by the QAR.
(2) The Contractor shall require subcontractors to provide and maintain inspection systems adhere to all the requirements in this contract provision.
(3) The QCP shall include the identification of key operational positions, a schematic diagram of plant facilities pertinent to the inspection system, indicating all inspection points, and a description of the following operations related to the supplies or services to be furnished under the contract:
(i) RECEIVING, BLENDING AND COMPOUNDING. Procedures used to ensure the quality of additives blended into product supplied under this contract. Procedures to identify and ensure the quality of component base stocks used to produce finished product. Procedures to be used for adding, prior to batching, all required additives at all locations. When procedures for in-line blending of non-aviation products in accordance with the IN-LINE BLENDING OF NON-AVIATION PETROLEUM PRODUCTS contract provision are used, the QCP will provide for establishing blend ratios, and identify the responsible personnel within the Contractor's organization authorized to establish the blend ratios. When line injection of additives is required by the contract, the QCP will provide procedures for proportionately injecting additives throughout the entire loading process to ensure the additive is homogeneously blended into the product, as well as procedures for maintaining records evidencing the homogeneous blending of all line injected additives. In addition to the testing in (iii) below, a laboratory hand blend of jet fuel with all additives required by the contract shall be tested, prior to shipment, to verify compliance with the specification;
(ii) SAMPLING. Procedures for sampling additives, blend tanks, shipping tanks, lines, and conveyances/containers in accordance with API Manual of Petroleum Measurement Standards (MPMS), Chapter 8, Section 1, (ASTM D 4057) Manual Sampling of Petroleum and Petroleum Products, and/or Section 2, (ASTM D 4177) Automatic Sampling of Liquid Petroleum and Petroleum Products. Procedures include sample location, frequency, quantity, and retention. For all tanker, barge, and pipeline shipments, a flow-proportional sample taken in accordance with MPMS Chapter 8, Section 2, is preferred at the custody transfer point. However, manual samples taken in accordance with MPMS Chapter 8, Section 1 are acceptable provided that they are taken hourly throughout the shipment and that the quantity of the composite sample meets the requirements in Table II of this contract provision. See Table I, Minimum Sampling and Testing Requirements, and Table II, Sample Retention;
(iii) TESTING. Types of test series and individual test methods/procedures to be performed on samples taken from each location identified in (ii) above. See Table I, Minimum Sampling and Testing Requirements, and Table III, Definitions of Test Series;
(iv) CALIBRATION. Program for testing and measuring equipment in accordance with ISO 10012, Measurement Management Systems – Requirements for Measurement Processes and Measuring Equipment, or equivalent local regulation, as appropriate; and, a program for meters used to determine quantity complying with the API MPMS, Chapters 4, 5, and 6, or equivalent foreign standard. For items not covered by API, ASTM, or IP publications, the applicable manufacturer's recommended calibration method(s), outlined in the applicable industry publication, shall be used if acceptable to the Government;
(v) STORAGE AND HANDLING. Procedures for quality/quantity determination. Includes a description of storage and handling equipment, such as tanks, lines, valves, and manifolds; identification of dedicated/common product systems, including description of line segregation and controls to assure capability for proper gauging, sampling, draining of water, filtration, circulation, and drying; and identification of any other process/system used in maintaining product integrity during storage and handling;
(vi) LOADING AND SHIPPING – GENERAL. Procedures for product movement and related quality/quantity checks from shipping tank(s) to custody transfer point (CTP). Description of transfer system from shipping tank to CTP. A dedicated system, including lines, pumps, loading arms, and hoses, is preferred, but an isolated common system incorporating blind flanges, spectacle plates, or double valves between systems is acceptable. An isolated common system using single valves designed to ensure positive isolation, such as twin seal single valves, are also acceptable. Systems with single valve (other than twin seal) isolation require specific procedures be included in the QCP to ensure product integrity prior to the CTP.
When single valves (other than twin seal) are present in the system, the Contractor shall provide their quality control procedures, from the first single valve to the CTP, at time of bid to the Contracting Officer for a determination of acceptability.