(SOW) VUZ VOR Stairway Refurbishment 1-17.pdf
PDF 3 MB Posted
- Attached to
- MARKET SURVEY: VUZ VOR stairway refurbish and repair. FAA facility VUZ VOR, Mount Olive, AL
- Solicitation number
- AC-24-02207
About this file
This is a Performance Specification document from the Federal Aviation Administration (FAA) detailing requirements for refurbishment of an existing pressure-treated wood staircase at the Mount Olive VUZ VOR facility in Alabama. The project involves rebuilding a 50-foot/4-story exterior staircase that connects the FAA VUZ VOR equipment shelter with an adjacent hilltop antenna array.
The scope includes installing a new center stringer, replacing outboard stringers while reusing existing support footings, adding balusters, and installing new treads with specific requirements for materials and dimensions. Key specifications include: ground contact pressure-treated lumber for all wood components, galvanized steel fasteners with zinc coating, concrete footings below frost line (minimum 36 inches), 7:11 stair pitch, minimum 1.5-inch thick treads, 36-inch minimum handrail height, and balusters spaced no more than 4 inches apart. The contractor must provide all labor, materials, and equipment, coordinate with the FAA COR for site access (work hours 7AM-4PM M-F), submit detailed work plans and safety protocols, and provide a 1-year workmanship warranty. The facility is located at 1693-1783 County Road 112 in Mount Olive, AL 35117, with a tentative project timeline showing bid responses due February 12, 2025 and estimated award date of March 14, 2025.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FEDERAL AVIATION ADMINISTRATION January 25, 2024
Mount Olive Very High Frequency Omni-Directional Range (VUZ VOR) Stair Refurbishment
Performance Specification for Refurbishment of Existing Pressure -Treated Wood Staircase at VUZ VOR.
1) Introduction / Project Overview This document outlines the performance specifications for the refurbishment of an existing pressure-treated wood staircase located in a highly vegetative exterior application. This stairway connect the FAA VUZ VOR equipment shelter with the adjacent hilltop antenna array. The stairs span an elevation change of approximately 50 feet / 4 stories with 3 intermittent landings across the span. The project goal is to rebuild this staircase and restore the structural integrity and functionality of the stairs while optimizing safety and aesthetics. The existing stair assembly does not have any balusters or risers and is built with 2 outboard stringers supported intermittently with existing in ground footings that have been found to be intact and capable of reuse.
2) Scope of Work Contractor must Provide all labor, tools, equipment, materials, clean up, and supervision required to achieve the following:
a. Initial Assessment:
i) Contractor shall evaluate the existing staircase for any scope that is not currently addressed through this performance specification and notify the COR immediately.
b. Removal and Demolition:
i) Carefully remove and dispose of existing treads, outboard stringers, railings, and all fasteners and hardware.
c. Material Reuse:
i. Contractor should reuse the following components:
(1) Outboard stringer support footings
(2) Handrail support posts
(3) Outboard stringer cross members
(a) Existing outboard stringer cross members will need to be retrofitted as necessary to integrate the new center stringer into the stair assembly.
d. New Material Requirements:
i) Lumber – Ground contact Pressure treated for use in moist, highly vegetative outdoor environments.
ii) Fasteners – Galvanized steel with zinc coating or approved equal, for corrosion and rust protection.
e. Foundation and Support Components:
i) Center stringer: The refurbished stair assembly shall employ use of a new center stringer for added resiliency and structural integrity.
(1) Install new footing supports for the center stringer according to industry standards and local building codes. These supports must be concrete, with an embedment depth below the local frost line, but not less than 3 feet below grade.
(2) Modify outboard stringer cross members to receive new center sringer.
(3) New center stringer foundation support footings shall be installed in accordance with industry standards and local building codes but shall be installed no further than 6 feet apart.
ii. Handrail support posts: Furnish and install additional vertical support posts embedded in concrete for handrail sections more than 8 feet long.
(1) Newel posts - match existing post characteristics but shall not be less than 6” x 6”, placed at the starting, ending, and turning points of the stairs.
(2) Intermediate posts - match existing post characteristics but shall not be less than 4” x 4.”
(3) All vertical support posts embedded in concrete shall be installed at a depth that is below the local frost line and shall not be any less than 36 inches below grade for each support post.
iii. Outboard stringer foundations:
(1) Existing foundation supports and cross members used for the outboard stringers can be reused.
f. Structural Framing:
i. Outboard stringers:
(1) Replace both existing outboard stringers with new ground contact pressure-treated lumber.
(2) Stringers shall be selected in accordance with IBC but shall not be less than 2” thick.
ii. Center stringer:
(1) Install a new center stringer made of ground contact pressure-treated lumber.
(2) Stringers shall be selected in accordance with IBC but shall not be less than 2” thick.
iii. Secure stringers to existing materials appropriate for reuse and new material, including handrail posts (reuse allowed), outboard stringer cross members (reuse allowed, with proper modification to receive new center stringer) and new center stringer foundation supports. All connections shall be achieved using zinc coated, galvanized steel fasteners suitable for outdoor use.
(1) Contractor should bid the project reflective of reusing the existing vertical handrail support posts.
g. Treads and Risers:
i. Treads - Install new treads using ground contact pressure-treated lumber of thickness and width in accordance with local and national building codes.
(1) Treads shall not be less than 1.5 inches in thickness.
(2) Tread depth shall not be less than 11 inches.
(3) Stair pitch must conform to a 7:11 angle of ascent.
ii. Risers - No risers are required as part of this SOW, but a riser height opening of no more than 7 inches shall be used for this bid.
iii. Ensure proper spacing and adherence to building code requirements for rise and run (7:11).
iv. Secure treads to stringers using galvanized, zinc coated corrosion-resistant fasteners.
h. Landings
i. Contractors shall match existing configuration and provide landings at intervals not less than existing.
(1) No less than 3 landings shall be provided between the bottom and top of the stairway.
(2) Landing materials shall match tread materials in all characteristics.
i. Railings and Balusters:
i. Install new railings and balusters of ground contact pressure treated wood that complies with building code requirements for height, spacing, and strength.
(1) Balusters shall be spaced no more than 4” apart.
(2) Balusters shall be wood – square, at 1.5” x 1.5” minimum.
(3) Secure railings to stringers and support posts using appropriate zinc coated, galvanized steel fasteners.
j. Hardware and Fasteners:
i. All hardware and fasteners used must be galvanized steel for outdoor use and have a weather protection coating such as a zinc chromate or epoxy coating for added protection against rust and corrosion.
ii. Pre-drill all holes to prevent splitting of wood.
k. Finishing and Protection:
i. Apply a high-quality exterior stain and / or sealant to all exposed wood surfaces for weather protection and enhanced aesthetics.
(1) Color to be selected on-site by the facility system support center manager (SSC manager) and / or Contracting Officer’s Representative (COR).
l. Clean-up and Disposal:
i. Remove all debris and construction materials from the site.
3) Performance Requirements
a. Structural Integrity: The refurbished staircase must meet or exceed all applicable building codes for structural strength, stability, and load-bearing capacity, including but not limited to:
i. IBC 1011 Stairways
ii. IBC 1027 Exterior exit stairways and ramps
b. Safety: The staircase must be safe for use by people of all ages and abilities. This includes proper handrail height, spacing, and strength, as well as adherence to slip-resistant tread requirements.
i. Handrails shall be no less than 36” in height.
c. Durability: All materials used must be weather-resistant and suitable for long-term outdoor use, located in a highly vegetated area.
d. Aesthetics: The refurbished staircase should blend seamlessly with the existing architecture and enhance the overall property aesthetics
e. Stair pitch: A stair pitch of 7:11 (rise: run) is the acceptance criteria for this specification.
4) Reuse and Replacement
a. Posts: Reuse all existing handrail support posts.
b. Stringers: Replace all existing outboard stringers with new pressure-treated lumber and install a new center stringer with matching characteristics.
i. New stringers must satisfy local and national building codes, but not be any less than 2” in thickness.
5) Additional Requirements
a. Contractor shall submit a detailed plan for the proposed foundation supports and additional support posts, including materials, dimensions, and spacing, for approval by the project owner and/or engineer.
b. Contractor shall provide a 1-year workmanship warranty for all materials and labor.
6) Acceptance Criteria The following criteria will be used to determine the successful completion of the project:
a. All work is completed in accordance with this performance specification and applicable building codes.
b. The refurbished staircase is structurally sound, stable, and safe for use.
c. All materials and workmanship meet or exceed industry standards.
d. The finished staircase meets the desired aesthetic requirements.
7) Project Location
a. Project is located at the FAA facility VUZ VOR, with the access gate having an approximate GPS address of 1693 – 1783 County rd. 112 in Mount Olive, AL 35117
b. See attached screenshots for greater detail on project location and access.
8) Hours of work
a. Work will be permitted weekdays, M-F between the hours of 0700 and 1630.
9) Site Access, Facilities and Construction Limits
a. No restroom facilities are available on site – temp restrooms and wash station will need to be provided by the contractor.
b. On-site electricity can be made available for contractor use as necessary for small power tools. Advance coordination with the facility support manager will be required.
c. Staging and laydown can be accommodated on-site.
d. Contractor shall always maintain access to the site for routine COR inspection efforts.
e. Work Hours will be between 7 AM and 4 PM M – F. Alternate schedules must be discussed with and approved by the COR a minimum of 48 hours in advance.
f. Construction/demolition shall in no way interfere with FAA Operations. Extreme care shall be exercised so as not to cause any interference or interruption of service provided by this facility. It is mandatory that the contractor protect FAA personnel and existing equipment. Any damages incurred, as a result of construction activity during the performance of this contract will be repaired/replaced immediately by the contractor at no cost to the FAA.
g. Any work or activity that may impact the FAA, such as work on critical equipment or circuits, will require coordination with the COR. The COR will coordinate with the local facility personnel to address develop an activity specific “Risk Assessment” for the facility’s final approval. This process may take a full day to complete.
h. No contractor personnel may terminate or remove any connections to existing power panels. Only FAA personnel shall enter FAA panel boards unless they have been de-energized, and coordination has been done in advance with the COR. Contractor shall advise the COR at least one day in advance when it is expected that access to power panels will be necessary to allow for coordination with local FAA specialists to be on site to make the terminations. The contractor personnel shall not operate any breakers in any existing FAA panel boards. NO ELECTRICAL TERMINATIONS SHALL BE
MADE ON AN ENERGIZED CIRCUIT.
i. The contractor shall confine operations, activities, storage of materials and employee parking within the designated areas, as identified by the COR. If required, additional space the contractor deems necessary shall be obtained off site, at no additional cost to the Government.
j. Vehicles transporting materials shall not be loaded beyond the capacity prescribed by federal, state, or local laws. Obstruction of existing roadways, driveways, to the facility is strictly prohibited.
k. Damage to existing paving, lawns, and utilities caused by the contractor's activities shall be repaired immediately. Any damages that are a result of the contractor’s activities shall be repaired. All costs of repairs shall be paid by the contractor. After notice to proceed and prior to the commencement of construction, the contractor and
COR shall conduct joint inspections of the existing areas affected by the construction.
Existing damage or defects shall be noted and will be used as the basis for determination of damages caused by the contractor's operations.
l. It is strongly urged that the contractor carefully examine the premises to determine the extent of work and the conditions under which it must be done.
m. The Government reserves the right to enter the construction area at any time for work inspection and for the operation of the facility.
n. All work hours, shifts, and overtime work shall be coordinated with the COR. Before commencing construction, furnish to the COR a statement of hours per day and days per week to normally be worked and approximate number of persons on the job for a normal work shift.
o. At the end of each workday, the contractor shall secure all construction areas. The contractor is responsible for the security of the staging area and shall provide the required measures at no additional expense to the government.
10) Safety and Environmental Considerations
a. Personal protective equipment (PPE): Wear appropriate PPE such as gloves, safety glasses, respirators, and hearing protection during all removal and replacement activities.
b. Waste disposal: Dispose of all removed materials and debris in accordance with local regulations and COR direction.
11) QC / Inspection and Acceptance
a. Upon completion of the removal and replacement process, Contractor must schedule a final inspection with the FAA COR to ensure the refurbished stair system meets all specifications and is installed properly. This may involve visual inspection, and other Non-destructive testing measures.
12) PERSONNEL
a. Contract Manager: The Contractor must provide a contract manager who must be on-site and responsible for the performance of the work. The name of this person, and an alternate(s) who must act for the Contractor when the manager is absent, must be designated in writing to the contracting office prior to contract start date.
The Contract Manager or alternate must have full authority to act for the Contractor on all contract matters relating to administrating this contract.
b. Employees: The government reserves the right to restrict the access of any contractor employee, or prospective contractor employee, who is identified as a potential threat to the health, safety, security, general wellbeing, or operational mission of the installation and its population.
c. The contractor must coordinate all planned on-site activities with the FAA COR a minimum of 48 hours in advance. The contractor and his employees must be subject to all rules and regulations relative to entering and leaving the FAA facility.
Project COR:
Timothy Kelley
Timothy.Kelley@faa.gov
205-769-3960 (o)
205-569-9074 (m)
Secondary Project POC/COR:
Brett Charap
Brett.Charap@faa.gov
917-447-7211 (m)
404-305-7118 (o)
13) Removed
14) General
a. All work shall be warrantied against defects in materials and non-compliance with manufacturer’s required installation methods for a period of one (1) year.
b. All work shall comply with current codes and standards in effect, and operational requests of local Facility Management. Contractor shall comply with all local, state, and federal permitting and code compliance in effect and known prior to beginning work.
c. Construction duration and working hours must be coordinated with project COR, and allow for adverse weather, holidays, and routine interruptions. Allowable working mailto:Brett.Charap@faa.gov hours shall be Monday through Friday, 7 AM – 4 PM, and allowance for weekends with prior COR approval.
d. Upon completion of work, the contractor shall notify the FAA Contracting Officer’s Representative (COR), requesting that the refurnished stair assembly be inspected.
Upon acceptance the contractor shall submit a warranty for the project, of not less than one (1) year. The warranty shall be a no dollar limit guarantee.
15) CONSTRUCTION SCHEDULE
a. The contractor shall provide a detailed project schedule.
b. The work plan and schedule prepared by the contractor shall consist of a logical narrative plan. Include construction activities, submittal and approval of materials, samples, and shop drawings (if applicable), the procurement of critical materials and equipment, fabrication of special materials and equipment along with their installation and testing.
c. Within fifteen (15) calendar days of contract award, the contractor shall submit the schedule and work plan. A Notice to Proceed will not be issued until the schedule is approved.
d. The Contractor shall warranty material, workmanship, and equipment furnished by the various manufacturers in writing for a period of one (1) year (or not less than the industry standard for the material specified, nor the manufacturer’s standard warranty period, whichever is greater) from the date of final project acceptance by the FAA.
16) SAFETY REQUIREMENTS
a. General Safety Provisions - The Contractor shall bear full responsibility to provide safe working conditions for its employees and Contractors. The Contractor shall not permit any employee or Subcontractor to work in surroundings or under working conditions that are unsanitary, hazardous, or dangerous to the health and safety of the employee.
b. Accident Prevention - The Contractor shall bear the responsibility of maintaining an accident prevention program such that frequent and regular inspections of the job site, materials and equipment are made by a competent person designated by the employer.
c. Use of Equipment - The Contractor shall not permit the use of any machinery, tool, material, or equipment that is not in compliance with OSHA regulations. The employer shall permit only those employees qualified by training and/or experience to operate equipment and machinery.
d. Submittals required include, but are not necessarily limited to, the following:
i. Contractor Safety Plan
(1) The FAA shall not be held responsible for safety inspections to ensure Contractor conformance with the OSHA safety regulations. The FAA, however, reserves the right to notify the Contractor of any deficiencies regarding worker safety.
(2) The FAA will evaluate the Contractor on its safety performance, including that of its Subcontractors. The number and severity of safety and security violations will be considered in this evaluation. Contractor safety violations are cause for termination for default, may result in notification of the Contractor’s bonding company, and will affect the Contractor’s opportunity to propose on future work. Failure to correct such deficiencies may impact the Contractor’s ability to work on future FAA contracts.
(3) OSHA Regulations
• The Contractor shall comply with the latest Occupational Safety and Health
Administration regulations (CFR 29 Part 1926) regarding safety in the work area.
• The Contractor shall be responsible for obtaining copies of non-FAA referenced documents without additional cost to the FAA. If Contractor requests a copy of FAA directives, they may be obtained by contacting the Contracting Officer.
• The Contractor is not relieved from adhering to other OSHA requirements not listed herein. The Contractor shall consult the latest referenced OSHA documents for safety regulations.
(4) OSHA Documents:
• CFR 29 Part 1926 Safety and Health Regulations for Construction CFR 29
Part 1910 General Industry Standards Applicable to Construction Industry
17) SUPPLIES AND EQUIPMENT
a. The Contractor shall furnish all supplies and equipment as specified to accomplish the contract specifications.
b. SHIPPING AND RECEIVING MATERIAL. FAA shall not be responsible for shipping or receiving any material relating to this contract nor shall the contractor ship or otherwise receive any materials at the expense of the FAA.
c. PROTECTION OF MATERIAL. Contractor shall protect and maintain in like new condition all materials and supplies to be incorporated into this project and shall be responsible for their safe storage.
d. STORAGE OF MATERIALS. No storage area/space will be provided for contractor furnished equipment or supplies except where prescribed by the COR. Onsite storage must be coordinated with the COR so that the roadway is not blocked.
18) Submittals
a. Submit product data for each of the following system components:
i. Stringers
ii. Treads
iii. Handrails
iv. Handrail support posts
v. Balusters
vi. Concrete foundation / footing mix design
vii. Wood stain / sealant
viii. Hardware / Fasteners
b. Contractor workplan - The work plan and schedule prepared by the contractor shall consist of a logical narrative plan. Include construction activities, submittal and approval of materials, samples, and shop drawings (if applicable), the procurement of critical materials and equipment, fabrication of special materials and equipment along with their installation and testing.
i. Shop drawing depicting proposed stair layout and assembly
ii. Detailed project schedule
iii. Bid breakdown.
c. Health and Safety Plan
d. 1-year material and workmanship warranty inclusive of POC and instructions for submitting a claim.
FEDERAL AVIATION ADMINISTRATION
January 25, 2024
Page Page 12 of 19
Page Page 13 of 19
Page Page 14 of 19
Page Page 15 of 19
Page Page 16 of 19
Page Page 17 of 19
Page Page 18 of 19
Page Page 19 of 19
| Performance Specification for Refurbishment of Existing Pressure -Treated Wood Staircase at VUZ VOR. |
| Performance Specification for Refurbishment of Existing stair_VUZ VOR_10-17-24.pdf |
| Performance Specification for Refurbishment of Existing Pressure -Treated Wood Staircase at VUZ VOR. |
Name VUZ VOR access road: