This is a Statement of Work (SOW) for the VJETTS Furniture Phase 2 project located at Naval Support Activity (NSA) Orlando, Florida and UCF Hyperspace Orlando, Florida, prepared by NAWCTSD (Naval Air Warfare Center Training Systems Division).

The project involves two phases of furniture installation work to be completed by September 25, 2026. Phase 1 requires the contractor to purchase, ship, store at a CDS warehouse, transport, and install new systems furniture including all associated appurtenances at the UCF Hyperspace Building (12905 Ingenuity Drive, Orlando, Florida 32826), with all furniture required to match existing installations. Phase 2, if requested by the government, requires the purchase, shipment, storage, transport, and installation of seating and marker boards with the same matching and coordination requirements. Both phases mandate compliance with all applicable federal, state, and local codes including Unified Facility Criteria, completion and usability testing of all work, and maintenance of minimal dust and noise levels with daily cleanup. The Period of Performance begins July 1, 2026, and regular working hours are established as an 8-hour period between 6 a.m. and 6 p.m., Monday through Friday, excluding government holidays, with no power disruptions allowable during normal working hours. The contractor must submit three copies of Safety Data Sheets, Statement of Nonuse of Ozone Depleting Substances, Accident Prevention Plan with Activity Hazard Analysis, Work Schedule, Bonds and Insurance documentation, names and citizenship information for all on-site workers, and standard drawings in ACAD LT 2012 and PDF format within 7 calendar days after award. All work must comply with OSHA standards, U.S. Army Corps of Engineers Safety and Health Requirements Manuals (EM 385-1-1), and electrical safety codes, with Lockout/Tagout procedures required and no live electrical work permitted.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Title: VJETTS Furniture Phase 2 Activity Location: Naval Support Activity (NSA) Orlando FL and UCF Hyperspace Orlando, Florida

Scope of Work Prepared by: NAWCTSD, Orlando

PART 1 GENERAL

1 GENERAL INFORMATION:

It is the declared and acknowledged intention and meaning to provide new systems furniture in the UCF Hyperspace location, and incidental related work, complete and ready for use, at the

Naval Air Warfare Center Training Systems Division at 12905 Ingenuity Dr, Orlando, Florida

32826.

1.1 DETAILED PROJECT DESCRIPTION

Phase 1: Purchase, ship, store at CDS warehouse, transport, and install new systems furniture complete and ready to use including all associated appurtenances as listed in the materials list, CLIN 0002, in the UCF Hyperspace Building located at 12905 Ingenuity Dr, Orlando, Florida

32826. Furniture must match existing. All work to be coordinated with the government

(NAWCTSD) and work must be completed by September 25, 2026.

Several requirements for this project phase are as follows:

• All applicable federal, state, and local codes shall be followed including but not limited to

Unified Facility Criteria found at https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc

• Ensuring that all work is tested to be complete and useable

• Ensuring dust and noise levels are kept to a minimum with daily cleanup.

Phase 2: If requested by the government, purchase, ship, store at CDS warehouse, transport, and install seating and marker boards complete and ready to use including all associated appurtenances as listed in the materials list, CLIN 0002 in the UCF Hyperspace Building located at 12905 Ingenuity Dr, Orlando, Florida 32826. Furniture must match existing. All work to be coordinated with the government (NAWCTSD). Work must be completed by September 25, 2026.

Several requirements for this project phase are as follows:

• All applicable federal, state, and local codes shall be followed including but not limited to

Unified Facility Criteria found at https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc

• Ensuring that all work is tested to be complete and useable

• Ensuring dust and noise levels are kept to a minimum with daily cleanup.

1.2 SUBMITTALS

https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc

Submit three copies of the following for approval by the Contracting Officer within 7 calendar days after award.

1.2.1 Statements

a. Safety Data Sheet (SDS),

b. Statement of Nonuse of Ozone Depleting Substances (ODS),

c. Accident Prevention Plan including Activity Hazard Analysis,

d. Work Schedule,

e. Bonds and insurance.

f. Name, SSN, and Citizenship of each on site worker, and

g. Standard drawings in ACAD LT 2012 and PDF.

1.3 PERIOD OF PERFORMANCE

a. POP begins on 1 July 2026 and the Contractor shall be required to complete Phase 1, 2, and 3’s entire work, ready for use, not later than September 25, 2026.

1.4 DEFINITIONS

Where "as shown", "as indicated", "as detailed", or words of similar import are used, it shall be understood that reference to the drawings/sketches accompanying this specification is made unless stated otherwise. Where "as directed", "as permitted", "approved", "acceptance", or words of similar import are used, it shall be understood that the direction, requirements, permission, approval, or acceptance of the Contracting Officer is intended unless stated otherwise. As used herein, "provided" shall be understood to mean "provided complete in place in a completely usable condition", that is "furnished and installed". As used herein "secure" shall be understood to mean "marked by solidity, firmness, and stability, especially in design or construction".

1.5 SAFETY REQUIREMENTS

In performing the contract, the Contractor shall provide for protecting the lives and health of employees and other persons and for preventing damage to property, materials, supplies and equipment in accordance with the latest revision of the U.S. Army Corps of Engineers "Safety and Health Requirements Manuals" (EM 385-1-1) and "Occupational Safety and Health

Standards" (29 CFR 1910). Prior to commencement of the work, the Contractor shall meet in conference with representatives of the Contracting Officer to discuss and develop mutual understandings relative to the administration of safety. All OSHA work standards shall be followed including but not limited to Lockout/Tagout procedures. Electrical Safety Code and

OSHA 1910 subchapter S shall be specifically followed. Prior to commencement of the work, the contractor shall meet in conference with representatives of the Contracting Officer to discuss and develop a mutual understand relative to the administration of safety. Power shall not be deenergized without at least 2 weeks’ prior approval of the Contracting Officer. No live electrical work shall be permitted.

PART 2 PRODUCTS

Use only Contracting Officer approved parts or materials.

PART 3 EXECUTION

3.1 STATION REGULATIONS

The Contractor and his employees and subcontractors shall become familiar with and obey all applicable Federal, State, local and station regulations, including fire, safety, traffic, and security regulations. No employee of the Contractor shall be admitted to the work site without satisfactory proof of United States citizenship. Some work areas may require an escort and/or a security clearance for access.

3.1.1 Working Hours

Work hours will be coordinated with the Contracting Officer. No power disruptions are allowable during normal working hours. The Contractor will work together with the Contract

Surveillance Representative for access into restricted spaces. Contracting Officer shall approve working hours prior to commencement of work. Regular working hours shall consist of an 8-hour period established by the Contracting Officer between 6 a.m. and 6 p.m., Monday through

Friday, excluding Government holidays.

-- End of Scope of Work --