SOW VBDZ262101 Bldg 20 Sewer Pipe Repair.docx

DOCX document 1 MB Posted

Attached to
109 AW - Bldg 20 Sewer Pipe Repair
Solicitation number
W50S8J26QA011
Issued by

About this file

This is a Statement of Work (SOW) for sewer pipe repair at Building 20, Stratton Air National Guard Base, Scotia, NY (Project Number VBDZ262101). The contractor must repair a sheared sewer pipe located approximately 35 feet from the manhole and extending from the asphalt to the gravel border. The scope includes obtaining a dig permit (with Dig Safe notification), field verification of the damage location, asphalt cutting, excavation with appropriate protective systems for holes exceeding 5 feet in depth, removal of the damaged pipe section, and installation of new pipe, fittings, and joints compliant with current plumbing codes. If a Fernco coupling is used, it must be the heavy-duty version with shielded coupling. The contractor must install buried utility marking tape one foot below the pavement surface, properly bed the new pipe using Class IB or II material, backfill and compact in layers not exceeding 8 inches to achieve minimum compaction densities of 90 percent for cohesive material and 95 percent for cohesionless material, and repave the asphalt to match existing pavement with appropriate tack coat and joint sealing.

Contractor requirements include compliance with all facility access and security policies, completion of AT Level I awareness training within 10 calendar days of contract start, OPSEC training within 90 days, and adherence to strict substance abuse policies. The contractor must establish a safe work zone, maintain site cleanliness, notify the Contracting Officer's Representative (COR) of unforeseen conditions or utility shutdowns, coordinate material deliveries in advance, and maintain work hours from 0700-1530 Monday through Friday with no work on federal holidays. The project shall commence no later than 14 days after Notice to Proceed and must be completed within 30 days. This is a total small business set-aside under NAICS 237110 (water and sewer line construction) with a small business size standard of $45 million; the project magnitude is less than $25,000. A mandatory site visit is scheduled for March 19, 2026, at 10:00 am at the civil engineering building, Stratton Air National Guard Base.

View the file

Other files

File Type Posted
WD NY20260002 Mod 1.txt TXT text file
Solicitation - W50S8J26QA011.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Project Number VBDZ262101

Bldg 20 Storm Pipe Repair

DESCRIPTION:

A sewer pipe seems to have sheared off (potentially was held by Fernco). The damage location is approximately 35 feet from the manhole on the asphalt to the gravel border. Contractor to field verify the damage location before digging.

~35’ manhole Approximate damage location

Inside the pipe
Damage location

1. SCOPE

1.1. Fill out the dig permit. The paperwork includes calling Dig Safe and Base’s internal procedures. It is recommended to start the process two weeks before breaking ground.

1.2. Field verify the exact damage location.

1.3. Cut the asphalt at the right angles if necessary.

1.4. Excavate down to the broken pipe.

1.5. If the hole is 5 feet or deeper, protective systems such as sloping, benching, shoring, or shielding shall be used.

1.6. Contractor is responsible for the movement of construction machinery and equipment over pipes and utilities during construction. Excavation made with power-driven equipment is not permitted within 2 feet of known utility or subsurface construction. For work immediately adjacent to or for excavations exposing a utility or other buried obstruction, excavate by hand. Start hand excavation on each side of the indicated obstruction and continue until the obstruction is uncovered or until clearance for the new grade is assured. Support uncovered lines or other existing work affected by the contract excavation until approval for backfill is granted by the Contracting Officer. Report damage to utility lines or subsurface construction immediately to the Contracting Officer.

1.7. Where wet or otherwise unstable soil incapable of properly supporting the pipe or elbow, as determined by the Contracting Officer, is unexpectedly encountered at the bottom of a trench, such material shall be removed to the depth required and replaced to the proper grade with select granular material.

1.8. Contractor shall remove the damaged section/element.

1.9. Contractor shall install new fittings, joints, and pipe section following the latest plumbing code.

1.9.1. If Fernco is used, use the heavy-duty one with shielded coupling.

1.9.2. The new pipe and fittings shall be free of defects if used.

1.9.3. Joints shall be the type recommended by the pipe manufacturer and following the latest building code.

1.10. Install buried Utility Marking Tape a foot below the pavement surface.

1.11. The bedding surface shall provide a firm foundation of uniform density.

1.12. Use Class IB or II material for bedding, haunching, and initial backfill. Use Class I, II, or III material for PP pipe bedding, haunching and initial backfill.

1.13. After the pipe has been properly bedded, selected material from excavation or borrow, at a moisture content that will facilitate compaction, shall be placed along both sides of the pipe. The backfill shall be brought up evenly on both sides of the pipe for the full length of the pipe. The fill shall be thoroughly compacted under the haunches of the pipe. The remainder of the trench shall be backfilled and compacted by spreading and rolling or compacted by mechanical rammers or tampers in layers not exceeding 8 inches.

1.14. Compaction density shall be not less than 90 percent of maximum density for cohesive material and 95 percent of maximum density for cohesionless material.

1.15. Backfill and pave following the Asphalt Pavement Section figure below to meet the existing pavement.

1.16. Tack coat shall be applied between pavement courses as well as pavement lifts.

1.17. New to old asphalt joint shall be sealed.

New Asphalt Pavement Section

2. CONTRACTOR REQUIREMENTS

2.1. Comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

2.2. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

2.3. All contractor employees, to include subcontractor employees, requiring access to Government Installations, Facilities and Controlled Access areas shall complete AT Level I awareness training within 10 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Certificates of completion for each affected contractor employee and subcontractor employee will be maintained by the COR or Antiterrorism Representative. AT level I Awareness Training is available through MyLearning by completing the Force Protection CBT. For Contractors that do not require issuance of a CAC, local training will be provided during badge issuance at SFS via informational binder.

2.4. Requirement for OPSEC Training. In accordance with AFI 10-701, Operations Security, OPSEC PMs/SMO/SMNCOs/Coordinators will provide OPSEC training or training materials to contract employees within 90 days of employees’ initial assignment to the contract and annually thereafter. General organizational orientations may need to be supplemented by duty-related orientations in the work center targeted toward specific critical information and vulnerabilities associated with the work. Initial training (OPSE 1301 - OPSEC Fundamentals) and refresher training (Protecting Sensitive Information) are both available on the MyLearning website. For Contractors that do not require issuance of a CAC, local training will be provided during badge issuance at SFS via informational binder.

2.5. The use and possession of controlled substances to include marijuana (medical or recreational use) on the installation is in violation of Title 10 US Code 912a. Art 112a. Contractors are notified this policy is strictly enforced and violators will be denied entry. Personnel caught on the installation can be prosecuted.

2.6. The Contractor shall provide all personnel and necessary equipment to establish an adequate and safe work zone.

2.7. Contractor is responsible for site cleanliness.

2.8. The Contractor shall bring any unforeseen project conditions to the attention of the COR immediately. Differing site conditions, which may alter the scope of work, shall be approved by the contracting officer (KO) prior to such work being performed.

2.9. The Contractor must get approval from the COR prior to any utility shutdowns. (do not have contractor contact production control directly)

2.10. The Contractor shall notify the COR prior to delivery of any material or equipment to the site. The contractor shall ensure someone is available to receive delivered materials and able to store them safely in an area to be coordinated with the government project manager. Any materials delivered without prior coordination and without having someone to take receipt, shall not be accepted and turned away.

2.11. Contractor hours are 0700-1530 Monday through Friday. No work permitted during the Federal Holidays.

3. PROPOSED PROJECT SCHEDULE

The project will begin no later than 14 days after the Notice to Proceed. The project shall be completed within 30 days following the notice to proceed.

image1.png image2.png image3.png