SOW V2_Redacted.pdf
PDF 44 KB Posted
- Attached to
- Concrete Epoxy Pad Covering
- Solicitation number
- FA2823-25-Q-A030
About this file
This Statement of Work details interior floor refinishing for approximately 2,200 square feet of concrete flooring, excluding the server room. The project involves comprehensive floor restoration using a high-performance epoxy primer and finish system, with specific technical requirements including:
Surface preparation involves commercial diamond grinding to remove existing sealer, followed by a prime coat of General Polymer 3579 Epoxy Primer applied at 150 ft² per converted gallon. The finish coat will use General Polymer 3746 Epoxy applied at 100 ft² per converted gallon, with a notched squeegee and back roll technique. Additional steps include removing and reinstalling resilient cove base, filling expansion joints with RS-88 Polyurea joint filler, and performing touch-ups as needed. The United States Government (USG) will handle furniture and floor item removal and reinstallation prior to contractor mobilization, with the final solid color to be determined.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| QUESTIONS AND ANSWERS EPOXY FLOORING .pdf | ||
| FLOOR PLAN CONCRETE EPOXY.pdf | ||
| CONCRETE EXPOXY PICS.pdf | ||
| COMBO_SGT_Redacted.pdf | ||
| COMBO.pdf | ||
| (1)COMBO_Redacted.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
31 202 Statement of Work for Floor Refinishing
Interior Floor Refinishing - High Performance Epoxy Primer and Finish System (Approx. 2,200 ft² including all interior previously sealed concrete. Excludes server room)
Scope:
Mobilize: Carefully remove existing resilient rubber cove base throughout to allow for proper floor grinding surface preparation procedures. Install new resilient cove base upon completion of new floor coating system. Color to match original.
Surface Prep: Mask off perimeter walls as needed and Prep existing concrete slab by commercial diamond grinding w/ dust collectors to remove failing sealer and create an adequate surface profile for new epoxy system. Remove any residual dust and solvent wipe clean. Chase open expansion joints.
Patch divets or imperfections with epoxy patching solution.
Prime Coat: Apply 1 coat of industrial 100% solids General Polymer 3579 Epoxy Primer @ approx.
150 ft² per converted gallon (10 Wet MILS). Allow to dry. Abrade with 60 grit orbital pad and solvent wipe clean.
Expansion Joint Fill: Install RS-88 Polyurea joint filler, shaved smooth into expansion joints.
Finish Coat: Apply 1 coat of industrial 100% Solids High-Performance General Polymer 3746 Epoxy @ approx. 100 ft² per converted gallon (15 Wet MILS). Apply via notched squeegee and back roll.
Solid Color TBD. Allow to dry thoroughly. Touch-Up as needed.
NOTE: The USG will remove and re-install All interior furniture and floor items prior to API mobilization.