SOW_Upgrade Replace Controls on Crane B419.docx
DOCX document 37 KB Posted
- Solicitation number
- W911PT-22-Q-0078
About this file
This statement of work defines the requirements for upgrading controls on an overhead crane at the Watervliet Arsenal. The contractor will be required to remove existing control panels and wiring, install new NEMA-rated control panels for bridge, trolley and hoist functions, replace contactors and wiring, install new controllers in a control console, provide and install new resistors and conduit, check and potentially replace festoon wiring, install arc suppressors on all coils, open and inspect gearboxes and motors and identify any required repairs or rebuilds, test all functions, and load test the hoist at 125% capacity. The contractor must also provide documentation including shop drawings, equipment data, operations and maintenance manuals, a parts list, as-built drawings, and a one-year warranty.
The related federal contract opportunity is a 100% small business set-aside to upgrade controls on four overhead cranes at the Watervliet Arsenal. The work includes upgrading crane B214, replacing the trolley and upgrading controls on crane B419, upgrading crane B416, and furnishing and installing radio control systems on cranes B109 and B410. The pre-bid site visit will take place on September 8, 2022 and quotes are due by September 22, 2022. The contracting agency is the Department of the Army Materiel Command Contracting Command Detroit Arsenal.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW_Upgrade Replace Controls on Crane B214_REV1.docx | DOCX document | |
| W911PT22Q0078-00001.pdf | ||
| SOW_Furnish and Install Remotes Cranes B109 B410.docx | DOCX document | |
| SOW_Upgrade Replace Controls on Crane B416.docx | DOCX document | |
| SOW_Upgrade Replace Controls on Crane B214.docx | DOCX document | |
| SITE_VISIT INFORMATION PLEASE READ.doc | DOC document | |
| W911PT-22-Q-0078.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
FOR
UPGRADE/REPLACE CONTROLS ON CRANE B419
AT
Watervliet Arsenal Building 35
W16H1F221400GD, PR 79182404
Support Division (TAWV-ODR)
PART 1 GENERAL
1.01 Overview.
A. This Statement of Work (SOW) defines the effort required for the upgrade/replacement of control, enclosures and resistors for all crane functions on crane B419, BLDG 35, High Bay, Hexavalent Chrome Area
1.02 Hours of Operation.
A. Normal duty hours are 7:00 AM through 4:30 PM, Monday through Thursday, and 7:00 AM through 3:30 PM on select Fridays (the Arsenal is closed every-other Friday). Federal holidays are non-work days. If a federal holiday falls on a Saturday or Sunday, the preceding Friday or following Monday is a work holiday.
1.03 General Requirements.
A. Work will be performed at the Watervliet Arsenal Facility, Bldg. 35.
B. The contractor shall supply all tools, materials, supplies, equipment, labor, temporary utilities and supervision necessary for the complete execution of the requirements within the contract documents and requirements of this SOW.
C. The contractor shall, prior to submitting a proposal, review (i) all contract documents, and (ii) the project work site, and shall provide written notice to Contracting Specialist detailing any discrepancies that are found between the contract documents and the project work site.
1.04 Safety Requirements. Contractor shall follow all requirements of OSHA, as well as Federal, State and Local requirements. The Watervliet Arsenal Instructions for Contractors (WAIC) can be found here:
https://wva.army.mil/docs/librariesprovider6/default-document-library/waic.pdf?sfvrsn=8b90f522_0
1.05 Period of Performance.
A. The contractor shall be required to (i) commence work under this contract within 7 calendar days after the date the contractor starts work, (ii) prosecute the work diligently, and (iii) complete the entire work ready for use not later than [30] calendar days after start of work. The time stated for completion shall include final cleanup of the premises.
1.06 Project Schedule.
1.07 Permits.
1.08 Equipment Identification.
1.09 Applicable Documents.
1.010 Submittals.
PART 2 PRODUCTS
2.01 General.
PART 3 ITEMS OF WORK
3.01 General.
A. The contractor shall coordinate with WVA personnel to gain access
B. Install Festoon/Upgrade/Replace Controls for all crane functions (Trolley, Bridge and Hoist) for Crane B419, Bldg 35, Watervliet Arsenal NY
C. Crane Manufacturer is Shepard Niles S/N: 69614. Crane Capacity is 15 Ton. The contractor will be required to obtain any drawings they may require from a source (Kone Cranes, for example) other than the WVA.
D. Contractor will cover the cost of labor, equipment and materials for the upgrade/replace controls.
E. Contractor will disconnect and remove all power and control wiring to control panels and cab master switches.
F. Contractor will remove Sub Panels and resistor banks, dispose of all rubbish.
G. Contractor will furnish and install new replacement control panels with appropriate NEMA rated contactors mounted in NEMA 1 Indoor enclosures for all crane functions (Bridge, Trolley and Hoist). Ensure new controls provide the same range of controls as are no present (three functions, 5 speeds, etc). Upgrade/Replace contactors and wiring. The power source to which the crane is 250 VDC. However, the equipment shall be tolerant enough of line fluctuations to operate normally at source voltages ranging from 225 to 275 VDC.
H. Contractor will install one (1) new console using the JR Merritt (or equal) controllers one (1) for each motion (bridge, trolley and hoist)
I. Contractor will provide and install brand new resistors and all associated wiring and conduits as needed.
J. Contractor will check wiring in festoon system for possible replacement. Any additional required findings will be treated as an unforeseen change, and quoted for possible replacement.
K. Contractor will Install ARC Suppressors on all coils of all functions.
L. Gear boxes are to be opened and checked for wear, any deficiencies are to be identified for possible repair/rebuild and the gear boxes resealed.
M. Motors are to be PDMA tested and deficiencies if any are to be identified, with the possibilities of motors be taken down for rebuild/repair. To be coordinated by contractor.
N. Contractor will test all functions for correct operation. All equipment shall be operated through a complete lift and lowering cycle and through a complete travel of the bridge and trolley to determine that the equipment shall perform smoothly and safely. Any defects shall be corrected by the contractor without any expense to the WVA
O. Load Test hoist on Crane, test at 125%. Contractor will use Test Weights, not waterbags. The proposed overall Price should include round trip transportation, on site costs and per-diem if required.
P. Contractor shall provide a list of suggested spares along with pricing and copies of all associated drawings and bill of material to include p/n and manufacturer.
All work will be in accordance with the manufacturer’s specifications.
Equipment furnished shall, except as otherwise noted, comply in all respects with the requirements of the following standards:
| *CMAA | Crane Manufacturer’s Association of America | |
| Specifications for Top Running Bridge & Gantry Type Multiple |
Girder Electric Overhead Traveling Cranes - No. 70 (2010)
*ANSI/ASME
American National Standards Institute/American Society of Mechanical Engineers ANSI/ASME B30.2 - 201 Overhead and Gantry Cranes (Top Running Bridge, Single or Multiple Girder, Top Running Trolley Hoist) OSHA Occupational Safety and Health Administration Part 1910.179 – Overhead and Gantry Cranes
| NEMA | National Electric Manufacturer’s Association |
| NEC | National Electric Code – 2014 |
*Compliance to this standard is limited to the extent such standard is incorporated into and made mandatory by OSHA regulations.
When work is complete, the crane will be turned over for any and all work will be inspected and accepted by the Contracting Officer’s Representative.
Contractor will provide:
SHOP DRAWINGS AND EQUIPMENT DATA
1. Manufacturer’s catalog data for radio remote control system.
1. Dimensional drawings and details for component installation.
1. Wiring schematics (As-built drawings).
OPERATIONS AND MAINTENANCE MANUALS
1. Equipment function, normal operating characteristics, and limiting conditions.
1. Assembly, installation, alignment, and maintenance instructions.
1. Guide to “troubleshooting”.
1. Parts list.
1. As-built drawing.
WARRANTY
Upon final acceptance of the systems, a Standard Commercial Warranty shall commence for duration of One Year, to include as a minimum, parts and labor for the duration of the warranty, at no cost to the Government. The one year period shall commence from the date of notification by the Contracting Officer of the final acceptance. Final acceptance is defined as the act of an authorized representative of the Government, by which the Government assumes ownership of existing supplies/equipment and/or approves specific services rendered, as partial or complete performance of the contract (i.e. testing, training, and delivery of all required technical documentation).
PROCUREMENT OF SPARE PARTS AND EQUIPMENT
The contractor shall provide a comprehensive list with pricing of consumables, spare parts kits and spare transmitters available for purchase at the time of contract award.
Contract shall provide a list of suggested spares along with pricing and copies of all associated drawings and bill of material to include p/n and manufacturer.
PART 1 CLOSEOUT REQUIREMENTS
1.01 Cleanup of Work Site.
A. Removal of all excess equipment and waste wil be the responsibility of the contractor.
1.02 Final Repairs and Restoration to Work Site.
PART 2 APPENDICES
A. Consolidated List of Submittals APPENDIX A: Consolidated List of Submittals
| Line |
| Item Submitted |
| Submittal Needed By |
| Submittal Reviewed By (Office) |
| 1 |
| Safety Data Sheets for Hazardous Materials (SDS) |
| NLT 7 Calendar Days After Award |
| Safety Office |
| 2 |
| Signed Contractor Asbestos Notification Form |
| NLT 7 Calendar Days After Award |
| Environmental Office |
| 3 |
| Signed Lockout/Tagout (LOTO) Notification Acknowledgement Record |
| NLT 7 Calendar Days After Award |
| Safety Office |
| 4 |
| Project Schedule |
| NLT 7 Calendar Days After Award |
| COR |
| 5 |
| Contractor Safety Plan (1.05.A.) |
| NLT 7 Calendar Days After Award |
| COR |