SOW - University Mountain Tower Remediation - USFS R1.pdf

PDF 256 KB Posted

Attached to
UPDATE* University Mountain Tower Remediation - LPGBS Design Federal contract opportunity
Solicitation number
6973GH-26-R-00077
Issued by
Department of Transportation Federal Aviation Administration Franchise Acquisition Services

About this file

This is a Statement of Work (SOW) for University Mountain Tower Remediation services to be provided for the U.S. Forest Service Guy Tower, prepared on December 18, 2025 (Contract Reference: AJW-L531).

The contractor shall perform remediation work on a 65-foot guyed lattice-based communication tower located at University Mountain in the Lolo National Forest, Region 01, Forest 16 (coordinates: 46°51'5.43"N, 113°55'39.77"W). The scope includes four primary tasks: (1) implement guy wire tensioning in accordance with TIA-222 Rev. H specifications with all three legs tensioned to 1-7 1/4", including minor repairs as needed; (2) install lightning protection systems according to supplied design; (3) perform corrosion abatement on tower and guy systems; and (4) install industry-designed mounting hardware for transmission line support. The contractor must ensure grounding connections meet NFPA 780 standards with a preferred resistance of 10 ohms and acceptable maximum of 25 ohms. All work must comply with OSHA regulations (29 CFR 1910 and 1926) and applicable industry standards. The contractor is solely responsible for all pre-work logistics, permits, site access coordination, and establishing a safe work zone; on-site logistics support is not provided by the government.

The contractor must submit a preliminary project schedule within 10 calendar days of award and a final project schedule with remediation plan no later than two weeks before field work commences. All work must be fully completed within 30 days of the Notice to Proceed. Deliverables include a remediation plan, final report with tensioning test data (pre- and post-), detailed activity schedule, photographic documentation of below-grade work, and all field reports, site assessments, and data packages submitted to the Primary Project Point of Contact within 30 days of site completion in PDF format. Site access will be coordinated by FAA and USFS, with the contractor required to notify the assigned USFS radio technician of planned visits with date, time, and meeting location.

View the file

Other files for this federal contract opportunity

Other files attached to UPDATE* University Mountain Tower Remediation - LPGBS Design, newest first.
File Type Posted
University Mountain - LPS Design Drawing.pdf PDF
6973GH-26-R-00077.pdf PDF
University Mountain Photo Deck.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

University Mountain Tower Remediation

For

U.S. Forest Service Guy Tower

PREPARATION DATE: 12/18/2025

AJW-L531 / United States Forest Service

1. Introduction and Overview This Statement of Work (SOW) supports the mission of the United States Forest Service (USFS) to sustain the health, diversity, and productivity of the nation’s forests and grasslands for the benefit of current and future generations. This initiative addresses systemic maintenance and critical infrastructure issues affecting the USFS tower inventory, with a focus on ensuring these structures continue to support mission-critical operations.

The contracted entity will operate independently to provide technical and logistical services, in coordination with the Federal Aviation Administration (FAA), to perform the tasks outlined in this scope of work.

2. Scope of Work

The contract scope includes the following tasks:

1. Implement guy wire tensioning, including any minor repairs needed to achieve proper and uniform tension.

2. Install Lightning protection systems.

3. Corrosion abatement on tower and guy system.

4. Install industry designed mounting hardware for proper transmission line support.

All tasks must adhere to applicable industry standards and best practices for the specified tower structures. The contractor is responsible for providing all necessary labor, tools, equipment, materials, and technical expertise to complete the work. The scope of this SOW does not include the provision of on-site logistics. Vendor is solely responsible for all pre-work logistics, including the procurement of necessary permits, arranging for site access, and establishing a safe work zone prior to beginning work.

The selected contractor is responsible for furnishing all labor, tools, equipment, materials, and technical expertise necessary to complete the following tasks:

a. System Type

65’ guyed lattice-based communication tower.

b. Facility Type Sole-Use Facility: A stand-alone tower with an associated communications building or box that is not physically connected to any other facility, even if located on the same land unit.

c. Site-Specific Requirements

Tension all guy wires in accordance with TIA-222 Rev. H specifications.

o Leg A: 1-7 1/4” o Leg B: 1-7 1/4” o Leg C: 1-7 1/4”

Perform corrosion abatement and control on tower and guy system.

Install industry designed mounting hardware for proper transmission line support.

Install lightning protection in accordance with the supplied design.

Ensure that grounding connections resistance meets the NFPA 780 preferred standard of 10 ohms, with 25 ohms as the acceptable maximum.

2.1 Location of Work

Guy wire tensioning and repair work will be performed at USFS field site.

Planning and preparation activities may take place at the contractor’s home office or at USFS field offices (subject to field office management approval).

Statement of Work Power Installation

Field Work Locations:

Region Forest Forest Name Site Name Site

Latitude Site Longitude

01 16 LOLO

University Mountain

46°51'5.43"N 113°55'39.77"W

3. Schedule The Contractor shall submit a preliminary project schedule within 10 calendar days following the contract award for Government review and approval. A final project schedule and remediation plan must be submitted no later than two (2) weeks prior to the commencement of field work.

All work described in this Statement of Work must be fully completed within 30 days of the issuance of the Notice to Proceed.

The project schedule should include, at minimum, the following key milestones:

Contract Award Post-Award Conference Deployment Readiness Review Mobilization Field Work Start Testing Field Work Completion Clean-up and Site Restoration

3.1 Site Access

The Contractor shall provide a staging and installation schedule that includes equipment and material delivery. Site access will be coordinated and granted by the FAA and USFS.

For each planned site visit, the Contractor is required to notify the assigned USFS radio technician with the date, time, and designated meeting location. The USFS technician will advise on any vehicle requirements for site access due to terrain or conditions.

Scope-related inquiries must be directed at the Primary and/or Secondary Project Points of Contact (POCs) listed below. Local Forest Service representatives do not have the authority to alter the Statement of Work or authorize changes that incur additional costs.

If a site-specific POC is not provided, the contractor must contact the Primary USFS

POC to obtain appropriate site contacts.

All email communications with site contacts should include both Primary and

Secondary POCs on copy.

3.2 Site Logistics

The Contractor is responsible for all on-site logistics and coordination prior to the start of work, including but not limited to securing access, setting up a designated work area, and confirming all necessary permits are in place.

4. Government Equipment Security

Physical Security The Contractor shall safeguard all Government-furnished property during the period of performance. At the conclusion of each workday, all facilities, equipment, and materials must be properly secured.

Key Control The Contractor shall develop and implement a key management system to prevent the loss, unauthorized use, or misplacement of any keys or access cards issued by the Government.

5. Applicable Standards:

All work must comply with the following standards:

a. OSHA Regulations (29 CFR 1910 and 1926)

Contractors shall adhere to all applicable safety, health, and operational standards during performance.

b. ANSI/TIA-222 Revision H

7.6.1 Initial Tension: Guy wire tension at 60°F [16°C] must fall between 7% and 15% of the strand's rated breaking strength. Adjustments are allowed if structural sensitivity and local temperatures are considered.

13.3.2 Guy Tensions: Tension deviation from design values must be within ±10% for guys ≤1 in. [25 mm] and ±5% for guys >1 in. [25 mm], corrected for ambient temperature.

7.4.6.1 Turnbuckles: Turnbuckles must be made from AISI 1030, 1035, or 1045 steel, or equivalent, and must be properly heat-treated.

Sections 10.4 and 10.5: Electrical resistance and grounding material requirements.

c. NFPA 780 Grounding systems must comply with current lightning protection and electrical grounding standards.

6. Deliverables and Schedule of Delivery The Contractor shall provide the following deliverables:

a) A remediation plan submitted along with the final project schedule, due two weeks before work begins.

b) A final report including documentation of completed site activities and tensioning test data (pre- and post-tensioning).

c) A detailed schedule of all pre-work and on-site activities for approval by the Primary Project POC.

d) Photographic documentation of all below-grade work, taken before, during, and after excavation.

e) All field reports, photos, site assessments (SA), and data packages must be submitted to the Primary Project POC within 30 days of site completion.

f) All final project documents shall be delivered in PDF format.

7. Completion Criteria Project completion will be determined based on the following:

a) Submission and formal acceptance of all required documents by USFS and FAA.

b) Completion and acceptance of all technical requirements as specified in this Statement of Work.