SOW T-6 Shacks.pdf
PDF 616 KB Posted
- Attached to
- T-6 Flightline Shacks
- Solicitation number
- FA302226R0005
About this file
Statement of Work Summary
This is a Design-Build Statement of Work for the repair of four T-6 Flightline Shacks (Buildings 247, 628, 629, and 633) at Columbus Air Force Base, Mississippi. The project number is EEPZ230749, dated March 13, 2025, with a total performance period of 330 days from Notice to Proceed.
The scope includes comprehensive repairs to restore HVAC, plumbing, electrical, and interior finishes in nearly identical work across all four buildings. HVAC work requires demolition and replacement with direct expansion ducted split systems with heat-pump operation, including load calculations to ASHRAE standards, new ductwork, concrete slabs for condensing units, and a complete TAB report by an independent third party. Plumbing work includes new flush-valve toilets, urinals, sinks, floor drains, and exhaust fans with timer integration. Electrical work includes replacement of LED lighting systems with occupancy sensors and dimming controls per UFC 3-530-01, new main panelboards with appropriately sized breakers, new thermostats, and emergency exit signage per NFPA 101. Interior finishes require ceiling replacement with 2'x2' grid-style tegular acoustical tiles, demolition of walls separating certain areas to create open space, new insulated metal doors meeting ASHRAE 90.1 standards, wall and window frame repainting to Sherwin Williams Accessible Beige, polished concrete floors with self-leveling sealant, and new cove base throughout. Communication infrastructure requires conduit, cable supports, and pull strings for future implementation without cable installation by the contractor. The contractor must establish and submit a phasing plan by the 35 percent design submittal, with final phasing due by 65 percent design, as all four buildings cannot be shut down simultaneously.
The contractor must provide all design services including plumbing, mechanical, electrical, and professionally sealed drawings, with submittals at 35%, 65%, 95%, and 100% design stages with defined review timelines. Design standards must comply with applicable UFCs, ETLs, NEC, NFPA codes, and Columbus AFB Installation Facility Standards. The contractor is responsible for all personnel, equipment, materials, and labor, including a Contractor Project Manager with minimum five years' experience in multi-discipline commercial construction, a Contractor Site Superintendent with five years' experience overseeing similar projects, and a Quality Control Manager with five years' quality control experience. Standard warranty covers materials and workmanship for one year from total project acceptance. All existing DX units in the buildings must be salvaged and returned to the government. The government will not furnish equipment or materials.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| T6 site visit sign in sheet.pdf | ||
| Solicitation - FA302226R0005.pdf | ||
| EAL Form.pdf | ||
| AF Form 66.xlsx | XLSX spreadsheet | |
| Contractors CUI Training Slides.pptx | PPTX presentation | |
| MFR CUI Contractor Training Acknowledgment July 2024.pdf | ||
| Wage Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DESIGN-BUILD STATEMENT OF WORK
PROJECT NUIMBER: EEPZ230749
REPAIR T-6 FLIGHTLINE SHACKS HVAC/PLUMBING, B247, B628, B629, B633
COLUMBUS AFB, MISSISSIPPI
13 MARCH 2025
COLUMBUS AFB, MS
PROJECT NUMBER: EEPZ230749
REPAIR T-6 FLIGHTLINE SHACKS HVAC-PLUMBING, B247, B628, B629, B633
TABLE OF CONTENTS
NOMENCLATURE
1.1 ACRONYMS & ABBREVIATIONS
1.2 BASIC TERMS
DESCRIPTION OF PROJECT
2.1 SUMMARY (EXAMPLE BELOW)
2.2 BACKGROUND
2.3 SCOPE OF PROJECT
2.4 GOVERNMENT FURNISHED EQUIPMENT/MATERIALS
2.5 SALVAGE
DESIGN REQUIREMENTS
3.1 SUMMARY
3.2 NATURE/EXTENT OF DESIGN
3.3 RESPONSIBILITY
3.4 DESIGN STANDARDS
3.5 DRAWINGS
3.6 DESIGN SUBMITTALS
3.7 DESIGN REVIEWS
3.8 CONFERENCES
ADMINISTRATION OF CONSTRUCTION
4.1 PERFORMANCE CAPABILITIES
4.2 COMMENCEMENT, PROSECUTION & COMPLETION
4.3 SCHEDULING
4.4 MANAGING
4.5 MATERIAL SUBMITTALS AND SHOP DRAWINGS
4.6 WORK BY GOVERNMENT
4.7 PRE-FINAL AND FINAL INSPECTION
4.8 WARRANTY
4.9 CONTRACTOR OFFICE
4.10 CONSTRUCTION SITES
4.11 CONSTRUCTION EQUIPMENT
4.12 AVAILABILITY OF UTILITY SERVICES AT JOB SITES
4.13 TEMPORARY UTILITIES
4.14 CONSTRUCTION SECURITY
QUALITY REQUIREMENTS
5.1 QUALITY CONTROL PLAN
5.2 TESTING AND INSPECTION SERVICES
5.3 MANUFACTURERS' FIELD SERVICES
5.4 PRODUCT REQUIREMENTS
5.5 CLOSEOUT PROCEDURES
SAFETY, HEALTH AND ENVIRONMENTAL PROTECTION
6.1 SAFETY AND HEALTH
6.2 GENERAL
6.3 HAZARDOUS MATERIAL
6.4 PROJECT EXECUTION
6.5 HAZARDOUS WASTE GENERATION/DISPOSAL
6.6 RECYCLING
6.7 PROHIBITED MATERIAL/ACTIONS
6.8 SPILLS AND CLEANUP
6.9 AIR CONSIDERATIONS
6.10 AFFIRMATIVE/GREEN PROCUREMENT/BIO-BASED/ENERGY
6.11 ASBESTOS/LEAD BASED PAINT
6.12 DRINKING WATER
6.13 EMS
6.14 HISTORICAL AND CULTURAL ARTIFACTS
6.15 NATURAL RESOURCES
6.16 NOISE
6.17 PESTICIDES/FERTILIZERS
6.18 STORM WATER PROTECTION
6.19 REQUEST FOR CE SERVICE/ACTION/CLEARANCE; AF FORMS 332/813
6.20 TANKS
6.21 LIMITS AND EXCEPTIONS
6.22 LEGAL AUTHORITY
NOMENCLATURE
1.1 ACRONYMS & ABBREVIATIONS
AF Air Force AFI Air Force Instruction AFM Air Force Manual AFUE Annual Fuel Utilization Efficiency AHU Air Handling Unit ATFP Anti-terrorism/Force Protection BCE Base Civil Engineer CAD Computer Assisted (or Aided) Design CAFB Columbus Air Force Base CDs Construction Documents CEPM Civil Engineering Project Manager CES Civil Engineering Squadron cfm cubic feet per minute CFR Code of Federal Regulations CHW Chilled Water CMI 14CES Construction Manager Inspector CO Contracting Officer COR Contracting Officer Representative Comm Communications CPM Contractor’s Project Manager CSS Contractor’s Site Superintendent DP Design Professional EMCS Energy Management & Control System EMI Electromagnetic Interference EPA Environmental Protection Agency ETL Engineering Technical Letter FAR Federal Acquisition Regulation FCU Fan Coil Unit FM Factory Mutual
FOD Foreign Object Debris fps feet per second
ft. foot or feet GFCI Government Furnished Contractor Installed gpm gallons per minute Hazmat Hazardous Materials HMW Hazardous Material or Waste HTW Hazardous and Toxic Waste HVAC Heating, Ventilating and Air Conditioning NEC National Electrical Code NTP Notice to Proceed O&M Operation and Maintenance OSP Originally Specified Product PDF Portable Document Format PE Professional Engineer Ph Phase (electrical) PM Project Manager psi pounds per square inch QCP Quality Control Plan RFP Request for Proposal SOW Statement of Work TI Technical Instruction TL Technical Letter TM Technical Manual UFC Unified Facilities Criteria UPS Uninterruptible Power Supply VAV Variable Air Volume V Volts W Watts
1.2 BASIC TERMS
The following table provides many of the meanings of words or phrases commonly used in this document.
All directives, informative, etc. statements are directed to the Contractor even if the term “contractor” or the contractor name is not included (e.g. “Provide a nail.” is equivalent to “The contractor shall provide a nail.” And “remove” is equivalent to “The Contractor shall remove”). Also, the Contractor shall ably and competently execute all directives including all directly or indirectly related tasks required to safely and legally perform the directive (e.g. “remove debris from CAFB” includes “safe and legal removal, disposal and obtaining all necessary permits, etc.)
A device, equipment or system referred to in the singular (e.g. “the pump”, or “the ___ system”) includes all related devices, elements and components required to Provide (see below in this table) that device, equipment, or system.
The Term Shall Mean (*=Shall in Addition Mean) Approved (by CAFB) *without waiving or suspending the full force of Contractor obligation to fulfill the CDs Aspect Distinct feature or element of the project CAFB Government contracting Authority on Columbus Air Force Base
Construction Documents
Drawings, specifications and their references including all Design Criteria and Design & Construction Requirements for this Project.
Contractor The Design-Build entity holding a current Government contract including all personnel in direct or indirect employ of same entity servicing same contract including partners, consultants, subcontractors, suppliers, and manufacturers.
Design Professional (Abbreviated: DP) Professionals including Architects, Engineers and Landscape Architects licensed to practice in one or more states of the U.S.
Day Calendar day unless noted otherwise.
DP Licensed Design Professional fully responsible for all professional design on this project.
Engineer DP For example (e.g.) One among many possible examples Government Columbus Air Force Base Contracting Officer Including [Includes] Including, but not limited to [Includes, but is not limited to] Provide Furnish and install complete, functional, and ready for use without added government action Provision Furnishing & installation complete, functional, and ready for use without added government action Will, must, shall & similar Terms are mandatory directives whereby ‘Term’ = ‘Term + to CAFB satisfaction’ Work The whole or any part, product, system or subsystem of this project Replace Demolish and dispose of existing element. Provide new element of equal or greater value.
Review Review and, if and when acceptable to the government, approval Subcontractor Subcontractor and all personnel in Subcontractor’s direct or indirect employ on any given
Project including suppliers and manufacturers
DESCRIPTION OF PROJECT
2.1 SUMMARY
The Contractor must provide all plant, labor, equipment, transportation, and tools required to repair the dilapidated T-6 Flightline Shacks (Buildings 247, 628, 629, and 633). These buildings will undergo nearly identical repairs to restore plumbing, electrical, heating, ventilation, air conditioning, and interior repairs. Perform all work according to this Statement of Work (SOW), the Concept Design Drawings, and all related AF requirements and other codes and references.
2.2 BACKGROUND
The T-6 Flightline shacks serve as an essential part of maintenance operations for the T-6 Texan II, the initial aircraft that student pilots learn to fly during Undergraduate Pilot Training (UPT). These buildings are required for shift changes, restroom accommodations, maintenance briefings, and supervisory administrative work for maintainers. They also serve as break areas between aircraft maintenance operations. These T-6 Flightline Shacks, Buildings 247, 628, 629, and 633, have become extremely dilapidated; HVAC is ineffective, the plumbing systems and associated fixtures are aged, the electrical systems require upgrades, and the interior finishes are extremely run down with peeling paint, aged doors, and damaged ceiling panels. Each of these T-6 Flightline Shacks requires repairs to improve the quality of life for maintainers.
2.3 SCOPE OF PROJECT
The contractor shall complete the following work in Buildings 247, 628, 629, and 633. These buildings will receive nearly identical repair work as outlined in the following scope of work. Asbestos was not detected in all areas of these facilities. The roof was not tested; if work is done on the roof throughout the course of this project, although unlikely, the Contractor must assume asbestos is present and abatement must occur. Any abatement done must be completed and negative test results must be provided to the 14 CES Air/QRP/Toxics Manager and the 14 CES Environmental Element Chief, 14 CES/CEIE. Lead based paints are not expected to be present, but the Government does not have official reports. If Contractor suspects lead-based paints, he must act in accordance with OSHA safety considerations for lead-based paints.
The following scope of work is required for Buildings 247, 628, 629, and 633:
HVAC:
2.3.1 The Contractor will demolish and replace the existing HVAC unit. The new HVAC unit shall a direct expansion ducted split system with heat-pump operation. The system shall be designed to provide ample conditioned air for the following zones: Areas A-D and restrooms, see locations on attached drawing labeled “Concept Drawing”. Provide load calculations to size to new air conditioning systems to ASHRAE standards. All refrigerant piping is to be insulated per manufacturers recommendations.
Demolish and install new ductwork. New return grilles and diffusers are to be white finished aluminum.
2.3.2 The Contractor will pour a new adequately sized concrete slab with the strength capacity to place and accommodate the new HVAC condensing unit. Provide outside air intake into the building mounted a minimum of 10 feet off of the ground according to UFC 4-010-01. Mount the indoor unit above the ceiling grid system.
2.3.3 Provide a complete TAB report of the system (details including but not limited to those specified in UFC 1-200-02 and UFC 3-410-01. It is the responsibility of the Contractor to obtain this independent, third-party service.
Interior Finishes:
2.3.4 The Contractor shall demolish and remove the existing ceiling and replace with a 2’x2’ grid-style tegular acoustical ceiling tile system. During this process, disconnect and store all sensors, monitors, alarms, and sprinkler heads mounted in the ceiling as needed. Coordinate all fire protection work with the Government and Emergency Services to ensure proper disconnection, draining, testing, storage, and any other necessary components and aspects to perform the modifications. Any damage to fire alarm or fire suppression components caused by Contractor will be fixed or replaced at the Contractor’s expense.
Reinstall and reconnect all previously removed equipment in the ceiling and verify proper operation.
2.3.5 The Contractor shall demolish the walls and doors separating areas C and D from area A, thus opening the whole space to be available for a “cubicle farm” style of orientation. The Contractor shall perform any necessary patchwork to create flat, uninterrupted wall, ceiling, and floor surfaces at locations impacted from demolition.
2.3.6 Demolish all exterior doors and associated hardware and trim, then furnish and install new insulated metal doors in place to meet current ASHRAE 90.1 standards. Provide new hardware and trim, door sweeps, thresholds, door closers, weather stripping, locksets, and anything else necessary for a complete and usable product. Exterior door hardware must be Best 7-pin core compatible. Doors must be factory finished to their final color approved by the Government Project Manager. Repair, prepare, and repaint the frames to conform to base standards and approved by the Government Project Manager.
Prepare and repaint door for main office, Area B. Preparation must include everything necessary to create a smooth, uniform finish. At a minimum, painting should include 1 coat of primer, 2 coats of paint, sanding and prepping of all surfaces, and placing drop cloths on the floor.
2.3.7 Repair, prepare, and repaint all interior walls (Areas A through D). Preparation must include everything necessary to create a level 4 finish. Color shall be Sherwin Williams Accessible Beige or approved equal. Color shall be approved by the Government Project Manager. At a minimum, painting should include 1 coat of primer, 2 coats of paint, sanding and prepping of all surfaces, and placing drop cloths on the floor.
2.3.8 Remove door and door frame from doorway in the restroom vestibule and make flush with hallway wall and main admin area (Area A) wall. Remove floor-fastened doorstop. During floor work (see 2.3.11 below), the Contractor shall ensure damage from doorstop is covered. Remove wainscotting and chair rail on portion of wall extending out from this doorway up to the first corner in area A to create a uniformly level 4 finished wall all the way through the vestibule area.
2.3.9 The contractor shall install a wall mounted fire extinguisher cabinet on the opposite wall in the vestibule, on the inside portion of the wall from where the current door is located. Remove existing fire extinguisher and place in new cabinet.
2.3.10 Prepare and repaint interior window frames throughout. Color shall be Sherwin Williams Accessible Beige or approved equal. Preparation must include everything necessary to create a smooth, uniform finish. At a minimum, painting should include 1 coat of primer, 2 coats of paint, sanding and prepping of all surfaces, and placing drop cloths on the floor. The Contractor shall install ultraviolet tint film on all windows.
2.3.11 Remove existing VCT throughout entire facility. The Contractor will not replace VCT with new VCT but shall instead perform all work necessary to provide a smooth, sealed, and polished concrete floor as the finished product. This work includes cleaning and grinding the floor in its entirety to remove imperfections, spot-repairing any areas of the floor as necessary to provide a smooth and even surface, and any other work necessary to prepare the bare concrete for polishing. After the floor is fully prepared, provide self-levelling sealant across the entire area of the floor and finish with a buffer/polisher to create a smooth and uniformly finished concrete floor.
2.3.12 Furnish and install new 4” cove base throughout the facilities to match interior. Provide color samples to Government Project Manager for approval.
2.3.13 Remove and replace floor drain in entrance corridor and smooth the concrete surrounding drain.
2.3.14 Demolish and replace existing water fountain in Area A with a new wall mounted combination water fountain with bottle filler. water bottle filling style water fountain.
2.3.15 Patch any drywall holes left from communications wiring.
Restrooms:
2.3.16 In both restrooms, the Contractor shall demolish existing toilets and associated piping that cannot properly connect to the new furnished toilets. Furnish and install one (1) new flush-valve type floor mounted toilet in each restroom, to include all service piping for a complete and useable system.
2.3.17 Demolish and replace the existing men’s urinal and all existing pipework necessary. Modify the existing wall protrusion to be uniform throughout the bathroom.
2.3.18 In both restrooms, remove and replace mirror above the sink.
2.3.19 In both restrooms, remove and replace the door to the restrooms and all associated hardware.
These doors shall be a single style restroom type door with all associated hardware including but not limited to hinges, pull handles, push plates, among others.
2.3.20 In both restrooms, remove and store all dispensers: toilet paper, paper towel, soap, and any other dispensers serviced by the base service contract. Deliver these items back to the Government. The Contractor will not reinstall these items.
2.3.21 In both restrooms, demolish and replace the existing floor drain.
2.3.22 In both restrooms, install new exhaust fans. Integrate exhaust fan operation into and the light switch, programmed to remain on for an adjustable period of time after the restroom becomes vacant.
2.3.23 In both restrooms, furnish and install new 4” cove base to match interior. Provide color samples to Government Project Manager for approval.
2.3.24 In both restrooms, demolish and replace existing sink, p-trap, trap-on, and tailpiece and replace with like-sink and PVC items.
2.3.25 In both restrooms, remove the existing outlet, faceplate, and outlet conductor. Furnish and install all components including but not limited to outlet, faceplate, conductor, among others as required for a GFCI outlet to be complete and useable
2.3.26 The floors will be demolished and replaced with new vinyl composite tile. Color shall conform to base standards and be approved by the Government Project Manager.
2.3.27 In both restrooms, repair, prepare, and repaint interior walls. Preparation must include everything necessary to create a level 4 finish. At a minimum, painting should include 1 coat of primer, 2 coats of paint, sanding and prepping of all surfaces, and placing drop cloths on the floor.
2.3.28 In both restrooms, demolish existing sheetrock ceiling and replace with 2’x2’ grid-style tegular acoustical ceiling tile – see Section 2.3.4.
Electrical:
2.3.29 Demolish existing 1’x4’ LED flat panels in bathrooms and hallway with 2’x4’ LED flat panel lights. Furnish and install new 2’x2’ LED flat panel lights, switches, and lighting controls in accordance with (IAW) UFC 3-530-01 throughout the facility. This includes occupancy sensors and dimming protocols; the Contractor shall install any associated components for new lighting systems, including, but not limited to, conductors, conduit, and conduit supports. Provide all new light with new fixture whips.
Reuse existing wiring, conduit, and breakers where possible, but furnish and install any wiring, conduit and breakers as required to ensure the electrical system is complete and usable. Reinstall and reconnect all previously removed equipment in the ceiling and verify proper operation.
2.3.30 Demolish and replace existing exterior lights with full cutoff style LED fixtures next to both entrance doors. Demolish and replace switch boxes.
2.3.31 Remove existing main panelboard and associated breakers. Furnish and install new main panelboard with appropriately designed breakers. Reuse existing conduit and wiring wherever possible but furnish new conduit and wiring as required.
2.3.32 Thermostat for the new HVAC unit shall be wall mounted. The thermostat shall provide the user with a ±2°F adjustment through warmer cooler adjust.
2.3.33 Demolish and replace the main disconnect switch on the outside of the facilities near the existing heat pump. Install all new conduit and wiring as necessary.
2.3.34 Demolish and remove existing faceplates, receptacles, outlets, junction boxes, conductors, and light switches that cannot be reused in their entirety throughout the facility. Test before demolition to ensure power is disconnected. Furnish and install new faceplates, receptacles, outlets, junction boxes, conductors, and light switches as necessary to supply the entire facility. Color to be selected by Base Architect. Design shall ensure new receptacles are connected to the best option existing circuit or new circuit and shall follow applicable UFCs and local and national codes. Design and approval to be completed by Electrical P.E. Install outlet boxes, conduit, and conductors within the new and existing interior and exterior walls to have uninterrupted, flat wall surfaces. Install receptacles and faceplates flush to the new and existing interior walls.
2.3.35 The Contractor shall ensure there are adequate receptacles on the new admin area after Areas C and D are joined with Areas A.
2.3.36 Furnish and install emergency exit signs and egress lighting in accordance with NFPA 101.
Communications:
2.3.37 The Contractor shall coordinate communication work with the Base Communication Officer (BCO) to achieve designs necessary for future implementation of a complete and functional communication system. Work shall follow UFC 3-580-01 Telecommunications Interior Infrastructure Planning and Design.
2.3.38 The Contractor shall install any required size conduit, cable supports, and pull strings for all new communication locations. The Contractor shall not install cables, faceplates, and jacks. Keep existing conduit in place for future circuit connections by Base Communications, and repair any damages to existing communications components.
2.3.39 The Contractor shall not demolish the communications node on the wall separating Areas C and D from Areas A. The Contractor shall remove and suspend this communication node unless otherwise directed by Base Communications Officer.
2.4 GOVERNMENT FURNISHED EQUIPMENT/MATERIALS
The Government will not furnish any equipment or materials for this project.
2.5 SALVAGE
The following are to be salvaged and returned to the Government:
2.5.1 Each existing DX Unit in Buildings 247, 628, 629, and 633
DESIGN REQUIREMENTS
3.1 SUMMARY
Design will consist of all site investigations and design work associated with preparing complete contract documents for this project as described in this SOW. The design documents must be developed from the functional and technical data contained in this SOW and include construction drawings, schedules, and design analysis. The Contractor will also be required to submit design documents for review as described in Paragraph 3.6 as well as final contract documents. The Contractor will be required to attend review and conference meetings as needed and requested by the Government.
3.2 NATURE/EXTENT OF DESIGN
3.2.1 This project requires the services of licensed Design Professionals. The project requires plumbing design and details for the demolition of existing and subsequent installation of new plumbing fixtures.
Mechanical design and details are required for this project with new HVAC units being installed.
Electrical design and details including variable frequency drives, power, conduit, circuit breakers, wiring, etc. are required. Professionally sealed drawings are required. Design/shop/coordination drawings, materials and equipment submittals, and final as-built record drawings are required for this project.
Contractor must maintain accurate redline As-Builts throughout construction and must submit final As- Built drawings (with any of the redline changes updated on the drawings) upon project completion (see paragraph 4.7.2 for more information).
3.2.2 Due to the nature of work and mission requirements within these flightline shacks, the design shall establish a phasing plan for construction to be approved by the Government, facility occupants, and the Contractor. Phasing is required as shutdown of all four facilities at once is not possible. Phasing requires working in only one building at a time. The customer will work to create a phasing plan for employee relocation during this project. The Contractor shall submit preliminary phasing for Government review and comments by the 35% design submittal. Contractor shall submit final phasing for Government review and comments by the 65% design submittal.
3.2.3 Provide psychrometric/load design analysis of all renovated HVAC systems detailing the systems’ compliance with all applicable codes and standards. See UFC 3-401-01 and UFC 3-410-01 for details on the required HVAC design analysis. Psychrometric/load design analysis is to be provided to the Government at the 35% design.
3.2.4 Provide complete sequence of operations for HVAC systems including, but not limited to, start up, occupied operation (heating and cooling), unoccupied operation (heating and cooling), nighttime setback, and any other necessary components.
3.2.5 Provide photometric analysis of all renovated lighting systems detailing compliance with all applicable codes and standards. See UFC 3-530-01 for details on the required photometric analysis.
Photometric analysis is to be provided at the 35% design.
3.3 RESPONSIBILITY
3.3.1 Due to the nature of work and mission requirements within these flightline shacks, the design shall establish a phasing plan for construction to be approved by the Government, facility occupants, and the Contractor. Phasing is required as shutdown of all four facilities at once is not possible. Phasing requires working in only one building at a time. The customer will work to create a phasing plan for employee relocation during this project. The Contractor shall submit preliminary phasing for Government review and comments by the 35% design submittal. Contractor shall submit final phasing for Government review and comments by the 65% design submittal.
3.3.2 Due to the nature of work and mission requirements within the facilities the Contractor must ensure that all required materials, equipment, and labor is available and on-site before beginning construction actions of this project. Contractor shall notify the Government when everything is available and on-site, and receive approval by the Government to perform construction actions of this project.
3.3.3 Contractor must perform all services, including travel, required to prepare and to furnish complete design documents consisting of drawings, analysis, and addenda as required, for the construction of the project in accordance with this SOW.
3.3.4 Record drawings are provided to the Contractor as a courtesy at the discretion of the Government, but their accuracy is not guaranteed. The Contractor is responsible for doing his own field investigations of the utilities, existing conditions, and other items in the area.
3.3.5 Although the sizing and specification of major equipment is suggested by this SOW, the Contractor is responsible for all remaining design and coordination to provide an acceptable final product that meets intent of this SOW. Contractor is responsible for ensuring constructability and code compliance.
3.4 DESIGN STANDARDS
All design and construction must be accomplished in accordance with applicable UFC’s, ETL’s, (UFC’s and ETL’s may be found on-line at www.wbdg.org.) local and national codes, Columbus AFB Installation Facility Standards (IFS) and all Appendices (Special Construction, Mechanical, and Electrical) and other guidance as modified by this SOW. The IFS document may be found at the following location:
http://www.wbdg.org/ffc/af-afcec/installation-facilities-standards-ifs/columbus-afb-ifs. The list of documents includes, but is not limited to, the latest editions of the following
1) UFC 1-200-01 DoD Building Code (General Building Requirements)
2) UFC 1-200-02 High Performance and Sustainable Building Requirements
3) UFC 3-401-01 Mechanical Engineering
4) UFC 3-410-01 Heating, Ventilating, and Air Conditioning Systems
5) UFC 3-410-02 Direct Digital Control for HVAC and Other Building Control Systems
6) UFC 3-410-04 Industrial Ventilation
7) UFC 3-501-01 Electrical Engineering
8) UFC 3-520-01 Interior Electrical Systems
9) UFC 4-010-01 DoD Minimum Antiterrorism Standards for Buildings http://www.wbdg.org/ffc/af-afcec/installation-facilities-standards-ifs/columbus-afb-ifs
10) NFPA 101
11) NFPA 72
12) NEC 70
13) ACGIH: Industrial Ventilation Manual
14) Columbus AFB IFS
15) CAFB Base Standards
The Contractor must submit a written request for approval of any deviations from the Government's established standards. No deviations from the Government's established standards will be permitted unless the Contracting Officer has issued prior written approval of such deviation.
3.5 DRAWINGS
Drawings under this Contract must be well prepared, complete, and accomplished in accordance with the best professional practice to show clearly and concisely the type and extent of work to be performed.
3.5.1 Drawings must be drawn to appropriate scales and dimensioned completely and accurately.
Lettering must be large enough to ensure legible half-size reduction and each dimensioned drawing must have a graphic scale. Use of fractions less than 1/8-inch for building dimensions must be avoided. Use standard building material indications and symbols for architectural items and for mechanical, electrical and plumbing equipment.
3.5.2 The Contractor will use paper sheets, 24" x 36". Each sheet will be numbered consecutively beginning with "1 of (x) Sheets" and continue to the last sheet. Number individual drawing sheets as follows:
Drawing Sheet Subject Notation Additional Sheets
Cover (Title Sheet, Map and Index)
T1 and following
Civil/Site Work C1 and following Demolition D1 and following Landscaping L1 and following Architectural A1 and following Structural S1 and following Plumbing P1 and following Mechanical M1 and following Electrical E1 and following
Note: All sheet subjects above may not be necessary for this project
3.5.3 Drawings must be prepared electronically in both AutoCAD (Release 2020) and PDF formats.
3.6 DESIGN SUBMITTALS
3.6.1 DELIVERY: Deliver two (2) hard copies of each submittal and one (1) digital copy via DoD SAFE containing each drawing sheet in PDF file format directly to the CO, along with AF Form 3000. For uploading to DoD SAFE, the Contractor must request an upload link from the CO and then upload the files using the details in the subsequent email from DoD SAFE. For the final design submittal (As-Builts in most cases), the contractor is to provide, in addition to the hard copies and digital copies via DoD SAFE, containing the PDF file as well as the associated CAD files in AutoCAD (Release 2020) .dwg file format. Hard copy submittals must be delivered to:
14th Contracting Squadron 495 Harpe Blvd, Suite 293 Columbus, MS 39710
3.6.2 SUBMITALS AT INTERMEDIATE STAGES OF DESIGN COMPLETION: To facilitate review and feedback throughout the design process, designs are submitted at various stages of completion as follows:
1) 35% DESIGN SUBMITTAL: Contractor must submit 35% design documents within 21 days after Notice to Proceed (NTP). The 35% design must include complete and thorough detailing to leave no question as to how demolition and construction is intended. All design documents must be clearly annotated (in both title block and revision block of drawings) with “35% REVIEW SET” and the date.
2) 65% DESIGN SUBMITTAL: Contractor must submit 65% design documents within 21 days after receipt of the “Approved” 35% design. The 65% design must include complete and thorough detailing to leave no question as to how demolition and construction is intended. All design documents must be clearly annotated (in both title block and revision block of drawings) with “65% REVIEW SET” and the date.
3) 95% DESIGN SUBMITTAL: Contractor must submit 95% design documents within 21 days after receipt of the “Approved” 65% design. The 95% design (essentially complete design and drawings, pending review and acceptance by Government as the 100% APPROVED CONSTRUCTION SET) must include complete and thorough detailing to leave no question as to how assembly is intended. All design documents must be clearly annotated (in both title block and revision block of drawings) with “95% REVIEW SET” and the date.
4) 100% DESIGN/APPROVED CONSTRUCTION SET: Contractor must submit the 100% DESIGN APPROVED CONSTRUCTION SET within 14 days after Contractor receipt of the “Approved” 95% design. The construction set must incorporate and/or address any Government comments on the 95% design and should leave no question to how demolition and construction will be done. If professionally stamped and sealed drawings are required for this project (paragraph 3.2), the approved construction set must include all stamped drawings. All final design documents must be clearly annotated (in both title block and revision block of drawings) with “APPROVED CONSTRUCTION SET” and the date.
5) For each holiday or extraordinary event in a submittal period, increase the required days for submittal by one day for each day in the event. Deliver no submittals within (before or after): one week of Thanksgiving; two weeks of Christmas; or one week of New Year’s Day. Extraordinary Events include: unscheduled holidays for base personnel; base-wide training exercises; etc. The Government may prohibit work during such events.
3.6.3 PARTIAL SUBMISSIONS: Partial submissions normally will not be accepted. However, under some circumstances, to expedite project execution, the Government may accept design/shop drawings or material submittals for major elements or long-lead-time equipment for review and approvals prior to 95% design submittal. Government approval of such items does not relieve the Contractor of his responsibility to ensure a complete, constructible, code-compliant design.
3.6.4 CONSTRUCTION PRIOR TO 100% DESIGN: Construction may not commence until Government approves the 100% design. Exception: To expedite contract completion, Contractor may petition CO for an Interim Notice to Proceed with specific elements of construction. Government review does not constitute approval or acceptance of any variations from this SOW, the Contractor’s Proposal, or the Contract unless authorized in writing by the CO. The Interim Notice to Proceed, if exercised, will in no way mitigate the responsibility of the Contractor to provide a complete, constructible, code-compliant design.
All drawings, specifications, design analyses and other project materials become the property of the Government.
3.7 DESIGN REVIEWS
3.7.1 DESIGN PHASE REVIEWS: Government review of each XX% design submittal (where XX = 95 or 100 as required per 3.6.2) will require up to fourteen (14) days after Government receipt. The Government will determine the sufficiency of each XX% design submittal as follows:
1) Approved as Submitted. If design is sufficient to proceed without correction to the next phase submittal, one (1) copy of AF FORM 3000 marked "Approved" will be returned to the Contractor.
Contractor must advance to the next stage design submittal.
2) Approved - Except as Noted. Design submittals that have only minor errors or deficiencies will be marked in red to indicate necessary corrections. Marked materials, along with one (1) copy of AF FORM 3000 indicating "Approved - Except as Noted" will be returned to the Contractor.
Contractor must revise the design documents, making the necessary corrections, and advance to the next stage design submittal.
3) Disapproved. Design submittals that are incomplete or require more than minor corrections will be marked in red to indicate necessary corrections. Marked materials, along with one (1) copy of AF FORM 3000 marked “Disapproved” will be returned to the Contractor. Contractor must revise the design documents, making the necessary corrections, and re-submit as the current stage “XX% Design – 2nd (or subsequent) Submittal”.
4) Disapproved – Major Deficiency. Examples include, but are not limited to, design submittals that fall significantly short of indicated level of completion, grossly deviate from or misinterpret the SOW, or contain errors of a nature or quantity that indicate failure of Contractor to review submittals for completeness, correctness, and coordination between trades. For such submittals, the Government will not complete a comprehensive review or provide an exhaustive list of needed corrections. Rather, one (1) copy of AF FORM 3000 marked “Disapproved – Major Deficiency” along with general reason(s) for disapproval will be returned to the contractor. The CO will issue a written warning to the Contractor that any subsequent grossly incorrect/incomplete submittals constitute evidence of inability to complete the project and may result in declaring the Contractor “In Default.” Contractor must correct deficiencies and resubmit as current stage “XX% Design – 2nd (or subsequent) Submittal”.
3.7.2 100% DESIGN REVIEW: The Government will have fourteen (14) days to verify that all review comments have been addressed and no unapproved changes have been made. Upon Government approval of the 100% design documents, the Contractor may begin construction.
3.7.3 IMPACT OF REVIEW ON PERIOD OF PERFORMANCE: Contract completion time includes time for Government review of drawings, specifications, and material submittals. Unless otherwise noted, the Government will use no more than 14 calendar days for review of each design submittal and each subsequent re-submittal of “Disapproved” submittals (paragraph 3.7.1, c or d). There will be no increase in the period of performance for review of re-submittals.
3.7.4 RESPONSE TO REVIEW COMMENTS: The Contractor is required to respond to all review comments and submit their annotated comments as a design analysis appendix in the subsequent design submittal. All comments must either be accepted and incorporated into the next design submittal or satisfactorily rebutted.
3.7.5 DESIGN ACCOUNTABILITY: The Contractor is solely responsible for accurately designing and constructing everything necessary to provide a fully functional product. Government approval of any design or design-related submittal does not waive or remove full liability from the Contractor to provide a design, facility, or final product that meets the intent of this SOW, performs as intended, and adheres to all applicable codes and standards.
3.8 CONFERENCES
3.8.1 PRECONSTRUCTION CONFERENCE: A Preconstruction Conference (Pre-Con) will be held at the Contracting Office as indicated.
3.8.2 COORDINATION/REVIEW CONFERENCES: Coordination/review conferences may be held from time to time as required. The Contractor may request such conferences when it is deemed necessary by both parties to clarify the work or expedite the preparation of plans, specifications or construction.
3.8.3 REVIEW/CONFERENCE MINUTES: The Contractor will be responsible for making memoranda of record of any conversations and minutes of any meeting with Government personnel concerning this project and forward one copy of these memoranda/minutes to each party concerned and one copy to the Contracting Officer within seven (7) days. The final version of the meeting minutes will be approved and filed at the CO’s discretion. Each copy will be numbered consecutively and chronologically.
3.8.4 MEETING LOCATIONS: Meetings will be held in person at Columbus Air Force Base.
Contractor transportation costs for attending all conferences/reviews and meetings must be included in the Contractor’s Proposal. There will be no teleconferences unless permitted otherwise by the Contracting Officer.
End of Design Requirements
ADMINISTRATION OF CONSTRUCTION
4.1 PERFORMANCE CAPABILITIES
4.1.1 One week prior to the start of work under this contract, Contractor must submit in writing to the CO for review and possible approval the names and credentials of Contractor Project Manager, Contractor Site Superintendent, and Quality Control Manager. Subsequent proposed changes of approved personnel must be submitted in writing to and receive prior approval from the CO before working on the project. Each of these personnel may upon CO approval hold additional onsite duties which must not diminish their required performance. Contractor must demonstrate to the Government’s satisfaction that proposed personnel exceed education, technical and experience levels of personnel described in this Contract including the following:
1) Contractor Project Manager (CPM) - Provide management of the prime contract to include subcontract purchasing and administration, review of material submittals and shop drawings. CPM must have full authority to develop cost proposals, negotiate with Government and subcontractors, sign awards and modifications, supervise project superintendents, attend weekly CO/CE/PM Contractor status meetings as well as pre-performance site visits, pre-final and final inspections.
The CPM must have a minimum of 5 years previous experience as primary contract manager or equivalent experience as a primary estimator and negotiator with a contracting firm engaged in similar multi-discipline commercial construction projects. CPM must also have not less than 5 years’ experience managing subcontractors.
2) Contractor Site Superintendent (CSS) - Provide on-site construction superintendent(s) to oversee all work under this contract. Site supervision must be daily (constant throughout each day) and includes submission of detailed weekly progress reports, scheduling and coordination of subcontractors and material suppliers, and attendance at all construction progress meetings, CO site visits, and pre-final and final inspections. Superintendents must have a minimum of 5 years previous experience as a project superintendent (exclusive of time employed as a tradesman or working foreman) for a general contracting firm overseeing one or more multi-discipline commercial construction projects. The superintendent must be available within 15 minutes during all normal working hours, except for such incidental errands as required by his duties. The superintendent must be responsible for the proper coordination and timeliness of the work, and for the proper workmanship of all trades; therefore, his absence from the project site without a suitable substitute Contractor representative must be considered as damaging to the Government.
3) Quality Control Manager (QCM) - Provide quality control management for the project. QCM must continually (constant throughout each day) ensure full compliance with all safety requirements, verification that work and materials in place and stored on site are in accordance with the approved construction documents, shop drawings and material submittals. QCM must submit daily status reports recording activities at each project site, prepare and coordinate material submittal sheets and shop drawing submittals, schedule and coordinate testing procedures, prepare quality control reports for construction progress and other required meetings, and attend all pre-final and final inspections. QCM must have a minimum of five years’ experience in Quality Control Management of multidiscipline construction projects.
4.1.2 Contractor must have additional personnel including management, technical, service, labor or subcontractor, available as necessary to fulfill all construction contract requirements. The Government may restrict employment under this contract of any personnel identified as a potential threat to the health, safety, security, well-being, or operational mission of CAFB and its population.
4.1.3 Contractor must be available by telephone 24-hours a day, 7-days a week and upon 15 minutes’ notice during normal duty hours and 30 minutes’ notice during non-duty hours must meet the CO at a CO designated location.
4.2 COMMENCEMENT, PROSECUTION & COMPLETION
4.2.1 Contractor must start design and various construction phases at times specified by CO issued Notice(s) to Proceed (NTP), prosecute the work, and complete the entire work within the Period of Performance.
4.2.2 Contractor must provide a Submittal Log (Schedule of Material Submittals), Progress Schedules, Progress reports and Status Reports.
1) Submittal Log: See Material Submittals and Shop Drawings below.
2) Progress Schedule: (AF Form 3064) Submit the progress schedule to the CO within 10 days after contract award, unless otherwise specified by the CO. Subdivide total schedule into individual work items. Show completed work percentages at the end of each two-week reporting period. Progress schedule should only be resubmitted during the project duration if there’s an issue with Period of Performance or if deemed necessary by the CO as described in 4.2.2.3.
3) Progress Reports: (AF Form 3065) Submit Project Progress reports to the CO minimum twice per month on the first working day of each month and again on the 15th. Describe the percentage of work completed during the report period. If behind schedule, report in writing what actions will be taken to regain the schedule. If the CO agrees to add days to the contract performance period, Contractor must provide an amended schedule.
4) Status Reports: Submit to the CO daily reports of the work status. In each report, list the tasks accomplished for that day, any deliveries received, equipment currently on-site, weather conditions for that day, and number of personnel working on each area listed by trade. Photos may be included.
4.2.3 Period of Performance: Is the period between the issuance of the NTP and the time all construction is complete, including all punch list items, and final inspection is approved by the Government. The total Period of Performance for this project is 330 days.
4.2.4 Contract Completion: At contract conclusion, vacate all work areas, including: Contractor offices, storage and staging areas, and individual work sites. Restore these areas to their condition prior to Contractor occupancy not more than 14 days from the earlier of: approved final inspection or CO notification.
4.2.5 Coordination and Project Conditions: Schedule and manage submittals, materials, products, equipment, manpower, etc. to control all parts of the work efficiently and orderly. Verify compatibility of existing building utilities with new operating equipment. Coordinate required space, supports, and mechanical and electrical work shown (even if via diagrams) on Drawings. Follow routing shown for pipes, ducts, and conduit; place runs parallel with building lines. Use space efficiently to maximize maintenance and for repair accessibility for other systems. Conceal wiring behind finish surfaces and locate fixtures and outlets with finish elements. Coordinate pre-Substantial Completion clean-up in separate building areas.
After CAFB occupancy, coordinate site access to correct defective (or non-compliant with CDs) to minimize disruption of Government activities.
4.2.6 Cutting and Patching: Only employ skilled and experienced workers to cut and patch. Report in writing to the CO wherever cutting and patching might degrade: safety; appearance, structure, weatherproofing, O&M, or separate Contractor or government construction. Prevent damage to existing or new construction and provide proper surfaces to receive patching and finishing. Match new finishes to existing adjacent surfaces unless noted otherwise. Maintain integrity of existing walls, ceilings, or floors;
completely seal voids. Refinish entire assemblies and continuous surfaces to nearest intersection. Cut, fit, and patch where CDs require e.g.: mechanical and electrical penetrations; integration of new components with one another or with existing construction; removal and replacement of defective and non-conforming elements; remove samples for testing.
4.2.7 Special Procedures: Employ skilled and experienced tradespersons to perform alteration work.
Remove debris from open work areas and concealed spaces. Remove, cut, and patch to minimize damage and provide means of restoring products and finishes to original or specified condition. If a change of plane of 1/4 inch or more is discovered, submit recommendation to the CO for providing a smooth transition.
Patch or replace portions of existing surfaces which are damaged or showing other imperfections. Finish surfaces as specified.
4.2.8 Airfield Waiver: The work will be done on or near an active airfield and special considerations apply for vehicle traffic control and work in the vicinity of the airfield. A FOD control plan must be established and maintained at all times. Vehicle operators must be trained on flight line driving procedures prior to entering the airfield. Disruptions to airfield activities must be scheduled with the Government in advance. The airfield is a controlled area; contractor shall comply with CAFB controlled area procedures. Coordinate with the Government and provide any assistance needed to prepare an Airfield Waiver. Work may not start on the airfield until the waivers are approved. Waiver information shall be supplied a minimum of 30 days before desired start date.
4.2.9 Welding Permits: No cutting or welding will be permitted without first obtaining a permit issued by the Base Fire Department. All fire and safety regulations are to be followed stringently. Contractor’s failure to obtain a cutting or welding permit may not be reason for extending the contract performance period. Any damages incurred while welding work is done without a permit are the responsibility of Contractor.
4.3 SCHEDULING
4.3.1 Contractor must coordinate all work schedules and manage progress of work with the CO and CEPM prior to start of work. Weekly progress meetings will be conducted with the CO, CMI, and Contractor’s team which may require corporate management representation at CAFB discretion.
4.3.2 Contractor must schedule all work. Performance periods must not be established or extended to accommodate insufficient personnel resources. Contractor will not move crews on and off the project while making minimal progress on concurrent projects as this must be construed as having an inadequate work force to fulfill the contract requirements. Contractor’s CPM and CSS must not change more than two (2) times during project construction as this would demonstrate an inadequate management force to fulfill contract requirements.
4.3.3 Before construction begins, Contractor must agree with CO on a sequence of procedures; means of access to premises and buildings; materials and equipment storage space; delivery of materials and use of approaches, corridors, and stairways. Contractor may be required to revise the CD work-phasing schedule.
4.3.4 Contractor must ensure that all required materials, equipment, and labor is available and on-site before beginning construction actions of this project. Contractor shall notify the Government when everything is available and on-site, and receive approval by the Government to perform construction actions of this project.
4.3.5 Interference and inconvenience to Government operations and personnel caused by project work including use and delivery of materials, tools and equipment must be kept to a minimum.
4.3.6 The Government may require that work, so far as practicable, be done in separate phases. Each phase may relate to a different occupied or unoccupied area, in which work in one area must be completed before work in another area may begin. Phased work areas must be clearly delineated and annotated in the CDs.
4.3.7 Hours of Work: Normal work hours will be Monday through Friday from 7:30am to 4:15pm excepting days observed as Federal Holidays as listed below: