SOW STA Hatteras Inlet - HVAC Replacement.pdf
PDF 195 KB Posted
- Solicitation number
- 70Z08126QELIZ0022
About this file
This is a Scope of Work and Specifications document for a federal HVAC replacement project at USCG Station Hatteras Inlet, North Carolina.
The contractor must remove and replace existing HVAC equipment at the Main Building (Multipurpose Building), including three packaged rooftop units currently serving different areas of the facility. The new equipment requirements include three packaged heat pump units rated at 3-ton, 2-ton, and 3-ton capacities respectively, all 208/230 volt with auxiliary heaters (10 KW, 5 KW, and 10 KW), rooftop curb adapters, and digital thermostats. The contractor must perform complete installation per North Carolina building and mechanical codes, including electrical work with licensed electrician certification, ductwork modifications and balancing, thermostat installation, and comprehensive testing and commissioning with TAB reporting. The work scope also requires removal of existing equipment and disposal offsite, repair of all building penetrations, and provision of Operation and Maintenance manuals and one-year equipment warranty. All personnel must possess current EPA CFC/HCFC/HFC refrigerant handling certifications per 40 CFR Part 82, Section 608. The project COR is Christina Gramza, Facilities Engineering Officer, Sector North Carolina.
Contract requirements include mobilization within 10 calendar days of award and work completion within 30 calendar days. Required submittals include initial and final product data, mechanical and electrical licenses, EPA certification, past performance documentation, and project schedule within specified timeframes. Normal working hours are 0700-1600 Monday through Friday. The contractor bears full responsibility for work site safety, environmental compliance including wastewater management and hazardous material handling, and any damage to government property. Site visits require pre-arrangement with minimum three-day advance notice and visitor access forms. All work must comply with NFPA 70, ASHRAE 62.1 and 90.1 standards, OSHA regulations, and applicable federal and state laws.
Scope of Work
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work and Specifications
STA Hatteras Inlet - Replace HVAC in Multipurpose Building
July 2026
Project COR
Name: Christina Gramza Email: Christina.A.Gramza@uscg.mil Facilities Engineering Officer Sector North Carolina
1. Scope:
The Contractor shall provide all necessary transportation, labor, equipment, materials, parts, tools, necessary to remove and replace the existing HVAC equipment. The Contractor must perform testing and commissioning of the new equipment. The work will be performed at USCG Station Hatteras Inlet at the following locations:
• Main Building – Multipurpose Building
2. Government Facilities and Utilities:
a. Electrical power is available on the site. The Contractor will be permitted to utilize these utilities in performing the work, provided that the existing systems are not overloaded.
b. Telephone services will not be available for use by the Contractor.
c. Building restroom facilities are not available for use.
d. The Contractor, their employees, and any sub-contractors shall become familiar with and obey all Station regulations. All personnel employed on the project shall keep within the limits of the work area and shall not enter any other area outside of the work site unless to do so in the performance of their duties. Work site and execution must be arranged so as not to disrupt normal operations in this area. There shall be No Smoking in any Coast Guard building. All smoking must be done only in a designated smoking area.
3. Materials and Locations:
a. Materials shall be delivered to the jobsite in their original unopened packages, clearly marked with the manufacturer’s name, brand name, and description of contents. Storage shall be in accordance with manufacturer’s recommendations in a clean, dry, well-ventilated area. Stored materials shall be protected from sunlight and kept away from excessive heat. Insulation board shall not be exposed to flame or other ignition sources. The Contractor shall not store any highly flammable materials in the work area. Sufficient area for staging is available on site; storage areas will be pre-approved by the Contracting Officer’s Representative (COR). Special precautions shall be taken to ensure construction materials and debris do not enter the roadways or water.
b. Laydown areas will be approved by the COR with coordination from the Station Environmental Compliance Office. Any damage to vegetated areas shall be repaired and reseeded by the Contractor.
4. Labor Laws:
a. See Section 52.222 of the contract clauses for applicable labor requirements, and the attached wage determination for prevailing rates that must be paid to covered workers.
5. Safety:
a. The Contractor is wholly responsible for work site safety. The Contractor shall implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property, and avoids work interruptions. The Contractor shall provide appropriate safety barricades, signs, signal lights, etc. as well as complying with the requirements of all federal safety regulations as published by the Occupational Health and Safety Administration, 29 CFR 1910 (series), 29 CFR 1926 (series), State and Local safety laws, rules, and regulations. Any operation defined as “Hot Work” as per OSHA/NFPA requires a permit to be issued by Station Hatteras Inlet. This includes welding, cutting, brazing, grinding or any work that could produce sparks or heat and may initiate a fire.
6. Environmental Compliance:
a. Environmental Discharges
i. The Contractor shall ensure all discharges do not exhibit contaminates contrary to Station Hatteras Inlet Non-Significant User (Wastewater) Permit. Any flushes, backwashes and or slug loads shall be scheduled and reported to Station Hatteras Inlet Environmental Compliance Office Wastewater Permit Manager at least two weeks in advance. Wastewater associated with any maintenance or repair shall be quantified in a maintenance schedule. All work will be performed in accordance with the Station Spill Prevention Control and Countermeasures Plan, Clean Water Act and the Station Stormwater Pollution Prevention Plan. All activation flushes of the system shall be captured and disposed of IAW Dare County Sewer Use Ordinance and USCG Station Industrial User Wastewater Permit. All storm drains within range of a potential discharge shall be covered/sealed during installation and kept covered until the work has been completed and the system has been deemed fully operational and compliant with all applicable Coast Guard policies/plans/permits/laws/ordinances. All storm drains and waterways within range of a potential discharge shall be covered/sealed or protected by silt fence. Nothing shall be discharged to a storm drain at any time during the project. If an Erosion and Sediment Control Plan is required, then these shall be preapproved by Station Environmental Compliance Office. All spills shall be reported to SFO Environmental Protection Specialist Office (Todd Ogle) at (252) 269-0112 after containing and dialing (252) 395- 0253 for Station Officer of the Day to activate Station Spill Response.
b. Waste
i. Any waste as a result of the project shall either be recycled in accordance with CIM 16455.10 and the Station Pollution Prevention Plan or be disposed of in accordance with the Resource Conservation and Recovery Act. Any Hazardous Waste shall be manifested off site with Base listed as the generator and signatory. Any hazardous waste shall be analyzed, characterized, stored and disposed of in accordance with the Resource Conservation and Recovery Act and all applicable federal, state and local laws and ordinances.
c. Chemicals
i. All chemicals required for this project shall be preapproved by the
Station Environmental Compliance Office. All applicable Safety Data Sheets shall be provided to both the Station Environmental Compliance Office and Station Safety Officer upon request. Proper storage shall be provided in accordance with 29 CFR 1910.1200. All installation related solid waste shall be removed from the Station after each working day. All extra chemicals and products shall be removed from the site upon work completion, as the Emergency Planning and Community Right-To-Know Act requires Coast Guard to maintain an inventory of all Hazardous Materials located at the site.
The Contractor is required to comply with local VOC laws and regulations.
7. Liability of Contractor:
a. Any damage to government property caused by the Contractor shall be repaired or replaced by the Contractor at no cost to the government. The Contractor shall not disconnect any service without approval from the COR.
8. Existing Site Conditions:
a. The Contractor must satisfy themselves with the existing site conditions and the work to be performed. All potential Contractors are strongly encouraged to visit the site to field verify any/all quantities before submitting proposals.
All visitors must complete a visitor access request form in accordance with Station security policy and present a valid Real ID or passport as a method of identification. Visitors with a valid Military ID or RAPIDGate pass will not be required to complete the access form. Interested Contractors shall make arrangements for site visits with the COR. All site visits are to be prearranged a minimum of three (3) days in advance. To arrange a site visit, the following information must be provided: full name, date of birth, and driver’s license number.
b. After award, all Contractors that require Station access will have to be pre-vetted for entry prior to commencement of work. All work that has a period of performance greater than 10 days may be subject to obtaining a RAPIDGate pass as a method of Station entry.
9. Site Restoration & Clean Up:
a. The work site shall be cleaned up at the completion of each workday. The
Contractor shall take special care to contain dust while working. Upon completion of the job, the Contractor shall clean up the job site, returning it to a state of cleanliness equal to or exceeding that in which it was found. The Contractor shall properly dispose of any trash, extra materials, dirt, debris, or other litter that remains. There will be no final acceptance of the contract until the COR approves the appearance of the job site.
10. Contract Timeline:
a. Schedule of Work:
i. A workday is defined as any non-weekend or non-Federal Holiday. The Contractor shall perform all work during normal Station work hours.
The normal Station working hours are 0700 – 1600, Monday through Friday. If the Contractor would like to work outside normal working hours, permission must be obtained from the COR.
ii. The Contractor shall provide all required information and complete this contract within the time schedule below, unless approved by the Contracting Officer.
iii. Provide all required submittals to the Contracting Officer within 10 calendar days after contract award.
iv. The COR will have 7 calendar days to review the submittals and respond to the Contractor.
v. The Contractor, upon receiving notification to proceed and acceptance of submittals, must mobilize to the site within 10 calendar days.
vi. Completion of work shall be accomplished within 30 calendar days from notification to proceed and acceptance of submittals.
vii. The Contractor shall schedule all work with the COR. The Contractor shall understand the importance to schedule and complete all work in a timely fashion.
viii. The Contractor may notify the Contracting Officer of any long lead time equipment or materials and request a modified delivery date of the work.
b. Contract Submittals:
i. The following list of submittals must be submitted on the timeline indicated and define the specific minimum requirements for this contract. The submittal shall contain sufficient information that can be used to determine compliance of the material with these specifications and referenced specifications.
Submittal Deliverable Required Submittal Timeline
Pre-Bid Site Visit Request Information ☒ In accordance with solicitation posting
Initial Product Data
• Packaged HVAC Unit
☒ With quote/proposal
Certifications/Licenses
• Mechanical License
• Electrical License
• EPA License
☒ With quote/proposal
Past Performance of Related Work ☒ With quote/proposal
Final Product Data
• Packaged HVAC Unit
Within 7 calendar days after
Contract Award
Project Schedule ☒ Within 15 calendar days after
Contract Award
Operation and Maintenance Manuals ☒ Within 15 calendar days after completion of project*
Product Warranty Information ☒ Within 15 calendar days after completion of project*
Final TAB Report ☒ Within 15 calendar days after completion of project* Post-Award Site Visit Request
Information ☒ As required
*Final payment will not be made until all deliverables are submitted and accepted.
11. Detailed Technical Requirements:
• The Contractor shall provide all necessary transportation, labor, equipment, materials, parts, and supervision to demo the existing HVAC equipment and install a new packaged unit IAW specification provided at Main Building – Multipurpose Building. Attachments have been provided including map location, floor plan, and equipment photos.
a) The Contractor shall demo the existing three (3) ton rooftop packaged unit that serves the second level sleeping and entertainment area; demo the existing two (2) ton rooftop packaged unit that serves the second level hall and laundry room; demo the existing three (3) ton heat pump system for the first level watch room and Master Chief’s office. The Contractor shall remove the outdoor unit, refrigerant lines, electrical connections, condensate pan, condensate lines, platform, threaded rod, channel strut and all other components associated. The Contractor shall repair all holes on the outside of the building to include all penetrations. The Contractor shall remove and reinstall the drop ceiling on the inside of any applicable areas. The Contractor is responsible for disposal of existing HVAC split equipment and all other accumulated trash OFFSITE.
b) The Contractor shall provide a new 208/230 volt, three (3) ton, three (3) phase rooftop packaged heat pump unit that serves the second level sleeping and entertainment area; unit will be ten (10) KW auxiliary heater;
rooftop curb adapter; digital heat pump thermostat. The Contractor shall provide a new 208/230 volt, two (2) ton, single phase rooftop packaged heat pump unit that serves the second level hall and laundry room unit will be five (5) KW auxiliary heater; rooftop curb adapter; digital heat pump thermostat. The Contractor shall provide a new 208/230 volt, three (3) ton, three (3) phase heat pump unit that serves the first level watch room and Master Chief’s office; unit will be ten (10) KW auxiliary heater; rooftop curb adapter; digital heat pump thermostat.
c) The Contractor shall crane off existing heat pumps from the roof and new units will be installed in the existing locations where applicable. A curb adapter will be placed on the existing roof curbs to adapt the old curbs to the new packaged heat pumps. The existing service disconnects shall be replaced with new fuses installed.
d) The Contractor shall be responsible for verifying the existing electrical voltage, phase, and power available including electric heat for the new HVAC equipment. The Contractor is responsible to coordinate electrical work and tie into existing electrical circuits. The Contractor is responsible to test and ensure existing electrical circuits are satisfactory for new installation. The Contractor shall be responsible for electrical service requirements to the new HVAC equipment including all electrical devices, metal conduit, copper conductors, non-fused electrical disconnect switches, electrical circuit breakers and any other necessary items to install the new equipment. The Contractor shall provide a licensed electrician to install any necessary electrical power for the HVAC equipment.
e) The Contractor shall re-use the existing ducting to the maximum extent possible. The Contractor shall modify existing duct as required for the new HVAC packaged unit to transition to the existing ductwork.
f) The Contractor shall ensure the ducting to the space is properly balanced, so the air flow is adequate. The Contractor shall remove existing, provide new, and install all duct work, supply registers, and return grilles for the equipment to be properly balanced.
g) The Contractor shall provide a detailed drawing to scale of the new HVAC equipment, including duct design layout, size, cfm to each register, duct lengths, etc. See reference drawing for approximate room dimensions.
Contractor shall field verify all dimensions of existing ductwork and room square footage prior to making calculations or ordering materials.
h) The Contractor shall provide and install a new programmable thermostat and wiring necessary for the new packaged HVAC equipment. The Contractor is responsible for the new programmable thermostat operating with the existing control. The Contractor shall use liquid tight conduit for any control wiring outside the building.
i) The Contractor shall install this equipment IAW North Carolina building code, mechanical code, and plumbing code. All work must comply with manufacturers’ installation instructions and recommendations. The Contractor shall have a mechanical license to perform the subject work as required.
j) All work must be completed in accordance with NFPA 70 (National Electrical Code).
k) All work must meet requirements of ASHRAE 62.1 and ASHRAE 90.1 standards.
l) All exterior duct work shall be insulated and covered with galvanized sheet metal. Penetrations through the exterior walls shall be properly flashed/sealed.
m) Where applicable, all supply registers and return grilles must be aluminum with a factory applies white paint finish. The Contractor shall provide/replace all supply registers and return grilles including any extra necessary to properly balance the equipment.
n) Where applicable, all supply registers must be high velocity type with insulated backing.
o) The Contractor shall be responsible for making any building wall or roof openings and ensure they are properly sealed.
p) The Contractor shall provide and attach a UV rated adhesive decal on the new equipment. The adhesive decal shall state the model and serial number, service start date and warranty end date of the installation and equipment warranty dates.
q) The Contractor shall provide operational testing and start-up to verify proper operation of the newly installed packaged unit. The Contractor shall provide a one-time basic training to on-site Station personnel of the newly installed packaged unit. The training shall include operation sequence and maintenance.
a. The Contractor is responsible for performing all testing and commissioning of the new HVAC equipment.
b. Commissioning:
i. The Contractor must verify operation of the new HVAC equipment. The Contractor must verify supply/return airflows, supply/return temperatures, and proper operation of all modes. The Contractor must provide a TAB report for the new equipment.
ii. The Contractor must ensure there are no leaks in the equipment.
iii. The Contractor must charge the equipment with the proper type and quantity of refrigerant per manufacturer’s instructions
r) It is HIGHLY recommended that the Contractor make a site visit to properly evaluate the location of the equipment and verify all aspects and/or specifications to the existing equipment.
s) Scheduling: The Contractor shall provide a detailed schedule within fifteen (15) calendar days after contract award. The Contractor shall schedule all work with the Contracting Officers Representative (COR).
12. Certifications and Refrigerant Handling:
a. Contractor personnel working on HVAC units must possess current CFC/HCFC/HFC certifications/licenses as required under EPA regulation 40 CFR Part 82, Subpart F, Section 608 of the CAA. Certifications/licenses must be made available to the COR and Base Environmental Compliance Office upon request.
b. All refrigerants must be properly recovered and recycled in accordance with EPA regulations. Documentation of proper recovery and disposal must be submitted to the COR and Base Environmental Compliance Office
13. Inspection and Acceptance:
a. The Contractor shall ensure testing and start-up to verify proper operation.
The COR will accomplish inspection and acceptance of work.
b. The Contractor must notify the COR two working days before the performance, inspection and acceptance tests are to be conducted. The tests must be performed in the presence of the COR.
c. Installation, workmanship, fabrication, assembly, erection, examination, inspection, and testing shall be in accordance with appropriate sections of
29 CFR 1910, 1926.
d. The Contractor shall perform all work in accordance with all Federal, EPA, OSHA, and State of North Carolina laws and regulations.
e. New equipment must be installed in accordance with manufacturer instructions, Federal, and State codes.
f. Installation, operation, maintenance manuals and warranty information for the equipment shall be turned over to the COR upon project completion. The Contractor shall provide a one-year warranty on the equipment supplied by the Contractor (including labor) from the startup date of the equipment for any problems that might occur with the new installation.
14. Reference Documents:
a) Map Location, Floor Plan, & Equipment Photos – Maintenance Building