This is a Statement of Work (SOW) for periodic maintenance services on a SSMD-2mm Solid-State Disintegrator located at Minot Air Force Base, North Dakota. The 5th Communications Squadron, Asset Management Office requires the contractor to perform preventative maintenance inspection and repair on the equipment, which has been in use for over a year. The vendor must contact the Government's Point of Contact at least 5 days prior to arrival to verify access availability. A lead technician must arrive on-site within 72 hours of COR approval and complete troubleshooting and necessary repairs within 6 hours, with parts costs not to exceed $100 per service call. If repairs cannot be completed within the 6-hour timeframe or exceed the $100 parts threshold, the contractor must submit a Service Order to the Contracting Officer and Contracting Officer's Representative for evaluation and approval, with cost estimates and schedules required within 48 hours of the service call.

The work will be performed at Bomber Boulevard, Minot AFB, North Dakota 58705. Contractor personnel must obtain base identification and vehicle passes through the Security Forces office and must present valid REAL ID or equivalent documentation. The contractor is responsible for disposing of any old parts or waste materials and must supply standard commercial warranty. The Points of Contact are Mr. Rob Schutt and SrA Kailer Lasagna at 701-723-4545. This SOW is associated with a Notice of Intent to Single Source contract (Solicitation Number FA4528-26-N-KM03) to Data Security, Inc., which includes annual preventative maintenance and out-of-cycle repairs for multiple pieces of equipment under a firm-fixed-price structure with a base year and four option years. Responses to the single-source notice were due by June 25, 2026, at 8:00 AM CDT.

View the file

Other files

File Type Posted
BECO Equipment Mx Sole Source Justification.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CUI

STATEMENT OF WORK

SSMD-2mm Disintegrator Periodic Maintenance 5th Communications Squadron, Asset Management Office Minot AFB ND 58705 25 March 2026

1Overview and Objective2
2Background2
3Scope of Work2
4Requirement2
5Warranty2
6Special Requirements2
7Delivery or Place of Performance2
8 Point of Contact2

Overview and Objective Minot AFB is home to two major Air Force units: the 5th Bomb Wing and the 91st Missile Wing. Minot AFB is located approximately 13 miles north of Minot, North Dakota and approximately 120 miles north of the North Dakota state capital, Bismark. Minot is known for pleasant, warm to moderately hot summers and bitterly cold winters. At times, the area can have extreme winds, with wind speeds exceeding forty miles per hour occurring regularly. Minot AFB is in the central time zone. For more information visit https://www.minot.af.mil/, https://minotnd.gov/, and https://visitminot.org/. Web links provided within this work statement are for informational purposes, and the Contractor must not consider them contractual guidance.

5th Communications Squadron needs periodic maintenance performed on SSMD-2mm disintegrator. The Squadron has supplies on hand to be used for the periodic maintenance.

Background Equipment has been in use for over a year and a maintenance check of the system is needed.

Scope of Work Vendor must complete periodic maintenance inspection and repair for any need issues identified with the equipment. The Vendor must contact the Government’s Point of Contact at least 5 days prior arrival to verify availability to access the equipment. Vendor must dispose of any old parts or waste materials.

Requirement Vendor must complete required periodic maintenance action on SSMD-2mm disintegrator per recommended technical specifications.

Warranty The Contractor must supply the standard commercial warranty.

Special Requirements

6.1 Base access requirements: Contractor Access to Department of the Air Force Installations The contractor shall obtain base identification, and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Department of the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation. The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid REAL ID, current vehicle registration, valid vehicle insurance certificate to obtain a vehicle pass. ▪ Contractor personnel who do not possess a REAL ID must present a valid U.S. passport with the State’s ID. Personnel who do not possess a valid U.S. passport must present: (1) original or certified copy of their birth certificate, (2) their original social security card, and (3) marriage certificate or divorce decree as applicable.

7 Routine

7.1 The Lead Technician will be on site within 72hrs starting from approval by the COR. Within 6 hrs from arrival, the technician will complete troubleshooting and make the needed repairs, NTE $100 for parts per call. If the system cannot be returned to operational status within 6hrs and under the $100 parts call threshold included in the Service Call, the Contractor shall provide the COR with a plan to repair before the Contractor leaves the site. The estimate and schedule for the proposed Service Order are required within 48 hours of the Service Call unless otherwise negotiated by the CO.

8. Service Order Once the Technician arrives on-site and determines the extent of the repair required, the Contractor shall notify the CO/COR of the scope and cost of the repairs. If the repairs cannot be made within the time 6 hours or cost NTE $100 for parts per the PWS the Contractor shall submit a SO for CO and COR evaluation and approval. The official repair SO document shall include the relevant facts and proposed costs for the situation.

9. Delivery or Place of Performance

9.1 Bomber Blvd, Minot AFB, ND 58705

10. Point of Contact Primary: Mr. Rob Schutt, 701-723-4545 and Alternate: SrA Kailer Lasagna, 701-723-4545