This statement of work outlines tower strengthening and repair requirements for the Sierra Vieja communications tower located in Fort Davis, Texas. The scope of work includes reinforcing existing tower diagonals with additional cross members, installing lightning protection, conducting safety and structural inspections, and performing general maintenance and repairs. Contractors must submit security clearance documentation, a project schedule, and design plans certified by a professional engineer. Deliverables include a project completion report with as-built drawings and photographs. The period of performance is six months from contract award. Responses to this market survey will inform an upcoming solicitation for similar tower work at locations in Corrizo Springs, Laredo, and Fort Davis, Texas. Interested vendors must provide capability statements and past performance details by August 13, 2020 to the Federal Aviation Administration.

View the file

Other files

File Type Posted
SOW Laredo-Wormser Tower Strengthening 1.0.doc DOC document
SOW Artesia Wells Tower Strengthening 1.0.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

For

Sierra Vieja Tower Strengthening

1.0 Scope of Work

The purpose of this statement of work includes the strengthening of the Tactical Communications (TACCOM) 80.0’ guyed tower in Fort Davis, TX (Sierra Vieja) (Latitude 30.579821, Longitude -104.706604). The tower is in need of reinforcement of the existing diagonals. Existing diagonals from 0’ to 74’ need additional cross members installed using 5/8” and 7/8” solid round bar for each diagonal on each face. Bar sizes will have to be matched from Tower Repair Report or field verified. The reinforcement is intended to create an X Brace rather than the Z or K Brace currently on the tower. The tower from 74’ to 80’ will need a scab on brace made of bisected pipe for each X Brace. The scab on will result in a solid round bar and pipe composite section with an equivalent diameter of 1 1/8”. All material is to be made of A36 Steel and welded into place using 70 KSI electrodes. All bisected pipe scabs will need to be welded along cuts and plug welds on 36” centers to secure pipe halves into place. The tower reinforcement plan described above must be verified by submitting a reinforcement work plan that provides costs for the GFI tower reinforcement work plan and any contractor/installer proposed reinforcement work plan. All contractor/installer tower reinforcement work plans must effectively reduce the cost or schedule to be considered for approval. Tower reinforcement work plan to be signed, sealed and dated by a registered professional engineer in the state the tower is erected. Tower reinforcement work plan may require a site visit by contractor or installer. It is preferred the tower reinforcement plan be produced by the installer so that the anticipated work will maximize available capability of installation team.

In addition to the reinforcement the tower and site must also be repaired, the repairs include replacement of safety wire restraints with corrosion, spot treatment for corrosion control throughout tower height, tighten/replace mount hardware, reseal feed-line jumper connections to 8 foot grid dish, install new turnbuckle safety cables with 2 Crosby Clamps through the thimbles at all anchors, install locking nut devices on guy wire connections at all locations, install lightning rod and ground lead, install concrete step below shelter doors that provides no more than eight inches in drop between steps, install safety climb device, re-tension guy wires, vegetation control to clear over growth around shelter and anchors, install (4) corner and (2) line posts to delineate limits of propane tank and installation of (4) corner post to delineate guy wire anchor locations for each guy wire anchor . The tower repair does not include replacement or repair of antennas noted in General Repair Report nor fence installation. All repair locations and additional information can be found in General Repair Report.

The contractor will provide labor, travel, permits/application fees, mobilization costs and tools for technicians to travel to Fort Davis, TX to repair and restore the Sierra Vieja tower as described in this SOW. A site condition assessment may be required to gather information to complete an assessment for the tower and adjacent facilities located in Fort Davis, TX. During the site condition assessment, a site survey, and data collection may be required to facilitate production of the tower strengthening and infrastructure repairs as outlined in this SOW. Site survey will be used for the purpose of developing any additions or deletions to this scope associated with the strengthening of the tower system and infrastructure of the existing owned or leased Customs and Border Protection (CBP) properties for the Sierra Vieja site.

1.1 Objectives

This SOW shall achieve the following specific objectives:

· Tower structural repair and strengthening shall be designed to meet structural design in accordance with IBC 2010; ASCE-2007; NEC, NFPA, ANSI/ASTM and TIA-222-H as a Class III structure. Structure shall be designed to accommodate the proposed loading and be structurally modeled for a target of 75% capacity in controlling element using a commercially acceptable modeling program (e.g., TnX, or RISA). Loading calculations shall include all climb systems, proposed communications equipment, and lightning rod protection.

· Other infrastructure repairs may include damaged shelters, power systems, ice bridges, perimeter fencing, etc.

1.2 References

All applicable documents referenced in this SOW are listed below.

1) Government furnished documents.

2) Applicable Federal, State, and Local Requirements.

3) Applicable Standard Industry Quality and Safety Requirements

2.0 Requirements

Contractor will:

· Must submit and clear a law enforcement clearance through the local CBP sector office for all personnel including sub-contractor personnel

· Provide all necessary labor (or sub-contract labor) of appropriate skill to accomplish all tasks with this SOW

· Submit Project Completion Report as Described in Section 3.0

· Travel as necessary to accomplish all tasks in the SOW.

· Provide specialized services to accomplish all tasks specified in the SOW.

· Provide procurement services as required for materials and equipment.

· Complete all tasks as required in Section 3.0

· Provide deliverables as required in Section 3.1

· Schedule and coordinate as required by Section 4.0

· Provide progress/compliance as required in section 4.0

· Provide construction site access to government construction monitors for the purpose of monitoring progress and quality. The contractor will retain the right to limit access to the immediate construction area during high safety risk activities. The contractor will provide an observation area for monitors during high safety risk activities.

3.0 Tasks

The tasks to be performed under this SOW are described below in several categories. Where conflicts arise between documents this document shall supersede.

1) Phase I: Security Clearance

a) All contractor personnel shall submit personal information to the Government for the purposes of submitting to security clearance check. Security clearance check will be performed by DHS-CBP. All personal and private information (PPI) will be submitted on Attachment A and submitted directly to DHS-CBP. Point of contact for receipt of PPI will be provided upon submission of project schedule after award. Security clearance must be completed 3 weeks prior to construction start date or any requested site visit.

2) Phase II: Construction Planning

a) Contractor will provide complete project schedule that denotes start dates, end dates and duration of all major construction activities. Projects schedule may include as many lines and work activities as necessary for the contractor to control and manage the project. However the following items must be included in the project schedule. Security Clearance, Prework Meeting, Mobilization, Tower Repairs, Tower Modifications, Final Inspection and Demobilization.

b) Schedule shall be reasonable and denote working hours for each activity or project in general to coordinate any required helicopter operations and allow sufficient mobilization and demobilization times.

3) Phase II: Construction/Installation

a) Contractor will repair the tower as noted in the Tower General Repair Report.

b) Contractor will reinforce the tower as noted in the Tower Structural Repair Report and Foundation Repair Report (as applicable).

c) Contractor will be present and attend final inspection and acceptance performed by government.

4) Phase III: Project Close Out

a) Contractor will submit project close out report and photographs of all completed work. Contractor will author a summary document of the effort provided during the completion of the work. The document will provide a list of work completed, list of materials used for each installation, pre installation pictures of major components, post installation pictures of major components, field observations made (if additional work was identified) and redlines of government furnished information to produce construction as-built documentation.

3.1 End Results/Deliverables

The deliverables to be completed and submitted under this SOW is the tower strengthening as outlined in this SOW and a project close out package that reflects the milestones of this agreement that are agreed upon by all parties at the site survey visit. Basic requirements may include, but not limited to, the tasks listed in Section 3.2, and other applicable documents for the completed site made up of red line drawings, tests and material data sheets/information, etc. for the project.

3.2 List of Deliverables by Task

The deliverables to be completed and submitted for each task under this SOW are described below. Acceptance of the work will be based on conformance with construction drawings and other government furnished information.

1) Security

a) Complete and Submit Site Access Form reference Appendix A. (Due to the location of this project this requirement will likely be waived.)

b) Complete and Submit Project Schedule reference Schedule Section for major components to be captured.

2) Tower Repair

a) Mobilize for construction.

b) Reinforce diagonals as noted in 1.0.

c) Replace safety wire restraints.

d) Apply corrosion control along entire height of tower.

e) Replace, check and tighten hardware as noted in 1.0.

f) Install lightning rod and ground lead.

g) Install concrete step below shelter doors as noted in 1.0.

h) Install safety climb device

i) Retension guy wires.

j) Restore surrounding area to previous state.

k) Clear the work area.

l) Conduct a Final Inspection and Acceptance with FAA and/or CBP.

m) Complete punch list items identified in the Final Inspection.

n) Conduct punch list verification walk through with FAA and/or CBP if requested.

o) Demobilize from construction efforts

3) Project Completion

a) Complete and Submit Project Completion report as described in Section 3.

4.0 Schedules/Milestones

Project scheduling and milestones for the site will be submitted within 7 days of award and include no less than the following milestones:

· Security clearance

· Pre-work meeting

· Mobilization

· Site work

· Final Inspection & Acceptance

· Punch list item completion

· Demobilization

· Close-out report submission

5.0 Other Considerations

All personnel shall be required to submit and clear a law enforcement clearance through the centralized CBP office by completing and submitting the form in Attachment A.

Coordination with CBP technical personnel will be required and will be done through communication through the FAA project leadership.

A note should be included in the final report regarding the decommissioning of any old assets.

“As-built” drawings based upon the redlines will be part of the closeout so a note shall be included in the final report annotating this requirement to be completed 30 days after receipt of the redline drawings.

6.0 Progress/Compliance

The following will be coordinated with FAA-AML-4000 in order to monitor progress and ensure compliance (identify action):

· Security clearance paperwork

· Preconstruction Meeting, if required.

· Final Inspection and Acceptance

· Submission of documents in Sections 3.1 & 4.0

· Government construction monitors may be on site to verify progress and compliance.

7.0 Period of performance

After contract is awarded, the awarded contractor should be prepared to submit the site access found in “Attachment A” within 5 calendar days and to attend site visit within 30 days after award, if needed. Design completion should be completed within 90 days after site visit or award, whichever is applicable. A kickoff meeting will be scheduled within 7 calendar days prior to the site visit. Site visit hours may be constricted due to allowable working hours for Government Escort. Working hours are typically Monday through Friday 8 am to 5 pm unless otherwise approved. All weekend work must be approved with agency of Government Escort. Completion of the project should occur within 6 months of award of contract.

8.0 Place of performance

The place of performance is Fort Davis, TX (Sierra Vieja) (Latitude 30.5798, Longitude -104.7066) Appendix A: Site Access Form

U. S. Customs and Border Protection

Headquarters

Contract Worker Pre-Clearance Request

_1626858819.doc U. S. Customs and Border Protection

Headquarters

Contract Worker Pre-Clearance Request

Date:

MEMORANDUM FOR:

Office of Internal Affairs

Security Management Division

FROM (CBP federal employee):

Name

Office

Room, Phone Number

SUBJECT: Contract Worker Pre-Clearance Request

Floor and room location where visit will take place

Floor

Room #

Name of visitor escort (must be DHS/CBP employee)

Name

Telephone number of visitor escort

Office

Mobile

Date(s) and Time of visit

From Date

Time

To Date

Time

Contractor Name & Home Address

U.S.

(Last name, first name, middle name)

DOB

POB

Citizen

(List in alphabetical order by last name)

SSN

(MM-DD-YYYY) (City, State) (Y / N)

Contractor Name

U.S.

(Last name, first name, middle name)

DOB

POB

Citizen

(List in alphabetical order by last name)

SSN

(MM-DD-YYYY) (City, State) (Y / N)

SUBMISSION:

The Office of Internal Affairs requires a mandatory submission of 72 hours prior to arrival of visitor(s) in order for any visitor to be considered for approval. Email request to SMDSECURITYSERVICESBRANCH@dhs.gov or fax to Internal Affairs, ATTN: Security Management Division at 202-344-1075.

NOTICE:

All visitors must present a U.S. Government issued Photo Identification Card.

All visitors must check in at the 14TH Street Security Desk upon arrival and check out at the desk upon departure. Visitor escorts are responsible for constant escort of headquarters visitors. The designated escort must accompany visitors at all times, to include returning visitors back to the front desk upon departure. Any visitors found in U.S. Customs and Border Protection space without an escort will be immediately reported to security.

PRIVACY ACT NOTICE: This information is provided to PL 93-579 (Privacy Act of 1974). The purpose of this document is provide information necessary for a minimum security check prior to limited authorized access to U.S. Customs and Border Protection facility. Failure to provide this information may result in denial of access.