SOW Laredo-Wormser Tower Strengthening 1.0.doc
DOC document 144 KB Posted
- Solicitation number
- 6973GH-20-4580
About this file
This statement of work outlines tower strengthening and repair requirements for three locations in Texas. The Federal Aviation Administration seeks to reinforce structures in Corrizo Springs, Laredo, and Fort Davis through replacement of double angles and bolts from 19' to 152' on towers. Interested vendors must submit capability statements by August 13th detailing experience on similar projects, business size, and past performance to be considered for either an unrestricted competition or small business set-aside. Responses to the related market survey will inform the acquisition strategy and source list for required tower repair and modification services.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW Artesia Wells Tower Strengthening 1.0.doc | DOC document | |
| SOW Sierra Vieja Tower Strengthening 1.0.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
For
Laredo-Wormser Tower Strengthening
1.0 Scope of Work
The purpose of this statement of work includes the strengthening of the Tactical Communications (TACCOM) 250’ self-support tower in Laredo, TX (Laredo-Wormser) (Latitude 24.457772, Longitude -114.827463). The work will be solicited with a bid option to determine the most cost effective reinforcement option for the structure. The base bid will be based on the following work: Existing double angles 2L2.5”x2.5”x0.25” need to be replaced with 2L3”x3”x0.25” double angles from 19’ to 38’. Also existing double angles 2L2”x2”x0.25” need to be replaced with 2L2.5”x2.5”x0.25” double angles from 95’ to 114’. All double angles at diagonal and horizontal locations must be bolted at 36” centers along its length using 5/8” diameter bolts with associated hardware and spacer blocks. Spacing block thickness is unknown and will need to be field verified. All tower material is to be A36 steel. In addition to the tower reinforcement the tower must also be repaired, the repairs include install (4) corner and (2) line posts to delineate limits of generator and propane tank, foundation repairs at each tower leg, weather seal top of anchor bolts at Leg B, install lightning rod and ground lead, replace missing anchor rod nut locking devices all Legs, check and torque as necessary anchor rod nuts all Legs, install safety climb device, replace all corroded guy hardware at all heights specifically kellum grip attachments, check and tighten all mount hardware for entire tower height,, perform corrosion control for full tower height, replace missing or improperly installed locking devices at 19’ and 152’ and replace bent or missing step bolts for entire tower height. The tower repair does not include replacement or repair of antennas noted and does not include fence installation in General Repair Report. All repair locations and additional information can be found in General Repair Report.
The bid option will be based on the following work: All 5/8” bolts from 38’ to 76’ must be replaced with ¾” diameter bolts which will require drilling or punching new oversized holes at each location. All bolts must be A325N with the required associated hardware.
For the base bid and bid option the contractor will provide labor, travel, permits/application fees, mobilization costs and tools for technicians to travel to Laredo, TX to repair and restore the Laredo-Wormser tower as described in this SOW. A site condition assessment may be required to gather information to complete an assessment for the tower and adjacent facilities located in Laredo, TX. During the site condition assessment, a site survey, and data collection may be required to facilitate production of the tower strengthening and infrastructure repairs as outlined in this SOW. Site survey will be used for the purpose of developing any additions or deletions to this scope associated with the strengthening of the tower system and infrastructure of the existing owned or leased Customs and Border Protection (CBP) properties for the Laredo-Wormser site.
1.1 Objectives
This SOW shall achieve the following specific objectives:
· Tower structural repair and strengthening shall be designed to meet structural design in accordance with IBC 2010; ASCE-2007; NEC, NFPA, ANSI/ASTM and TIA-222-H as a Class III structure. Structure shall be designed to accommodate the proposed loading and be structurally modeled for a target of 75% capacity in controlling element using a commercially acceptable modeling program (e.g., TnX, or RISA). Loading calculations shall include all climb systems, proposed communications equipment, and lightning rod protection.
· Other infrastructure repairs may include damaged shelters, power systems, ice bridges, perimeter fencing, etc.
1.2 References
All applicable documents referenced in this SOW are listed below.
1) Government furnished documents.
2) Applicable Federal, State, and Local Requirements.
3) Applicable Standard Industry Quality and Safety Requirements
2.0 Requirements
Contractor will:
· Must submit and clear a law enforcement clearance through the local CBP sector office for all personnel including sub-contractor personnel
· Provide all necessary labor (or sub-contract labor) of appropriate skill to accomplish all tasks with this SOW
· Submit Project Completion Report as Described in Section 3.0
· Travel as necessary to accomplish all tasks in the SOW.
· Provide specialized services to accomplish all tasks specified in the SOW.
· Provide procurement services as required for materials and equipment.
· Complete all tasks as required in Section 3.0
· Provide deliverables as required in Section 3.1
· Schedule and coordinate as required by Section 4.0
· Provide progress/compliance as required in section 4.0
· Provide construction site access to government construction monitors for the purpose of monitoring progress and quality. The contractor will retain the right to limit access to the immediate construction area during high safety risk activities. The contractor will provide an observation area for monitors during high safety risk activities.
3.0 Tasks
The tasks to be performed under this SOW are described below in several categories. Where conflicts arise between documents this document shall supersede.
1) Phase I: Security Clearance
a) All contractor personnel shall submit personal information to the Government for the purposes of submitting to security clearance check. Security clearance check will be performed by DHS-CBP. All personal and private information (PPI) will be submitted on Attachment A and submitted directly to DHS-CBP. Point of contact for receipt of PPI will be provided upon submission of project schedule after award. Security clearance must be completed 3 weeks prior to construction start date or any requested site visit.
2) Phase II: Construction Planning
a) Contractor will provide complete project schedule that denotes start dates, end dates and duration of all major construction activities. Projects schedule may include as many lines and work activities as necessary for the contractor to control and manage the project. However the following items must be included in the project schedule. Security Clearance, Prework Meeting, Mobilization, Tower Repairs, Tower Modifications, Final Inspection and Demobilization.
b) Schedule shall be reasonable and denote working hours for each activity or project in general to coordinate any required helicopter operations and allow sufficient mobilization and demobilization times.
3) Phase II: Construction/Installation
a) Contractor will repair the tower as noted in the Tower General Repair Report.
b) Contractor will reinforce the tower as noted in the Tower Structural Repair Report and Foundation Repair Report (as applicable).
c) Contractor will be present and attend final inspection and acceptance performed by government.
4) Phase III: Project Close Out
a) Contractor will submit project close out report and photographs of all completed work. Contractor will author a summary document of the effort provided during the completion of the work. The document will provide a list of work completed, list of materials used for each installation, pre installation pictures of major components, post installation pictures of major components, field observations made (if additional work was identified) and redlines of government furnished information to produce construction as-built documentation
3.1 End Results/Deliverables
The deliverables to be completed and submitted under this SOW is the tower strengthening as outlined in this SOW and a project close out package that reflects the milestones of this agreement that are agreed upon by all parties at the site survey visit. Basic requirements may include, but not limited to, the tasks listed in Section 3.2, and other applicable documents for the completed site made up of red line drawings, tests and material data sheets/information, etc. for the project.
3.2 List of Deliverables by Task
The deliverables to be completed and submitted for each task under this SOW are described below. Acceptance of the work will be based on conformance with construction drawings and other government furnished information.
1) Security
a) Complete and Submit Site Access Form reference Appendix A. (Due to the location of this project this requirement will likely be waived.)
b) Complete and Submit Project Schedule reference Schedule Section for major components to be captured.
2) Tower Repair
a) Mobilize for construction.
b) Install double angles as noted in 1.0.
c) Replace bolts as noted in 1.0.
d) Make repairs to tower and foundation as noted in 1.0.
e) Install lightning rod and ground lead.
f) Replace, check and torque hardware as noted in 1.0.
g) Apply corrosion control on full height of the tower.
h) Replace bent or missing step bolts.
i) Restore surrounding area to previous state.
j) Clear the work area.
k) Conduct a Final Inspection and Acceptance with FAA and/or CBP.
l) Complete punch list items identified in the Final Inspection.
m) Conduct punch list verification walk through with FAA and/or CBP if requested.
n) Demobilize from construction efforts
3) Project Completion
a) Complete and Submit Project Completion report as described in Section 3.
4.0 Schedules/Milestones
Project scheduling and milestones for the site will be submitted within 7 days of award and include no less than the following milestones:
· Security clearance
· Pre-work meeting
· Mobilization
· Site work
· Final Inspection & Acceptance
· Punch list item completion
· Demobilization
· Close-out report submission
5.0 Other Considerations
All personnel shall be required to submit and clear a law enforcement clearance through the centralized CBP office by completing and submitting the form in Attachment A.
Coordination with CBP technical personnel will be required and will be done through communication through the FAA project leadership.
A note should be included in the final report regarding the decommissioning of any old assets.
“As-built” drawings based upon the redlines will be part of the closeout so a note shall be included in the final report annotating this requirement to be completed 30 days after receipt of the redline drawings.
6.0 Progress/Compliance
The following will be coordinated with FAA-AML-4000 in order to monitor progress and ensure compliance (identify action):
· Security clearance paperwork
· Preconstruction Meeting, if required.
· Final Inspection and Acceptance
· Submission of documents in Sections 3.1 & 4.0
· Government construction monitors may be on site to verify progress and compliance.
7.0 Period of performance
After contract is awarded, the awarded contractor should be prepared to submit the site access found in “Attachment A” within 5 calendar days and to attend site visit within 30 days after award, if needed. Design completion should be completed within 90 days after site visit or award, whichever is applicable. A kickoff meeting will be scheduled within 7 calendar days prior to the site visit. Site visit hours may be constricted due to allowable working hours for Government Escort. Working hours are typically Monday through Friday 8 am to 5 pm unless otherwise approved. All weekend work must be approved with agency of Government Escort. Completion of the project should occur within 6 months of award of contract.
8.0 Place of performance
The place of performance is Laredo, TX (Laredo-Wormser) (Latitude 27.4578, Longitude -99.4201) Appendix A: Site Access Form
U. S. Customs and Border Protection
Headquarters
Contract Worker Pre-Clearance Request
_1626858819.doc U. S. Customs and Border Protection
Headquarters
Contract Worker Pre-Clearance Request
Date:
MEMORANDUM FOR:
Office of Internal Affairs
Security Management Division
FROM (CBP federal employee):
Name
Office
Room, Phone Number
SUBJECT: Contract Worker Pre-Clearance Request
Floor and room location where visit will take place
Floor
Room #
Name of visitor escort (must be DHS/CBP employee)
Name
Telephone number of visitor escort
Office
Mobile
Date(s) and Time of visit
From Date
Time
To Date
Time
Contractor Name & Home Address
U.S.
(Last name, first name, middle name)
DOB
POB
Citizen
(List in alphabetical order by last name)
SSN
(MM-DD-YYYY) (City, State) (Y / N)
Contractor Name
U.S.
(Last name, first name, middle name)
DOB
POB
Citizen
(List in alphabetical order by last name)
SSN
(MM-DD-YYYY) (City, State) (Y / N)
SUBMISSION:
The Office of Internal Affairs requires a mandatory submission of 72 hours prior to arrival of visitor(s) in order for any visitor to be considered for approval. Email request to SMDSECURITYSERVICESBRANCH@dhs.gov or fax to Internal Affairs, ATTN: Security Management Division at 202-344-1075.
NOTICE:
All visitors must present a U.S. Government issued Photo Identification Card.
All visitors must check in at the 14TH Street Security Desk upon arrival and check out at the desk upon departure. Visitor escorts are responsible for constant escort of headquarters visitors. The designated escort must accompany visitors at all times, to include returning visitors back to the front desk upon departure. Any visitors found in U.S. Customs and Border Protection space without an escort will be immediately reported to security.
PRIVACY ACT NOTICE: This information is provided to PL 93-579 (Privacy Act of 1974). The purpose of this document is provide information necessary for a minimum security check prior to limited authorized access to U.S. Customs and Border Protection facility. Failure to provide this information may result in denial of access.
Revised 8/9/2019