SOW - SF Vault Toilets.pdf
PDF 162 KB Posted
- Solicitation number
- 127EAX25R0022
- Issued by
-
Department of Agriculture Forest Service
About this file
This Statement of Work (SOW) details vault toilet replacement projects for three campgrounds in the Santa Fe National Forest's Pecos/Las Vegas Ranger District, located north of Pecos, New Mexico. The project involves demolition and replacement of existing toilet facilities across three sites: Field Tract Campground (removing a 288 sq. ft. concrete block flush toilet building and installing one double-vault pre-cast concrete toilet with a gravel pathway), Link's Tract Campground (demolishing a single-vault toilet and installing a double-vault pre-cast concrete toilet with gravel pathways), and Jack's Creek Campground (demolishing four composting toilets and two double-vault toilet buildings, and installing six double-vault pre-cast concrete toilets with concrete sidewalks).
The contract has a 180-day performance period, with estimated work timeframe from May 1, 2025, to October 31, 2025. The specific campground locations are precisely identified by GPS coordinates: Field Tract Campground (35.6871, -105.6937), Links Tract Campground (35.7569, -105.6624), and Jack's Creek Campground (35.8391, -105.6560). Referenced attachments include specifications, drawings, and additional documents such as the 1996 Jacks Creek Contract Package Drawings, Field Tract Restroom Photo & Floor Plan, and Links Tract Toilet Photo.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| GAOA - Santa Fe Vault Toiltet Replacement PLVRD.pdf | ||
| SOI - SF Vault Toilets.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Santa Fe Vault Toilet
Replacements 2023
FY23 TASK ORDER INFORMATION
Dated October 24, 2023
BRIEF DESCRIPTION OF PROJECT:
This project consists of the following:
Field Tract Campground: The work consists of demolition of one 288 sq. ft. concrete block flush toilet building (including the concrete foundation) and installation of one double-vault pre-cast concrete toilet. It also includes installing a gravel pathway from the road to the toilet.
Link’s Tract Campground: The work consists of demolition of one single-vault toilet building and installation of one double-vault pre-cast concrete toilet. It also includes gravel pathways around the new toilet.
Jack’s Creek Campground: The work consists of demolition of four composting toilets and two double-vault toilet buildings and installation of six double-vault pre-cast concrete toilets. The work also includes construction of concrete sidewalks leading to and around the toilets.
Location:
The site locations are on the Pecos/Las Vegas Ranger District of the Santa Fe National Forest and include three separate campgrounds. All the campgrounds are north of Pecos, New Mexico off
NM-63. The campgrounds are listed below:
1. Field Tract Campground: 35.6871, -105.6937
2. Links Tract Campground: 35.7569, -105.6624
3. Jack’s Creek Campground: 35.8391, -105.6560
Period of Performance:
Contract time begins on the effective date of the Notice to Proceed (NTP) and runs 180 days.
Estimated time of work is May 1, 2025, to October 31, 2025.
References:
• Specifications
• Drawings
• Referenced Attachments o Ref 1 - 1996 Jacks Creek Contract Package Drawings o Ref 2 - Field Tract Restroom Photo & Floor Plan o Ref 3 - Links Tract Toilet Photo