SOW revised 050720.pdf
PDF 223 KB Posted
- Attached to
- FIber Optic Lines Repair for Range 24
- Solicitation number
- W911S720Q0011
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Fiber repair for 200 and 300 meter targets at Range 24
1.0 INSTALLATION SCOPE
1.1 General: Install 6 strand single mode armored fiber from BD-7 (Emerson control box) to 200 meter and 300 meter targets. At Range 24.
2.0 REQUIREMENTS
1.2 2.1 General: Locate and repair existing collapsed buried conduit between BD-7
(Emerson control box) to 200 meter and 300 meter targets.
a. Locate and repair the existing collapsed buried conduit between the BD-7 and 200 meter target NEMA closure
b. Locate and repair the existing collapsed buried conduit between the BD-7 and 300 meter Target NEMA closure
2.1.1 Tasks: Install 6 strand single mode armored fiber optic cable from BD-7 (Emerson control box) to 200 meter and 300 meter targets.
a. Install 6 strand single mode armored fiber optic cable from BD-7 (Emerson control box) to 200 meter target
b. Install 6 strand single mode armored fiber optic cable from BD-7 (Emerson control box) to 300 meter target
c. Re-terminate new fiber in the 200 meter NEMA box using SC/UPC style connectors. Clean connectors and plug into existing SC bulkhead adapter plate.
d. Re-terminate new fiber in the 300 meter NEMA box using SC/UPC style connectors. Clean connectors and plug into existing SC bulkhead adapter plate.
e. Re-splice 200 and 300 meter fiber in BD-7 Coyote closure.
2.1.2 Tasks: Test 6 strand single mode armored fiber optic cable from BD-7 (Emerson control box) to Tower.
a. Test fiber link from Tower patch panel to the 200 meter BD-7 (Emerson control box bulkhead using OPM-LS and OTDR
b. Test fiber link from Tower patch panel to the 300 meter BD-7 (Emerson control box bulkhead using OPM-LS and OTDR
c. Reconnect all patch cords and have Range maintenance perform 200 and 300 meter target acquisition test to confirm target is operating properly.
d. It is a mandatory requirement to obtain a dig permit prior to starting work.
3.0 DELIVERABLES
3.1 Work Completion Date. A job site walk through is required to be performed with Range control personnel before any work is to start. Period of Performance is 30 days after “Notice to Proceed” is issued.
3.2 Status Reports. The Contractor shall keep the Government Personal apprised of any issues at the worksites
File details come from the government source that posted it. Updated .