SOW Repair JACC Chilled Water Piping -New 03-20-2025.pdf
PDF 1 MB Posted
- Solicitation number
- 36C25625R0003
About this file
This Statement of Work (SOW) details repair work for the chilled water piping system at the VA Gulf Coast Veterans Health Care System's Joint Ambulatory Care Center (JACC) in Pensacola, FL, addressing damage from a Memorial Day 2023 flood. The project is divided into two phases: Phase 1 includes outside penthouse grooved pipe fastener replacement and penthouse waterproofing, while Phase 2 involves miscellaneous damaged insulation repair and penthouse grooved piping replacement.
Key requirements include mandatory subcontractors (Siemens for controls, Kurita for chemical treatment, Master Insulation for insulation work, and Southern Commercial Installations for furniture services), specific technical specifications for piping replacement, waterproofing, and insulation, and strict work schedules. The project mandates 100% of work be performed outside normal duty hours, requires new 304L stainless steel piping with specific installation methods, and includes detailed requirements for weld inspection, hot work permits, and infection control. The total project timeline is 275 calendar days, with a 90-day pre-construction period for submittal preparation and site survey.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25625R0003 0003.docx | DOCX document | |
| 36C25625R0003 0002.docx | DOCX document | |
| 520-25-107 Site Visit Sign in Sheet.pdf | ||
| 36C25625R0003 0001.docx | DOCX document | |
| 36C25625R0003 EXHIBIT C.docx | DOCX document | |
| 36C25625R0003 EXHIBIT A.docx | DOCX document | |
| P07 Wage Determination FL20250203 03-14-2025.pdf | ||
| 36C25625R0003-Drawings Repair JACC chilled water piping .pdf | ||
| 36C25625R0003 Brand Name JA-Redacted.pdf | ||
| 36C25625R0003 EXHIBIT D.docx | DOCX document | |
| 36C25625R0003-520-25-107 -Specifications -01-22-2025 .pdf | ||
| 36C25625R0003.docx | DOCX document | |
| 36C25625R0003-Contracting Only ICRAs and PCRAs Repair JACC Chilled Water Piping .pdf | ||
| 36C25625R0003 EXHIBIT B.docx | DOCX document | |
| Site Visit Instructions - 520-25-107-Repair JACC Chilled Water Piping v2.pdf | ||
| 36C25625R0003 EXHIBIT E.docx | DOCX document | |
| 36C25625R0003 EXHIBIT F.docx | DOCX document |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Repair JACC Chilled Water Piping
VA Gulf Coast Veterans Health Care System (GCVHCS) JACC Pensacola, FL 32507
520-25-107
Table of Contents
1. Sole Source Subcontract Requirements
2. Phasing
3. Phase 1: Penthouse Waterproofing
4. Phase 1: Outside Penthouse Grooved Pipe Fastener Replacement
5. Phase 2: Misc. Damaged Insulation
6. Phase 2: Penthouse Grooved Piping Replacement
7. Interior Finishes
8. Equipment
9. Fire Protection During Construction
10. Infection Control
11. Installation Time
12. Special Bid Considerations by the Contractor
13. Safety Considerations
14. Notes
Revision Date:
3/20/2025
Scope of work
The awarded Contractor shall furnish all labor, tools, materials, equipment, subcontractors, and supervision necessary to safely perform all work associated with repairing the damage from the Memorial Day 2023 flood and executing preventative measures to prevent reoccurrence in the future. This work shall be performed at the VA Joint Ambulatory Care Center (JACC) in Pensacola, FL.
1. Mandatory Subcontract Requirements:
a. Siemens- See brand name J&A
1. The existing controls system was built and is maintained under contract with Siemens. Therefore, all controls design, installation, and programming shall be through Siemens.
b. Kurita- Mandatory subcontractor
1. Kurita America operates the existing chemical program for the GCVHCS at the JACC. Kurita must be subcontracted to treat the chilled loop after all new piping has been flushed and cleaned.
c. Master Insulation- Mandatory Subcontractor
1. Master Insulation assisted in root cause failure analysis for the 2023
JACC flood event. Due to their understanding of the physical root causes of these catastrophic failures, all insulation materials and services are to be completed by Master Insulation.
d. Southern Commercial Installations (SCI)- Mandatory subcontractor
1. Southern Commercial Installations (SCI) maintains the existing service contract for all GCVHCS furniture services and as such, must be subcontracted to perform these office breakdowns to maintain the manufacturer’s (Haworth) warranty. This also prevents contractual conflict with SCI’s ongoing contract with the GCVHCS. This includes but is not limited to after-hours moves.
2. Phasing
a. This project shall be completed in phases to ensure least amount of disruption to veterans and staff and to ensure life safety requirements remain within required limits throughout the entire construction process.
b. Two phases are required for the work:
1. Phase 1 to include:
1. Outside Penthouse Grooved Pipe Fastener Replacement
2. Penthouse Waterproofing
2. Phase 2 to include:
1. Misc. Damaged Insulation
2. Penthouse Grooved Piping Replacement
3. Phase 1: Penthouse Waterproofing
a. Angle Flashing
1. Angle flashing must be fabricated from 24-gauge galvanized sheet metal and installed around the perimeter walls of the 3rd floor mechanical penthouse. This flashing must also be installed around curb penetrations in the mezzanine floor.
2. Flashing must be a minimum of 6” in height.
3. The new metal flashing must be anchored to the existing wall studs and concrete floor deck.
4. Angle flashing and existing concrete floor must be scarified to properly prepare the surfaces for the application of new waterproofing.
5. All Soprema products listed below are basis-of-design products and not required as a sole source.
6. All surfaces to receive the new waterproofing to be cleaned with
Soprema Alsan RS and primed with Soprema Alsan 276, or equal in lieu of, per the manufacturer's instructions.
7. All vertical joints in the new angle flashing to be sealed with Soprema Alsan RS 230 Flash And Soprema Alsan RS Fleece, or equal in lieu of, as per the manufacturer's instructions.
8. The flange of the new metal flashing must be sealed to the concrete floor surface with Soprema Alsan RS 230 Field and Soprema Alsan RS Fleece or equal in lieu of as per the manufacturer's instructions.
9. Coordinate with COR to ensure standoff distance is adequate in front of existing electrical equipment.
b. Miscellaneous Floor Penetrations
1. Penetrations unable to be angle flashed due to access constraints must be coated with Soprema Alsan or approved equal water proofing solution to prevent water migration down ductwork or other existing floor penetration. Application for waterproofing penetrations must following manufacturer’s instructions.
2. This includes but is not limited to air handler ductwork, piping penetrations, or beam penetrations.
a. Equipment Lift Floor Hatch and Doorways
i. Waterproofed angle flashing with structural backing should be used on the sides of the lift hatch where handrails are present.
ii. Provide and install basis-of-design Garadam or approved equal 2" High Flood Barrier Threshold Kits across host travel path. See Figure 1 below.
Figure 1: Equipment Lift Floor Hatch
iii. Edges of threshold seal must be neatly tied or overlapped with water proofed angle flashing to create a water tight fit at the connections.
iv. Provide and install watertight door seals on 3 penthouse doors currently without door seals.
b. Floor drains
3. Scanning for locations
1. Use 3D LiDAR data and high-resolution panoramic imagery to generate an AutoCAD Civil 3D Map of the 3rd Floor Mechanical Penthouse existing.
2. AutoCAD Civil 3D Map will provide pertinent features located along the floor, surfaces, low-spots, and slope arrows to aid in the determination of drain locations.
3. The AutoCAD Civil 3D file shall contain pertinent features of the 3rd Floor Mechanical Penthouse including, but not limited to walls, columns, equipment edges, raised equipment platforms, etc located along the floor level only.
4. Core drilled drains
Water proofed angle flashing
1. A Ground Penetrating Radar (GPR) scan must be completed at each of the desired six (6) new drain locations prior to core drilling being scheduled.
2. Furnish and install a minimum of six (6) new 3” floor drains in 3rd Floor Mechanical Penthouse. Tie into existing sanitary drains.
3. Final locations to be coordinated with COR in accordance with GPR and Civil 3D Map above.
4. Phase 1: Outside Penthouse Grooved Pipe Fastener Replacement
a. Chilled Water outside Penthouse
1. All work in this section applies to all chilled water pipe network outside the penthouse. This includes but is not limited to mechanical connections in the central energy plant, 1st and 2nd floor plenums, and any chases where grooved piping connections exist.
b. Insulation and Fastener Replacement
1. General
1. Chilled water must be isolated and drained before any fasteners are removed.
2. Existing insulation on chilled water must remain in place until immediately before fasteners are replaced to prevent sweating on ceiling materials below.
3. Provide and install fasteners for direct replacement of existing hardware.
I. Existing chilled water connections are II. Stainless steel oval neck track bolts meeting ASTM
F593, Group 2 (316 stainless steel) condition CW.
III. Stainless steel heavy nuts meeting ASTM F594, Group
2 (316 stainless steel) condition CW with galling reducing coating.
4. New hardware to be replaced according to existing grooved piping system (Victaulic) I-100 Field Installation Handbook and Appendix A:
I. This includes the required use of anti-seize compound on all stainless-steel hardware.
II. The coupling shall be disassembled and inspected to verify that the gasket is not pinched. If the gasket is pinched, a new coupling assembly shall be used.
5. All means of access to Victaulic joints are the responsibility of the contractor. All access must be in accordance with VA and OSHA safety policies.
6. Contractor is responsible for replacing any material removed or damaged gaining access to Victaulic joints including but not limited to ceiling tiles, insulation, gypsum ceiling systems, ceiling track, light fixtures, HVAC diffusers, HVAC grilled, wireless access points (APs), etc.
7. Contractor is responsible for performing a planning site survey on the chilled water loop and provide a phased fastener replacement plan for VA approval and shutdown scheduling.
2. New Insulation
1. Materials utilized must be minimum 1” closed-cell elastomeric foam and basis-of-design FOAMGLAS®, cellular closed-cell glass, or equal.
2. Minimum 1” closed-cell elastomeric foam with black finish is requested for all grooved couplings receiving replacement bolts above ceilings.
3. Minimum 1” closed-cell elastomeric foam with painted white finish is requested for all grooved couplings receiving replacement bolts in the mechanical plant.
4. Minimum 1” basis-of-design FOAMGLAS® or equal cellular glass is requested for straight piping insulation damaged or needing repair following bolt changes both above ceilings and in the mechanical plant.
c. Working above office space
1. VA is responsible for removing IT devices, staff personal belongings, health data, and biomedical equipment. Moves must be coordinated with VA COR in advance of any planned work in affected areas. Contractor to submit moves request form to the COR for review and approval 2 weeks prior to mobilizing for work in each affected area. The form includes proposed dates and areas to be considered by GCVHCS moves team.
2. Upon VA removal of all previously listed items, contractor is responsible for removing and storing systems furniture required to access overhead couplings having fasteners changed.
3. Southern Commercial Installations (SCI) maintains the existing service contract for all GCVHCS furniture services and as such, must be subcontracted to perform these office breakdowns to maintain the manufacturer’s (Haworth) warranty. This also prevents contractual conflict with SCI’s ongoing contract with the GCVHCS. This includes but is not limited to after-hours moves.
4. Contractor must provide offsite, climate-controlled storage to temporarily store furniture during the duration of overhead work.
5. Anything unable to be removed from the office space must be plastic wrapped and tightly tape sealed by the contractor to prevent dust buildup and potential water damage during work.
d. Chilled loop treatment
1. Inspect and empty all chilled water strainers while loop is evacuated.
2. Kurita America operates the existing chemical program for the Gulf Coast Veterans Health Care System at the JACC. Kurita must be subcontracted to treat the chilled loop after all new piping has been flushed and cleaned.
3. Retreatment of the full chilled loop requires approx. 10 gallons of Kurita America’s Protect-1201P closed loop corrosion inhibitor. Contractor is responsible to purchase any necessary treatment chemicals for the completion of this work.
e. Work Schedule
1. 100% of work is to be performed outside normal duty hours (0700 to
1630) Monday through Friday, exclusive of Federal holidays.
5. Phase 2: Misc. Damaged Insulation
a. Master Insulation
1. Master Insulation assisted in root cause failure analysis for the 2023 JACC flood event. Due to their understanding of the physical root causes of these catastrophic failures, all insulation materials and services are to be completed by Master Insulation.
b. Pulmonary (2A135)
1. Disassemble ceiling grid and associated fixtures for safe access to underside of roof decking.
2. Utilize basis-of-design HANDIFOAM® E84 (HFO) or approved equal to apply 5” insulative layer to underside of roof decking. Spray area is approximately 225 SF.
3. Reinstall ceiling grid and associated fixtures.
c. Loading dock HVAC duct
1. The location of this duct work is directly above the only active loading dock entrance at the JACC. Care must be taken when erecting scaffolding and overhead pedestrian protection must be provided if the scaffold is to remain in place during any normal duty hours (0700 to 1630) Monday through Friday. Detailed plan of scaffolding must be submitted to the COR for review and approval 2 weeks prior to erection.
2. Remove approximately 150 SF of dura rock on the loading dock ceiling for access to insulate duct.
3. Insulate 18x18” exhaust duct (approx. 30 LF) using foil faced blanket insulation.
4. Replace cement board removed for exhaust duct access.
5. Provide and install 2’x2’ ceiling access door.
6. Finish dura rock to match existing color and texture.
d. Loading dock repair
1. Replace approximately 16 SF of water damaged dura rock around storm water drain pipe penetration
2. Finish to match existing
e. Work Schedule
1. All work is to take place after normal duty hours (0700 to 1630) Monday through Friday, exclusive of Federal holidays.
6. Phase 2: Penthouse Grooved Piping Replacement
a. Chilled Water inside Penthouse
1. All work in this section applies to all chilled water pipe network inside the 3rd floor penthouse.
b. New Piping
1. Prior to start work, field survey existing site condition and features.
Verify at project site the exact size and clearance of all existing piping being connected to or removed to allow new piping.
2. Install new 304L stainless steel chilled water supply and return piping using screwed, welded, and flanged pipe according to VA spec 23 21 13 Hydronic Piping. Fitting determined by pipe size. No grooved pipe is allowed on chilled water service.
1. 2 inches and smaller: Screwed or welded joints
2. 2-1/2 inches and larger: Welded or flanged joints
3. Per JACC as-built structural drawing SS 103.7- Piping 8" and greater in diameter shall be supported by steel beams and joists. Piping shall not be supported from metal roof deck. Piping may be supported from the rib (thickest) portion of composite deck and concrete. Piping supported by joists shall be within 6" of joist panel points. Piping 8" diameter and greater and running parallel to joists/ beams shall be supported by at least two (2) joists/ beams. Pipes 8" diameter and greater supported by joists shall have support points at 5 feet o.c. max.
In each direction."
4. Weld Inspection
1. Contractor to provide independent, third party radiographic non-destructive testing (NDT) for a minimum of 10% of new welds at random.
2. Minimum ASNT Level-II qualified person must establish radiographic procedure to be approved by COR.
3. Contractor shall be responsible for carrying out Radiography;
rectification of defects and re-radiography of welds repaired/rectified at their cost.
4. Where random radiography is specified, the first weld of each welder shall be completely radiographed. In the case of pipe of radiographed.
5. For each weld performed by a welder found unacceptable, two additional checks shall be carried out on welds performed by the same welder. This operation is iterative and the two additional welds for each weld deemed unsatisfactory shall be continued till such time that two consecutive welds of satisfactory quality are found for every defective weld.
5. Existing piping shall remain in service throughout fabrication of new piping.
1. Phase and schedule cutovers of chilled water from existing piping to new piping and submit to COR for approval.
2. Scheduling of cutovers shall be done in a way to prevent all disruptions of HVAC service during normal business hours Monday-Friday 7am-4:30pm excluding federal holidays.
6. Existing soldered or brazed piping and insulation to remain.
7. All dissimilar metal connections shall be made using dielectric fittings.
Any existing dielectric fittings with grooved connections shall be replaced.
8. All hydronic piping elements with grooved joints must be replaced with fittings for steel pipe according to VA Spec 23 21 13 Hydronic Piping.
Grooved pipe and fittings are strictly prohibited.
9. Piping elements include but are not limited to electronic hydronic control elements and instrumentation, circuit setters, balance valves, strainers, air separators, test ports, gauge ports, etc.
1. The existing controls system was built and is maintained under contract with Siemens. Therefore, all control devices, design, installation, and programming shall be through Siemens.
2. All controls installed or replaced shall be native BACnet.
c. Hot Work
1. Contractor is responsible to obtain a daily hot work permit whenever performing hot work. Draft hot work permits should be reviewed with safety as well as an engineering employee from projects or Maintenance and Operations (M/O).
2. The contractor is responsible for safely planning and fabricating a hot work area exhaust system that prevents smoke and smoke smells from making their way into the HVAC system and lower, occupied floors.
3. Prior to beginning hot work while the JACC is occupied, contractor will be required to perform after-hours functional test of exhaust system.
4. Contractor will be permitted to utilize existing JACC general exhaust provided systems are returned to their initial condition following construction.
5. A hot work plan must be proposed by the contractor for approval by VA COR before any hot work begins. Adjustments to this plan have the potential to be required as conditions and work locations change within the penthouse.
6. VA Maintenance and Operations (M&O) will be responsible for safely placing the Simplex fire panel monitoring system in bypass while hot work is taking place and for communicating with Navy Corry Station Fire Dept., the responding fire emergency service house for the JACC.
d. Demolition Work
1. Contractor is responsible for the removal and disposal of all grooved piping and grooved piping elements.
2. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source.
e. Hydronic balance
1. Conduct hydronic balance per specification section 23-05-93 Testing, Adjusting, and Balancing (TAB) for HVAC
2. Scope of hydronic TAB is inclusive of all reheat and chilled loop networks at the JACC site, both those being replaced and those undisturbed.
f. Closed loop treatment
1. Inspect and empty all chilled water strainers while loop is evacuated.
2. Kurita America operates the existing chemical program for the Gulf
Coast Veterans Health Care System at the JACC. Kurita must be subcontracted to treat the reheat and chilled loops after all new piping has been flushed and cleaned.
3. Retreatment of the full chilled loop requires approx. 10 gallons of Kurita America’s Protect-1201P closed loop corrosion inhibitor with blue dye.
4. Retreatment of the full reheat loop requires approx. 10 gallons of Kurita America’s Protect-1201P closed loop corrosion inhibitor with red dye.
5. Contractor is responsible to purchase any necessary treatment chemicals for the completion of this work.
g. Work Schedule
1. 80% of work is to be performed during normal duty hours (0700 to
1630) Monday through Friday, exclusive of Federal holidays.
2. The remaining 20% of work must be done outside normal duty hours to prevent impacts from patient care due to HVAC cutover outages, overhead lifts, hot work area preparation and testing etc. Any work performed outside of normal working hours shall be coordinated with the COR.
3. If the contractor is unable to safely exhaust hot work smoke and fumes, all hot work will be required to be completed outside normal duty hours.
7. Interior Finishes
a. Replace all ceiling system disturbed by construction/demolition process.
b. Repair any damaged flooring from the construction/demolition process.
c. Repair walls/doors/trim of any damage in the construction/demolition process.
8. Equipment
a. Any equipment or rigging shall be provided by the contractor or equipment vendor. No equipment will be provided by VHA.
1. Equipment includes but is not limited to ladders, manlifts, scaffolding, forklifts, rental chillers, temporary cooling units, etc.
b. Contractor is responsible to provide all scaffolding or rental equipment necessary to complete work at height.
c. Scaffolding locations expected for above the ceiling Victaulic bolt changes is shown in drawings.
d. Contractor is responsible to mobilize and safely deliver their equipment to the work area outside of normal working hours 0700 to 1630.
e. Equipment staging locations to be approved by COR.
9. Fire Protection During Construction
a. Coordinate with the project Contracting Officer Representative (COR) prior to and throughout the construction period.
b. Coordinate with the project Contracting Officer Representative (COR) prior to and throughout the construction period.
c. Fire protection during construction shall comply with VA Master Construction Specification (VAMCS) 01 00 00, General Requirements. (Note: VAMCS 01 00 00, General Requirements, addresses NFPA 241, Joint Commission Interim Life Safety Measures, Hot Work Permits. This specification section was formerly section 01010.)
d. Separate all occupied areas from demolition, renovation, or construction activities by temporary smoke-tight construction partitions of gypsum board or other approved non-combustible or limited-combustible material. Partitions shall be full height, extending through suspended/hard ceilings to the floor slab or roof deck above and shall be one-hour fire rated, unless sprinklers are installed and are operational on both sides of the temporary partition whereupon the partition may be permitted to terminate at the ceiling in accordance with NFPA
241. Where the ceiling on one side of the temporary construction barrier has been removed, the temporary wall would need to go to the deck above. This requirement is due to the inherently greater potential for fire or hazardous materials incidents associated with the combustibles and operations of demolition/construction. This risk is made worse by the likelihood of compromised fire protection systems and fire/smoke resistant construction. This does not obviate the need to provide other protective measures to contain dust and debris as specified by VAMCS 01 00 00 section 1.8(D)(2). Sprinklers are considered to be operational when they are installed in accordance with NFPA 13 (spacing, protection, distance from the ceiling, etc.) and there is a sufficient automatic water supply. If the ceiling was removed and the sprinklers remain at the original ceiling level, they would likely not be considered operational.
e. Provide dust proof one-hour / fire-rated drywall construction barriers to separate construction from the operational areas of the clinic in order to contain dirt debris and dust. Barriers shall be sealed and made presentable on clinic occupied side.
Install a self-closing rated door in a metal frame, commensurate with the partition, to allow worker access. Always maintain negative air. A fire-retardant polystyrene, 6-mil thick or greater plastic barrier meeting local fire codes may be used where dust control is the only hazard, and an agreement is reached with the COR and Safety Office.
f. Phase construction as necessary to ensure that obstruction of exits is minimized or avoided. If exits are obstructed during construction, provide alternate exit routes during each phase of construction, and identify the alternate routes on the construction drawings.
g. Minimize or avoid disruptions to fire alarm and sprinkler systems. Delineate phasing of construction to ensure that installations of new systems are expedited, and where possible, maintain existing systems in service until the replacement system is operational. If fire protection systems are to be disrupted, ensure procedures are incorporated to maintain equivalent levels of fire protection and provide 5 calendar days formal written notification to COR and Safety Office before fire alarm systems are taken out of service.
10. Infection Control
a. See pre-construction infection control risk assessment (PCRA) and “contracting only” infection control risk assessment (ICRA) attached to this solicitation for contract requirements.
b. Contractor is responsible to implement all requirements of VAMC’s Infection Control Risk Assessment (ICRA) permit and request any clarifications to ICRA requirements during the solicitation phase.
c. During construction, VA Engineering and Infection Control will monitor conditions in and around work areas and will require the Contractor take corrective action immediately for any exceptions to ICRA requirements.
11. Installation Time
a. The construction portion of this project will consist of two separate periods, each of which must be preceded by a NTP issued by contracting.
1. Pre-construction period – 90 Days – Contractor to provide the following deliverables before the end of this period:
I. Submittal log of all submittals to be approved during the project.
II. Site survey of pre-existing conditions.
III. All submittals are to be approved by VA COR
2. Construction period – All contractually required work and tests must be successfully completed within 275 calendar days of issuance of Notice to Proceed for construction.
12. Special Bid Considerations by the Contractor It is the responsibility of the Contractor and all involved sub-contractors to visit the site and field verify all existing conditions necessary to be addressed for the pricing of this subject project. All disposal costs and fees for debris removal will be the contractor’s responsibility. The contractor will be responsible for cleanliness of the building area exterior and providing their own dumpster on site.
13. Safety Considerations Contractor’s shall provide and utilize all safety requirements in accordance with OSHA regulations in the performance of the work.
14. Notes
a. The Contractor shall submit ALL samples, including manufacture’s literature, of newly proposed materials for approval. No materials shall be procured or installed prior to the approval of the samples.
b. Site shall always be kept clean and free from debris, and the contractor shall remove debris daily from the health care system property. Contractor will not be allowed to use Government tools, materials, and/or labor for this project.
c. All work is to be performed in strict compliance with the attached specifications and “Scope of Work”.
Appendix A: Maximum Torque Values for Stainless Steel and Non-Ferrous Fasteners
Torque Values for S1ainless S1eel and Non-Ferrol!ls Fasteners Bo'lt Size
18-B Stainless Steel J.16 Stainless Steel SIDcon Bronze
IMOlilel Bra.ss 2024-li4 AluminumDrv Lubricated Drv Lubrl-cated
2-56 2.5 In-lbs 2.1 In-lbs 2.6 In-lbs 2.2 In-lbs 2.3 In-lbs 2.5 In-lbs 2.0 In-lbs 1.4 In-lbs 2-64 3 2.6 3.2 2.7 2.8 3.1 2.5 ·1.7 4-40 5..2 4.4 - 4.7 4.8 5.3 4.3 2.9 4-48 6..6 5.6 6.9 5.9 6.1 6.7 5.4 3.6 5-40 7.7 6.5 8.1 6.9 7.1 7.8 6.3 4.2 5-44 9..4 8.0 9.8 8.3 8.7 9.6 7.7 5.1 6-32 9..6 8.2 110.1 8.6 8.9 9.8 7.9 5.3 6-40 12.1 10.3 12.7 10.8 11.2 12.3 9.9 6.6 8-32 19.8 16.8 20.7 17.8 18.4 20.2 16.2 10.8 8-36 2:2 18.7 23 19.6 20.4 22.4 18.0 12.0
10-24 22.8 19.4 23.8 20.2 21.2 25.9 18.6 13.8 10-32 311.7 26.9 33.1 28.1 29.3 34.9 25.9 19.2 1(4-20 75.2 £3.9 78.8 67 68.8 85.3 61.5 45.6 1(4-28 94 80 99 84 87 106 77 57
5/16-18 132 112 138 117 123 149 107 80 5/16-24 142 121 147 125 131 16-0 116 86 3/8-16 236 201 247 210 219 266 192 143 3(8-24 259 220 271 230 240 294 212 157 7/16-14 376 320 393 .334 349 427 317 228 7/16-20 400 340 418 355 371 451 327 242 1/2-13 43 ft-lbs 37 fl-lbs 45 It-lbs 38 fl-lbs 40 ft-lbs 48.7 ti-lbs 35.2tl-lbs 26 fl-lbs 1f2-20 45 38 ,47 40 42 51 37 27
9/16-12 56 48 59 50 53 65 47 34 9116-18 62 53 65 55 :58 71 51 38 5/8-11 92 78 96 82 86 111 76 60 5(8-18 103 88 108 92 :96 123 85 67 .314-10 127 108 131 111 118 153 104 82 3(4-16 124 105 129 110 115 149 102 80 718-9' 194 165 202 172 178 2:.1 159 124
718-14 193 164 201 171 177 23,0 158 124 1 - 8 286 243 299 254 265 344 235 184 1 -14 259 220 270 230 240 311 212 166
1-118 - 7 413 351 432 367 383 4 9 337 265 1-1Al- 12 390 332 408 347 361 470 318 251 1-114 - 7 523 445 546 464 485 627 428 336 1 1/4 - 12 480 408 504 428 447 575 394 308 1-112- 6 888 755 930 791 822 1064 727 570
1-112- 12 703 598 732 • 622 651 840 575 450 Suggested Mruc1mum Torquing VaJues - a guide based upon actual lab testing on dry or near dry fasteners wiped clean. Whole Fastenal has used re-liable sources and testing to determine these values, there are many variables that will effect the results and theuse of this informationis an sole risk of the Liser.
Values ,hrough 7/16"'diameter are stated in inch-JPOUnds: 112"' diameter and over are stated in foot-pounds.
engineer@fastenal.com Rev 3-4--09 a
File details come from the government source that posted it. Updated .