This document is a Past and Present Performance Questionnaire for a federal contract opportunity related to VA construction work. The solicitation (36C25625R0003) is for a repair project involving JACC Chilled Water Piping, issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16, located in Biloxi, Mississippi. The questionnaire is designed to capture detailed performance evaluations from previous project references, with ratings across 23 performance categories ranging from unsatisfactory (1) to exceptional (5), including areas such as personnel management, quality control, problem-solving, scheduling, and overall contract performance. The form requires references to provide comprehensive feedback about a contractor's past performance, including whether they would award another contract to the contractor and if the contractor is rated in the Contractor Performance Assessment Reporting System (CPARS).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25625R0003 0003.docx | DOCX document | |
| 36C25625R0003 0002.docx | DOCX document | |
| 520-25-107 Site Visit Sign in Sheet.pdf | ||
| 36C25625R0003 0001.docx | DOCX document | |
| 36C25625R0003-Contracting Only ICRAs and PCRAs Repair JACC Chilled Water Piping .pdf | ||
| 36C25625R0003 EXHIBIT E.docx | DOCX document | |
| 36C25625R0003 EXHIBIT C.docx | DOCX document | |
| 36C25625R0003-520-25-107 -Specifications -01-22-2025 .pdf | ||
| P07 Wage Determination FL20250203 03-14-2025.pdf | ||
| Site Visit Instructions - 520-25-107-Repair JACC Chilled Water Piping v2.pdf | ||
| SOW Repair JACC Chilled Water Piping -New 03-20-2025.pdf | ||
| 36C25625R0003-Drawings Repair JACC chilled water piping .pdf | ||
| 36C25625R0003 Brand Name JA-Redacted.pdf | ||
| 36C25625R0003 EXHIBIT D.docx | DOCX document | |
| 36C25625R0003.docx | DOCX document | |
| 36C25625R0003 EXHIBIT F.docx | DOCX document | |
| 36C25625R0003 EXHIBIT A.docx | DOCX document |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOR OFFICIAL USE ONLY
Source Selection Sensitive Information—See FAR 2.101 & 3.104 520-25-107 CON Repair JACC Chilled Water Piping 36C25625R0003
EXHIBIT B
PAST AND PRESENT PERFORMANCE QUESTIONNAIRE
INSTRUCTIONS TO CONTRACTOR
Complete the CONTRACTOR INFORMATION section, below (type answers into light blue shaded boxes). Save the document. Send an electronic or hard copy print of the form to each of your reference contacts, asking them to please complete the form and submit it according to the instructions, below.
INSTRUCTIONS TO REFERENCE CONTACT
The contractor named below is submitting an offer for a United States Department of Veterans Affairs contract requirement, and has sent this form to you, in your role as a past performance reference contact. Please complete this form in full (all areas shaded in light yellow, below). Once completed, please send the form to the Contract Specialist via postal mail or email, directly to:
Department of Veterans Affairs NCO 16 Contracting Office 400 Veterans Ave. (BLDG 10 Engineering) Biloxi MS. 39530 Attention JB Herbst. Email Address: Jennings.Herbst@va.gov
Please return the completed form no later than the time set for receipt of proposals. If you have any questions, please contact JB Herbst via email. Thank you for your assistance in this matter.
GENERAL INFORMATION [completed by Contractor]
Contractor Company Name
Street Address
Contractor Point of Contact Name
City
Point of Contact Phone Number
State
Reference Project Title
Zip Code
Contract Period of Performance (start to finish):
Contract Number
Contract Dollar Value
Description of Work
Role of Contractor on This Project (check appropriate box) ☐ Prime Contractor ☐ Sub-contractor ☐ Key Personnel
RESPONDENT INFORMATION [completed by Reference Contact]
Company Name
Street Address
POC Name
City
Phone Number
State
Fax Number
Zip Code
PERFORMANCE INFORMATION: Choose the number on the scale of 1 to 6 that most accurately describes the contractor’s performance or situation. PLEASE PROVIDE A NARRATIVE EXPLANATION FOR ANY RATINGS OF 1 OR 2 in the Remarks section, below (text box will expand to whatever extent is necessary).
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| 6 |
| UNSATISFACTORY |
| MARGINAL |
| SATISFACTORY |
| VERY GOOD |
| EXCEPTIONAL |
| NEUTRAL |
| Performance did not meet most contractual requirements. There were serious problems and the contractor’s corrective actions were ineffective. |
| Performance did not meet some contractual requirements. There were problems, some of a serious nature, for which corrective action was only marginally effective. |
| Performance met contractual requirements. There were some minor problems and corrective actions taken by the contractor were satisfactory. |
| Performance met all contract requirements and exceeded some to the government’s benefit. There were a few minor problems, which the contractor resolved in a timely, effective manner. |
| Performance met all contract requirements and exceeded many to the government’s benefit. Problems, if any, were negligible and were resolved in a timely, highly effective manner. |
| No record of past performance or the record is inconclusive.[endnoteRef:1] [1: ] |
| The Contractor … |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| 6 |
| 1. |
| Provided experienced managers and supervisors with the technical and administrative abilities needed to meet contract requirements. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 2. | |||||
| Demonstrated ability to hire, maintain, and replace, if necessary, qualified personnel during the contract period. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 3. | |||||
| Delegated authority to project managers and supervisors commensurate with contract requirements. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 4. | |||||
| Home office participated in solving significant local problems. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 5. | |||||
| Followed approved quality control plan. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 6. | |||||
| Provided effective quality control and/or inspection procedures to meet contract requirements. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 7. | |||||
| Corrected deficiencies in timely manner and pursuant to their quality control procedures. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 8. | |||||
| Provided timely resolution of contract discrepancies |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 9. | |||||
| Identified problems as they occurred. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 10. | |||||
| Suggested alternative approaches to problems. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 11. | |||||
| Displayed initiative to solve problems. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 12. | |||||
| Developed realistic progress schedules. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 13. | |||||
| Met established project schedules. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 14. | |||||
| Provided timely resolution of warranty defects. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 15. | |||||
| Was responsive to contract changes. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 16. | |||||
| Provided adequate project supervision. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 17. | |||||
| Obtained consent of surety for increases in bonding as work-in-progress increased. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 18. | |||||
| Paid subcontractors/suppliers in a timely manner. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 19. | |||||
| Provided accurate and complete line item cost proposals including all aspects of work required for each task. |
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 20. | |||||
| Cooperated with Government personnel after award. | |||||
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 21. | |||||
| How would you rate the contractor's overall performance? | |||||
| ☐ | ☐ | ☐ | ☐ | ☐ | ☐ |
| 22. | |||||
| Was the contractor ever issued a cure or show cause notice under the referenced contract? If yes, explain outcome in “remarks.” | |||||
| ☐ | YES | ||||
| ☐ | NO |
| 23 | |
| Would you award another contract to this contractor? If not, please explain in “remarks.” | |
| ☐ | YES |
| ☐ | NO |
| 24 | |
| To the best of your knowledge, is the contractor rated in CPARS? | |
| ☐ | YES |
| ☐ | NO |
REMARKS (Please use as much space as is needed – the box will expand as you type).