SOW - Repair air compressor.docx
DOCX document 38 KB Posted
- Attached to
- Repair Power Lab Air Compressor
- Solicitation number
- 70Z03926QCGA00031
About this file
This is a Statement of Work (SOW) for the repair of an Ingersoll Rand Model R5.5i-A125 air compressor located at McAllister Hall, United States Coast Guard Academy, New London, Connecticut. The contractor shall provide all labor, materials, equipment, and transportation necessary to complete the repair work. Specific tasks include performing lockout/tagout procedures, replacing the failed cooling fan, inlet valve, stuck unload solenoid, and plugged blowdown valve, as well as changing the air filter, oil filter, and air/oil separator. Additional work includes removing an oil sample and changing the oil, checking the scavenge line, cleaning coolers with compressed air, replacing the drive belt, cleaning the panel filter, greasing the motor if applicable, and testing the unit to ensure proper operation before returning it to service.
The contractor and all personnel must be licensed by the State of Connecticut and shall designate a primary point of contact with phone and email information. All work must be performed between 7:30 a.m. and 4:00 p.m., Monday through Friday, excluding Federal Holidays, unless prior approval is obtained from the Technical Advisor, Jason Askew (Jason.M.Askew@uscg.mil). The contractor is responsible for scheduling all work with the Technical Advisor, maintaining the work site at a military installation with minimal interference to Coast Guard operations, and removing all debris and equipment daily. The government will provide electricity (120vac @ 20 amps) and water; however, the contractor is responsible for any additional utilities and removal upon completion. All removed materials become contractor property and must be disposed of offsite in accordance with applicable federal, state, and local regulations. Work is subject to inspection and acceptance by the Contracting Officer or Technical Advisor, with any unsatisfactory work corrected at no additional cost to the government.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AIR COMPRESSOR QandA.docx | DOCX document | |
| Combined Synopsis Solicitation_AIR COMPRESSOR.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work United States Coast Guard Academy New London, Connecticut Repair Power Lab Air Compressor
Part 1 – GENERAL
1.1 Project Description:
The contractor shall furnish all labor, material, equipment, and transportation, to repair the air compressor at McAllister Hall, Coast Guard Academy, New London, Connecticut.
1.2 Contractor Qualifications and Personnel Requirements:
The contractor and contractor personnel performing work under this contractor shall be licensed by the State of Connecticut. The contractor shall provide a primary point of contact to include a phone number and email address.
1.3 Technical Advisor:
All work performed by the contractor is subject to inspection and acceptance by the Contracting Officer or the Technical Advisor during and after the completion of each visit. Unsatisfactory work shall be corrected at no additional cost to the government. The Technical Advisor for site visits and technical support is Jason Askew who may be reached at Jason.M.Askew@uscg.mil. TA are not authorized to issue changes to the contractor or resolve contractual disputes.
1.4 Location of Work:
All work shall be performed at the Coast Guard Academy, 15 Mohegan Ave, New London, CT 06320.
1.5 Site Visit:
Bidders are encouraged to visit the site to become familiar with existing conditions. Failure to do so will not relieve the successful bidder from furnishing all labor, materials, and equipment to satisfactorily complete performance of all required work. Bidders shall contact the primary TA to schedule a site visit.
1.6 Hours of Work:
All work shall be performed between the hours of 7:30 a.m. and 4:00 p.m. local time, Monday through Friday excluding Federal Holidays. Should the contractor desire to work outside these hours, the contractor shall submit a request to the primary TA no less than 48 hours in advance.
1.7 Scheduling of Work:
The contractor shall schedule all work with the TA.
1.8 Contractor’s Use of Premises:
The contractor will be working within an operational Coast Guard military installation. The contractor shall perform and conduct all work to minimize interference with Coast Guard operations.
1.9 Parking:
The contractor is authorized parking during the performance of work. Overnight parking is not authorized. Parking arrangements shall be made through the TA.
1.10 Inspection and Acceptance of Work:
The contractor shall keep the TA fully informed of contract operations throughout the performance of work. The contractor shall notify the TA upon completion of work. The contractor and TA shall perform a joint final inspection and the contractor shall correct any noted deficiencies.
1.11 Government Furnished Utilities:
The government will furnish electricity (120vac @ 20 amps), and water from existing building services will be provided at no cost to the contractor. Additional hookups or temporary connections shall be the responsibility of the contractor and shall be removed by the contractor upon completion of work.
1.12 Storage Facilities:
The government will not provide storage facilities.
1.13 Site Clean Up:
Upon completion of daily work, the contractor shall remove and properly dispose of site debris and rubbish. Contractor equipment shall be removed from Coast Guard Academy premises unless otherwise authorized by the TA.
1.14 Disposal of Removed Materials:
All materials and equipment removed by the contractor shall become the property of the contractor and shall be disposed of offsite in accordance with all applicable federal, state and local laws and regulations. Under no circumstances shall materials be placed in government-owned or leased refuse containers.
1.15 Smoking:
The contractor shall strictly adhere to the Coast Guard Academy’s smoking policy which limits smoking to 4 designated locations. The TA will provide smoking area locations upon request.
Part 2 – SCOPE OF WORK
2.1 General:
The work associated with this contract includes repairing Ingersoll Rand Model R5.5i-A125 s/n: CBV681200
• Perform LOTO and remove all other energy sources one at a time
• Replace failed cooling fan
• Replace failed inlet valve, stuck unload solenoid, and plugged blowdown valve
• Change air filter, oil filter, and air/oil separator
• Remove oil sample and change oil
• Check scavenge line and clean coolers with compressed air
• Replace drive belt, clean panel filter, and grease motor if applicable
• Start unit, check operation and place each unit back into service with one in standby
File details come from the government source that posted it. Updated .