This is a Statement of Work (SOW) for janitorial services at the Occoquan Bay National Wildlife Refuge Multipurpose Building, located at 14050 Dawson Beach Road, Woodbridge, VA 22191.
The U.S. Fish and Wildlife Service requires performance-based janitorial services for the period October 1, 2026 through September 30, 2027, with four option years. Services will be provided Monday through Friday between 8:00 AM and 3:00 PM, excluding federal holidays. Weekly cleaning tasks include the multipurpose room/classroom and reception area (1,533 SF), restrooms (469 SF), administrative area with kitchen (2,145 SF), and storage areas (575 SF). Monthly tasks include cleaning the mezzanine/second floor (671 SF), kitchen appliances (microwave, oven, and refrigerator interiors), windows and windowsills, high-area dusting, and HVAC vent dusting. Annually, the contractor must professionally clean and shampoo carpets, strip and wax non-carpeted flooring per manufacturer specifications, perform deep cleaning of tile floors and grout in bathrooms and entrance halls, and wash all windows inside and out. The contractor is responsible for all janitorial equipment, supplies, materials, and labor while using green products whenever possible and providing Material Safety Data Sheets (MSDS) for all supplies used. All equipment must comply with OSHA standards and manufacturer directions. The contractor must pass a background check, maintain building security by locking doors and windows, report all accidents and safety incidents immediately to the Contracting Officer's Representative (COR) or Technical Coordinator, and submit a Quality Surveillance Plan (QSP) or performance measurement approach with the proposal.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140FS326Q0105.pdf | ||
| Sol_Clauses_Q4.pdf | ||
| B03_-_WD.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior
FWS OCCOQUAN BAY NWR
C/O POTOMAC RIVER NWR COMPLEX
12638 Darby Brook Court
WOODBRIDGE VA 22192
Statement of Work Occoquan Bay NWR Multipurpose Building
Janitorial Services
1. GENERAL:
The U.S. Fish and Wildlife Service (Service), Potomac River National Wildlife Refuge Complex at 14050 Dawson Beach Road Woodbridge, VA 22191 has a requirement for performance-based janitorial services from October 1, 2026 to September 30, 2027 with four option years. This is a government-owned facility located on Occoquan Bay National Wildlife Refuge. The Contractor will be responsible for planning, scheduling, coordinating and assuring performance and effective completion of all work under this contract. The areas to be cleaned are:
Weekly
• Multipurpose Room (Classroom) and Reception Area: 1533 SF
• Restrooms: 469 SF
Weekly
• Administrative Area including kitchen: 2145 SF
• Storage: 575 SF
Monthly
• Mezzanine (Second floor): 671 SF
• Kitchen Appliances (Microwave, Oven, and Refrigerator interiors)
See the attached floor plan
1.1 Conduct: At a minimum, the Contractor is required to take all steps and measures that would be taken by a prudent building owner to maximize the life expectancy of the building and property. This includes Contractors passing a background check to be able to access building.
1.2 Security of the Premises: The Contractor shall turn off all lights, and secure doors, and windows as appropriate for all areas pertinent to the Contractor’s access. The
Contractor shall immediately report to the COR or Technical Coordinator any instance (by specific location) of problems encountered while on-site. The
Contractor shall immediately notify personnel if buildings appear to be intruded or vandalized. Names and numbers of law enforcement officers shall be given to the
Contractor at the beginning of the contract.
1.3 Safety Measures: Contractor will put in place safety measures to reduce the risk of injuries in the performance of work. Additionally, the Service will provide any and all Job Hazard Analyses that may apply to the Contractor’s work.
1.4 Accident Reporting: The Contractor shall immediately report all accidents/injuries of person or property to the COR or Technical Coordinator and cooperate fully in any investigation as necessary.
2. SCOPE/DELIVERABLES:
2.1 Removal of trash and recycling in all bins to include in building should occur each time. Changing plastic liners if soiled and necessary. Trash and recyclables can be deposited in commercial bins adjacent to facility.
2.2 Cleaning and sanitation of bathrooms, sink areas, toilets, counters, mirrors, water fountains, and water faucets using suitable green non-abrasive cleaners and disinfectants will occur each time. All surfaces shall be free of grime, soap scum, mold, and smudges. The Contractor shall replace paper towels, toilet paper, sanitary napkin bags, and soap in all dispensers, as needed.
2.3 Cleaning and sanitation of multipurpose/classroom and kitchen sink areas, counters, tables, and chairs using suitable green non-abrasive cleaners and disinfectants will occur each time. All surfaces shall be free of grime, soap scum, mold, and smudges.
2.4 Cleaning all floors includes vacuuming carpeted areas and mopping solid surface floor areas. Floors should be maintained so that they are free from dust, dirt, mud, etc.
2.5 Wipe down mesh backing and arm rails on all chairs.
2.6 Dusting of all horizontal surfaces including furniture, and counter-tops will occur each time. If items are lying on these surfaces they are not to be moved.
2.7 As needed, cobwebs throughout the building.
2.8 Carpets and floors shall be professionally cleaned once a year. Carpets shampooed.
Strip and wax non carpeted flooring per manufacturer maintenance instructions.
Areas shall be free of all litter, lint, loose soil and debris. The Contractor shall move any chairs, trash receptacles, and easily moveable items to vacuum underneath, and then replace them in the original position. Time when this should occur will be determined and coordinated with Field Supervisor and Refuge Manager.
2.9 All office areas (office rooms, conference rooms, halls, office cubicle spaces, etc.)
will be included in cleaning, however, should an office be locked, that space will not be included in cleaning.
2.10 Windows and windowsills shall be cleaned once a month to remove smudges, streaks, or fingerprints.
2.11 Annually wash all windows inside and out.
2.12 Annually extra cleaning of tile floors and grout in all bathrooms, mud room, and entrance hall of administrative building.
2.13 Monthly complete dusting is high areas and dust HVAC vents.
3. PLACE/DELIVERY AND PERIOD OF PERFORMANCE:
3.1 The U.S. Fish and Wildlife Service, Potomac River National Wildlife Refuge
Complex at 14050 Dawson Beach Road Woodbridge, VA 22191
3.2 Contractor service will commence from Monday through Friday after 8:00AM.
3.3 Non-duty hours include Government holidays (New Year’s Day, Martin Luther
King, Jr. Day, Washington’s Birthday, Memorial Day, Juneteenth, Independence
Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, and Christmas
Day).
3.4 Emergency/Miscellaneous maintenance functions may be scheduled. Emergency work is required when immediate action to correct or prevent loss or damage of
Government property, or to eliminate hazards to personnel or equipment.
4. EVALUATION AND ACCEPTANCE/QUALITY SURVEILLANCE PLAN (QSP):
4.1 Contractor’s interested in submitting a proposal/quote are required to complete the
QSP or submit their own approach performance plan for each task. How will you measure your performance?
5. GOVERNMENT FURNISHED EQUIPMENT, SUPPLIES AND MATERIALS:
5.1 Government property shall be used only in direct operations of providing Contractor services and shall not be used in any manner for any personal advantage, business gain, or other personal endeavor by the Contractor.
5.2 Government will furnish all utilities, however, see below Section 7.
6. AVAILABILITY:
6.1 Cleaning will occur between 8 am and conclude by 3 pm. In the event of emergencies, the contractor shall provide contact information.
7. CONTRACTOR FURNISHED EQUIPMENT, SUPPLIES, & MATERIALS:
7.1 The Contractor shall furnish all equipment.
7.2 Equipment shall be used and maintained in accordance with the manufacturer’s directions and meet all applicable OSHA standards. The Contractor is responsible for using green products whenever possible. The contractor shall provide MSDS sheets for all supplies.
7.3 The contractor shall provide all management, tools, equipment, and labor necessary to ensure that janitorial services are performed at the USFWS Headquarters and
Maintenance buildings on an as-needed basis.
8. ONSITE REPRESENTATIVES and COORDINATORS:
8.1 Technical coordinators:
Enclosure: Floor Plan