This Statement of Work (SOW) details a comprehensive interior design and renovation project for the Naval Air Station Lemoore's Dining Facility located in Lemoore, CA. The project involves creating custom mixed-media murals, wall treatments, and integrated lighting across seven distinct areas, including wall coverings, window perforations, floating walls, and LED backlighting. Key requirements include using high-definition photographic integration, specialty 3M materials, custom wallpaper, hand-painted accents, and wood elements to enhance the facility's aesthetic.
The project must be completed within 90 days after contract award, with the first 30 days dedicated to design phase activities including drafting, editing, and final design approval. The contractor will be responsible for all aspects of design and installation, including consulting with the Food Service Officer, verifying dimensions, preparing work areas, managing installation during specified hours (primarily Monday-Friday, 0730-1530), and maintaining a clean work environment. The project scope encompasses detailed mural designs for various areas such as the NAS Lemoore History wall, check-in entrance, mess decks, overhead windows, and custom LED backlighting, with the Food Service Officer having final design approval authority.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment -QA Government Responses.xlsx | XLSX spreadsheet | |
| Exhibit-1.jpg | JPG image | |
| Exhibit-4.jpg | JPG image | |
| Exhibit-2.jpg | JPG image | |
| Exhibit-3.jpg | JPG image | |
| Attachment -QA Government Responses.xlsx | XLSX spreadsheet | |
| N00244-25-Q-S088 Combined Synopsis Galley Upgrades.pdf | ||
| TECHNICAL EXHIBITS LEMOORE.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Naval Air Station Lemoore, CA.
BLDG 10 K Street
Lemoore, CA. 92346
1. GENERAL: This requirement is to provide dining facility furniture, lighting fixtures, decorative signage, and modification of interior of facility to include window, doors, overheads, and walls identified at Naval Air Station Lemoore Galley.
2. SCOPE OF WORK: The contractor will provide materials, labor, supervision, installation and delivery of all items listed, unless noted otherwise in strict accordance with these specifications. The contractor will provide both custom design services as well as fabrication of custom mixed-media mural(s) with integrated lighting and floating walls.
3. Tasks: NAB Lemoore, Contractor will provide materials and modification in the facility to be identified by the customer as outlined below:
3.1 AREA 1 “Mural of NAS Lemoore History” (60’6” x 8’6")
3.1.1 Print: Custom Wallpaper Mural Design with high definition photographic integration. (SEE TECHNICAL EXHIBIT 1)
3.1.2 Finish: Specialty High-Tac 3M Material Matte Laminate) - Over Cinder Block Walls, trim to size.
3.1.3 QTY:1
3.2 AREA 2 Check-In Entrance Wall (11’x6’8)
3.2.1 Print: Custom Wallpaper Mural Design with high definition photographic integration. (SEE TECHNICAL EXHIBIT 2)
3.2.2 Finish: Over Wood Veneer Wall, Trim to Size
3.2.3 QTY: 1
3.3 AREA 3 Bays 1-4 (153’3” x8’2”)
3.3.1 Print: Custom Wallpaper Mural Design with high definition photographic integration. (SEE TECHNICAL EXHIBIT 3)
3.3.2 Finish: Specialty High-Tac 3M Material Matte Laminate) - Over Cinder Block
Walls.
3.3.2 QTY: 4
3.4 AREA 4 Khaki Mess (60’6” x8’2")
3.4.1 Print: Custom Wallpaper Mural Design with high definition photographic integration (SEE TECHNICAL EXHIBIT 4)
3.4.2 Finish: (Specialty High-Tac 3M Material Matte Laminate) - Over Cinder Block Walls, trim to size.
3.4.3 QTY: 2
3.5 AREA 5 Overhead Mess Decks (61’ x8’2)
3.5.1 Print: Custom Wallpaper Mural Design with high definition photographic integration (SEE TECHNICAL EXHIBIT 5)
3.5.2 Finish: Over Dry Wall, trim to size
3.5.3 QTY: 7
3.6 AREA 6 Over Head Windows 5’6” x30” and 3’11” x28” (16)
3.6.1 Custom Window Perforation Mural Design with high definition photographic integration. (SEE TECHNICAL EXHIBIT 6)
3.6.2 Finish: Over Glass Windows, trim to size
3.6.3 5’6” x30” QTY: 10
3.6.4 3’11” x28” QTY 16
3.7 AREA 7 Over Head Windows” (5’7”x36” Entrance Doors (4) and 6’x35” Exit Doors (5))
3.7.1 Custom window Perforation Mural Design with high definition photographic integration (SEE TECHNICAL EXHIBIT 7)
3.7.2 Over Glass Doors
3.7.3 QTY: 9
3.8 (AREA 1) Custom led Backlighting Integration with Reflective Edge
3.8.1 QTY: 1
3.9 (AREA 1) 3D Layered, Custom Floating Wall mounted on Cinder Block in Wood.
3.9.1 QTY: 1
3.10 (AREA 2) 3D Layered, Custom Floating Wall mounted on cinder block in wood.
3.10.1 QTY: 1
3.11 (AREA 2) Custom LED backlighting integration with reflective edge.
3.11.1 QTY: 1
3.12 (AREA 3) 3D Layered. Custom Floating Wall mounted on Cinder Block in Wood
3.12.1 QTY: 4
3.13 (AREA 3) Custom LED Backlighting Integration with Reflective Edge
3.13.1 QTY: 4
3.14 Digital Design and Engineering Services - Includes 3 Edits / Digital Scaling / Photo Realistic Mock-Up - 28 Design Hour Allotment
3.14.1 QTY: 1
3.15 Professional Installation -1yr Warranty on Workmanship- Includes all Prep Work, Cleaning, Installation Cost (All Custom Wallpaper), Vinyl, Window Perforation, Electrical Wiring, Re-Finishing, Hand Painted Details, Cleanup.
3.15.1 QTY: 1
Note: Presentation of all graphic design will be presented to the Food Service Officer by the contractor within seven (10) business days upon award of the contract . FSO will make the final decision for the design prior to installation.
3.14.3 All graphic custom design wallpaper will be top and finished by printed lamination for a high definition photography integration finish.
4. CONTRACTOR RESPONSIBILITIES
4.1. Contractor is responsible for verifying all dimensions prior to bidding and installation.
4.2. The contractor will provide personnel who are certified to perform required tasks.
4.3. Contractor will be permitted to work inside of the Dining Facility during the following hours:
Monday through Friday - 0730-1530 except during meal hours and holidays.
Meal hours are: Breakfast: 0530-0730; Lunch: 1100-1300.
Night or weekend shift may be coordinated with Food Service Officer. Night shift is preferred if project involves loud noise and heavy dust to not interfere with patrons during meal hours and must be coordinated with the FSO.
Exact days of work will be coordinated before commencement to ensure space availability. Coordinate with LCPO /FSO before commencing work to ensure serving line or each section is secured for work while utilizing different serving lines to serve the patrons.
Immediate work area will be properly secured by the contractor and will not conflict with meals being served or dining area being utilized.
4.4. Contractor will provide plastic barriers to contain dust or paint.
4.5. Contractor is responsible for daily clean up and disposal of all generated debris/materials to proper disposal or recycle containers at the back dock.
4.6. Contractor is responsible to obtain necessary security pass for base access. The government will not provide escorts to and from the gate.
5. ADDITIONAL REQUIREMENTS
a. The contractor shall provide consultation services to gain an understanding of specific visual references to incorporate into the mural work that are expressive of the location, culture, interest, or desired aesthetic of the client.
b. The contractor shall use a professional visual artist, design a mixed-media mural wall(s) that incorporates custom, commercial-grade wallpaper or high tach commercial grade vinyl, hand painted accents, high definition photography integration, LED lighting, wood, floating walls to create a 3 dimensional effect, and any other materials needed to enhance the overall look and feel of the space. (Consideration to the use of props, such as hanging décor, should be included and provided to further established the desired look and feel of the space.) The design should be artistic in nature and employ the use of stylization, fonts, negative and positive space, color, and texture to create a final look.
c. The contractor shall provide a visual artist’s draft using photo specific references of the space to show the full layout of elements, colors, textures, lighting, etc.
d. The contractor shall asses and prepare all affected areas to ensure proper installation of mixed media mural wall(s). Preparation may include but not be limited to, removal of molding, preexisting fixtures, repairing of holes or uneven textures, application of necessary primer, etc.
e. The contractor shall fabricate floating walls that create a three dimensional effect and layered aesthetic while simultaneously integrating walls into an overall cohesive design.
f. The contractor shall install LED lighting (backlighting) integrated into floating walls that create visual interest and align with the overall look and feel of the space. The contractor shall ensure the proper wiring and wire management of all electronic elements.
g. The contractor shall fabricate and install all visual aspects of mixed-media walls, including but not limited to, custom wallpaper or vinyl, hand-done painting, wood accents, veneers, stains or other specialty finishes. The contractor shall ensure the full design extends throughout floating walls while maintaining one cohesive look.
6. CONTRACTOR RESPONSIBILITIES
a. Contractor is responsible for verifying all dimensions prior to bidding and installation.
b. The contractor will provide personnel who are certified to perform required tasks.
c. Contractor will be permitted to work inside of the Dining Facility during the following hours: Monday through Friday - 0730-1700 except during meal hours and holidays.
Meal hours are: Breakfast: 0600-0730; Lunch: 1100-1230; Dinner 1600-1730. Night or weekend shift may be coordinated with Food Service Officer with no additional cost in pricing. Night shift is preferred if project involves loud noise and heavy dust to not interfere with patrons during meal hours and must be coordinated with the FSO. Exact days of work will be coordinated before commencement to ensure space availability.
Coordinate with LCPO /FSO before commencing work to ensure serving line or each section is secured for work while utilizing different serving lines to serve the patrons.
Immediate work area will be properly secured by the contractor and will not conflict with meals being served or dining area being utilized.
d. Contractor will provide plastic barriers to contain dust or paint.
e. Contractor is responsible for daily clean up and disposal of all generated debris/materials to proper disposal or recycle containers at the back dock.
f. Contractor is responsible to obtain necessary security pass for base access. The government will not provide escorts to and from the gate.
7. COMPLETION: This project must be fully completed within 90 days after contract award. First 30 days will be allotted for design phase, drafting, editing, and final approval of design. Once design has been approved, 30-60 days will be allotted for installation.