SOW Landscape Building 4 -25.pdf
PDF 208 KB Posted
- Attached to
- MDC BROOKLYN BUILDING 4 / DAYTON MANOR Landscaping services Federal contract opportunity
- Solicitation number
- 15BBR025Q00000016
About this file
This Statement of Work (SOW) outlines landscaping services for the Federal Bureau of Prisons (FBOP) Metropolitan Detention Center - Building 4 located at 199 Flushing Avenue in Brooklyn, NY. The contract requires a contractor to provide equipment, labor, and materials to maintain common areas from May 1, 2025 to September 30, 2025, with services including bi-weekly debris removal, weed control across roadways and walkways, and chemical application with safety notifications.
Key specifications include an initial cleanup in May 2025, strict adherence to environmental and safety regulations, and maintenance of all roadways, pavements, sidewalks, and gravel areas surrounding the building. Work hours are 7:00 AM - 2:00 PM, Monday through Friday, with all invoices to be submitted monthly to jmaffeo@bop.gov. The FBOP will provide water, restroom access, and minimal electricity, while the contractor must supply all other equipment, personal protective equipment (PPE), and handle all material disposal. Chemical storage on-site is prohibited, and any work outside standard hours requires prior written approval.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| REQUEST FOR INFORMATION.pdf | ||
| SOW Landscape Dayton Manor -25.pdf | ||
| SERVICE CONTRACT ACT WD 2015-4187 REVISION NO. 32.pdf | ||
| CONTRACTOR INFORMATION SHEET.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK/SPECIFICATIONS
MDC Brooklyn – Building 4
Landscaping Services
I. SPECIFICATIONS:
A. INTRODUCTION
The Federal Bureau of Prisons (FBOP), Metropolitan Detention Center- Building 4, located at 199 Flushing Avenue in Brooklyn, NY 11205 intends to make a single award to a responsible entity that will provide all necessary equipment, labor, materials, and incidentals to perform landscaping services.
B. SCOPE OF WORK
The contractor shall provide all necessary equipment, materials, and labor to maintain the common areas with strict adherence to weed control guidelines across all roadways, pavements, sidewalks, and gravel areas surrounding the building. The services include:
• Debris Removal: All leaves and foreign debris shall be cleared from the site on a bi-weekly basis.
• Weed Control: All walkways, driveways, and building perimeters must remain free of weeds.
• Chemical Application Safety: Whenever chemicals are applied, appropriate warning signs must be posted to notify occupants of the treatment.
Service Schedule:
• Initial Cleanup: May 2025
• Bi-weekly Maintenance Services: May 1, 2025 – September 30, Regulatory Compliance: Throughout every phase of this contract, all requirements—including environmental compliance, life safety, and all applicable Federal, State, and Local codes and regulations—must be strictly observed.
Industry Standards: All services and materials provided by the contractor shall conform to the most current industry standards.
Permitting: Should any permits be necessary, it is the contractor’s responsibility to secure them. Copies of all permits must be submitted to the Contracting Officer’s Representative (COR) immediately upon their receipt from the local agency.
D. UTILITIES
The FBOP will provide water, use of restrooms and minimal electricity service (120V) for small hand power tools including battery chargers. The contractor will provide all other equipment, supplies and materials needed to complete this project.
E. HOUSEKEEPING AND MATERIAL DISPOSAL
The contractor awarded the contract will be responsible to remove any cut grass, brush, and other debris from the services off the premises.
F. SUBMITTALS & TRAINING
1. All invoices sound be sent to jmaffeo@bop.gov at the end of each month.
2. Any deviations from this Statement of Work will be considered a Change Order Request and must be authorized through the institution’s Contracting Officer prior to the implementation of the requested change.
3. It is the Contractor’s responsibility to repair and/or replace any Government property damaged by contractors/subcontractors’ employees. Damage will be corrected and restored to previous condition at no cost to the Government.
mailto:jmaffeo@bop.gov
II. CONTRACTOR SECURITY/WORKING REGULATIONS
A. Work Hours:
Work Hours for the contractor are 7:00 AM – 2:00 PM, Monday - Friday, excluding weekends and federal holidays. Any work required to be completed at any other time than noted above must be requested in writing to the COR five (5) working days prior to the start of the work.
B. Storage of Materials and Equipment:
The storage of any type of chemical on site is prohibited.
C. Safety and Personal Protective Equipment:
All contractors and employees shall have and wear the required personal protective equipment (PPE) always prescribed by industry standards while on the job site. It is the responsibility of the contractor to provide all PPE equipment.