Summary: Statement of Work – Dining Facility Equipment Installation

This is a Statement of Work for professional dining facility equipment installation services at Stafford Dining Facility Building 2457. The contractor must provide comprehensive labor, supervision, tools, equipment, materials, and transportation to deliver, assemble, connect, and test 24 pieces of commercial kitchen and dining room equipment. Key scope elements include equipment delivery and placement per architectural floor plans; utility hookups (electrical, plumbing, gas, and steam) compliant with local commercial building and health codes; ventilation and exhaust system integration for cooking equipment; and initial operational checks, calibration, and safety testing performed in the presence of the facility manager.

The contractor is responsible for site preparation verification to ensure utilities meet manufacturer specifications; strict adherence to OSHA safety standards and PPE requirements; daily debris removal; and handover deliverables including manufacturer manuals, warranty documentation, maintenance schedules, a one-hour operational training session for kitchen staff, and a signed Certificate of Completion. The government will provide uninterrupted facility access during agreed working hours, ensure utilities are active and accessible, and designate a point of contact for coordination. Project acceptance requires that all equipment be securely anchored, leveled, and operational; utility connections pass local code inspections without defects; and staff training be completed and signed off by the Contracting Officer's Representative. The Period of Performance is listed as "TBD."

View the file

Other files

File Type Posted
Responses Solicitation W911SG26QA064.pdf PDF
Enclosure A.xlsx XLSX spreadsheet
Solicitation - W911SG26QA064.pdf PDF
Solicitation - W911SG26QA064.pdf PDF
Combined Solicitation for Kitchen Supplies- Updated Final.pdf PDF
Enclosure A.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work: Dining Facility Equipment Installation

1. Project Overview Project Title: Dining Facility Equipment Installation Services

• Objective: To procure professional delivery, assembly, utility connection, and testing services for commercial kitchen and dining room equipment at Stafford

Dining Facility Building 2457.

• Period of Performance: TBD

2. Scope of Work

The Contractor shall furnish all labor, supervision, tools, equipment, materials, and transportation necessary to install, calibrate, and test the dining facility equipment listed below.

• Equipment Delivery & Placement: Receive shipments, inspect for freight damage, and position equipment in designated kitchen and serving line layouts per architectural floor plans.

• Utility Hookups: Connect equipment to existing stub-ups for electrical, plumbing, gas, and steam lines in compliance with local commercial building and health codes.

• Ventilation & Exhaust: Tie in ventilation hoods or confirm proper clearance for convection ovens, fryers, and griddles.

• Startup & Testing: Perform initial operational checks, calibration, and safety testing for each piece of equipment in the presence of the facility manager.

3. Equipment Inventory (Example List)

Item # Description / Model Quantity Location / Zone

1 Commercial Combi Oven (Gas) 2 Main Kitchen - Hot Line

2 Convection oven 6 Main Kitchen

3 Pass thru refrigerator 1 Main Kitchen

Range 36” 6 open burners

20 Qt planetary mixer

Electric Food Slicer

60 QT planetary Mixer

Double stack steamer

Tilting skillet braising pan gas

Tilting kettle 40 gallon gas

Griddle gas counter

Fryer floor gas

HD range 36Inch 6 open burners gas

Wire shelving

Ice maker with bin

Main Kitchen

Manin Kitchen

Main kitchen

Mian Kitchen

4. Contractor Responsibilities & Deliverables

• Site Preparation Verification: Inspect the installation site prior to work commencement to verify that electrical voltage, water pressure, and drainage meet manufacturer specifications.

• Safety Compliance: Adhere to all OSHA standards, wear required PPE, and maintain a clean, debris-free work zone daily.

• Debris Removal: Remove all crating, packaging materials, and installation debris from the premises daily and dispose of them properly.

• Handover Deliverables:

o Provide manufacturer manuals, warranty documentation, and maintenance schedules.

o Conduct a 1-hour operational training session for facility kitchen staff.

o Deliver a signed Certificate of Completion and sign-off sheet.

Item # Description / Model Quantity Location / Zone

Pass thru heated cabinet

Reach in heated cabinet

Reach in refrigerator

Reach in Freezer

Pots and pans shelving racks

Heated holding proofing cabinet mobile

Six slots heated serving lines

Six well top mounted cold well

Roll through refrigerator

Mian Kitchen

Serving lines

5. Government / Client Responsibilities

• Provide uninterrupted access to the facility during agreed-upon working hours

([Insert Hours, e.g., 8:00 AM – 5:00 PM]).

• Ensure utilities (water, gas, electricity) are active and accessible at connection points.

• Designate a point of contact (POC) for site access and coordination.

6. Acceptance Criteria

The project will be considered successfully completed when:

• All equipment is securely anchored, leveled, and operational.

• Utility connections pass local code or safety inspections without leaks or electrical faults.

• Staff training has been completed and signed off by the COR.