SOW_Heavy Equipment Recovery and Transportation.pdf
PDF 228 KB Posted
- Attached to
- VSFB Heavy Equipment Recovery and Transportation
- Solicitation number
- FA461026Q0053
About this file
This is a Statement of Work (SOW) for heavy equipment recovery, environmental remediation, and transportation services at Vandenberg Space Force Base (VSFB) in California. The contractor must recover one Caterpillar Challenger MT765C rubber-track tractor (approximately 36,000 lbs) and one Case International 770 disc harrow (approximately 12,000 lbs) from an off-road ditch, along with approximately twenty 100-lb cast-iron suitcase weights dispersed up to 85 feet from the impact site and one 150-lb rear hitch assembly. The work is a firm-fixed-price, one-time operation that must be completed within seventy-two (72) consecutive hours from the start of on-site recovery operations.
The contractor shall provide all personnel, equipment, tools, PPE, and rigging necessary to safely upright and extricate both pieces of equipment using commercially recognized heavy recovery methods. Additional requirements include locating and recovering all ejected components, conducting a deliberate sweep for personal effects belonging to the deceased operator with strict chain-of-custody protocols, excavating and containerizing approximately 20 gallons of hydrocarbon-contaminated soil for proper disposal in compliance with federal and California environmental regulations, applying opaque tarping to maintain operational privacy during transport, and transporting all recovered assets approximately 20 miles to a Government-designated facility on VSFB. Personnel must possess professional heavy recovery certifications (WreckMaster, TRAA Level 3, or equivalent), HAZWOPER training per OSHA 29 CFR 1910.120, and be U.S. citizens or lawful permanent residents capable of obtaining Defense Biometric Identification System (DBIDS) credentials. Government acceptance requires safe extraction of both machines, complete collection of all ballast weights and hardware, dignified handover of personal effects to the authorized Government Point of Contact, proper excavation and packaging of contaminated soil, complete visual concealment via opaque tarping, successful delivery and offloading at the designated laydown yard, and final site walkthrough confirming clean closeout. Mobilization must occur within 24 hours of the Notice to Proceed.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
Heavy Equipment Recovery, Environmental Remediation, and Transportation Services Vandenberg Space Force Base, California
1.0 GENERAL OVERVIEW / PURPOSE
1.1 Purpose: The purpose of this requirement is to obtain commercial contractor support to safely recover, remediate the incident site of, secure, and transport Government-owned agricultural equipment and associated components from an off-road incident site located on Vandenberg Space Force Base (VSFB), California.
1.2 Primary Assets Involved:
• Primary Tractor: One (1) Caterpillar Challenger MT765C rubber-track tractor (approx. 36,000 lbs). The tractor is currently resting in a ditch; its precise orientation, structural integrity, and rollover state are unverified and require contractor verification.
• Towed Implement: One (1) Case International 770 rigid/non-folding disc harrow (approx. 12,000 lbs; estimated 15-foot working width).
• Detached Ballast and Components: Approximately twenty (20) cast-iron tractor suitcase weights (~100 lbs each, totaling ~2,000 lbs) ejected up to 85 feet from the impact point, and one (1) detached rear hitch/connection assembly (~150 lbs).
1.3 Environmental Remediation & Debris: The contractor shall collect all impact debris and ejecta, recover and secure any personal effects, and excavate, containerize, and legally dispose of hydrocarbon-contaminated soil resulting from an estimated 20-gallon release of diesel fuel, hydraulic fluid, and engine lubricating oil situated directly beneath the tractor.
1.4 Visual Screening & Transport: Following recovery, site cleanup, and loading, the contractor shall cover all recovered equipment with opaque tarpaulins to prevent unauthorized photography during transport and safely haul all assets approximately twenty (20) miles over unimproved and paved base roads to a designated Government facility on VSFB.
2.0 SCOPE OF WORK
The contractor shall provide all personnel, management, supervision, tools, materials, personal protective equipment (PPE), rigging, winching equipment, lifting devices, spill containment/excavation supplies, and heavy transport vehicles necessary to perform a one-time turnkey recovery, site clearance, environmental remediation, and transportation operation.
Specific scope elements include:
1. Accessing and assessing the incident site, ingress/egress routes, and equipment condition.
2. Developing and executing a safe rigging, uprighting, and extrication plan for the tractor and the disc harrow.
3. Locating, recovering, and consolidating all ejected tractor components, including twenty ~100 lb weights and the ~150 lb rear connection assembly.
4. Conducting a deliberate sweep for personal effects belonging to the deceased operator, maintaining chain-of-custody, and releasing them exclusively to the authorized Government Point of Contact (POC).
5. Excavating, containerizing, profiling, transporting, and disposing of petroleum-, oil-, and lubricant-contaminated soil (estimated 20 gallons of fluid release) in full compliance with federal, California state, and VSFB environmental regulations.
6. Applying opaque coverings/tarps to the equipment prior to public road movement to maintain operational privacy and prevent unauthorized observation or photography.
7. Transporting the tractor, implement, ballast weights, components, and containerized waste approximately 20 miles to Government-designated drop-off point(s) on VSFB.
8. Offloading and safely staging all equipment and materials at the destination.
3.0 EQUIPMENT AND INCIDENT DESCRIPTION
Asset / Parameter Description / Specification
Primary Unit Caterpillar Challenger MT765C Rubber- Track Agricultural Tractor
Estimated Tractor Weight Approximately 36,000 lbs (excluding detached weights)
Secondary Unit / Implement Case International 770 Disc Harrow (Non-folding)
Implement Specifications Approx. 12,000 lbs; estimated width:
~15 feet (contractor shall verify on-site)
Detached Ballast / Weights Approx. 20 suitcase weights (~100 lbs each), dispersed up to 85 feet
Detached Hardware Rear hitch / connection assembly (~150 lbs)
Incident Terrain Steep ditch / depression accessible via unimproved trails or firebreaks
Surface Conditions Unpaved dirt/gravel trail; potential uneven grading, grade transitions, and soft shoulder conditions
Contamination Estimate Approx. 20 gallons mixed diesel fuel, hydraulic fluid, and engine oil localized directly under the chassis
4.0 PLACE OF PERFORMANCE AND OPERATIONAL ACCESS
4.1 Incident Site: Government-designated incident site located within the boundaries of Vandenberg Space Force Base, California.
4.2 Access Route: Site access is restricted and requires traversal along unimproved trails, dirt roads, or utility rights-of-way. The Government will provide known waypoint coordinates and access corridor parameters. The contractor is solely responsible for determining whether its recovery vehicles, wreckers, or lowboy trailers can negotiate the trail or if winching/tow-staging to improved road surfaces is necessary.
4.3 Delivery Destination: A secure Government-designated laydown yard or maintenance facility located on VSFB, approximately 20 miles from the incident site.
5.0 CONTRACTOR RESPONSIBILITIES AND PERFORMANCE
REQUIREMENTS
5.1 Site Assessment and Work Plan
• Prior to commencing mechanical operations, the contractor shall conduct a thorough physical survey of the incident site, access road ground bearing capacity, slope stability, and equipment posture.
• The contractor shall establish a written or verbal Incident Recovery Plan presented to the Government POC, detailing rigging anchor points, winch lines of pull, ground stabilization requirements, spill containment precautions, and sequencing of the lift.
5.2 Heavy Equipment Recovery Operations
• Safely upright, extricate, and stage the Caterpillar Challenger MT765C tractor and the Case 770 disc harrow from the ditch without inflicting further avoidable structural damage to Government property.
• Employ commercially recognized heavy recovery methods (e.g., heavy-duty rotators, severe-duty winching, snatch blocks, crawler cranes, or track recovery apparatus).
• Ensure all wire ropes, synthetic slings, shackles, spreader bars, and pull points are certified and clearly rated well above the working load requirements of the combined ~48,000 lb machinery package.
5.3 Debris Field Clearance and Sensitive Item Protocol
• Hardware & Debris Retrieval: Locate, recover, and load all scattered vehicle components and impact ejecta within the incident perimeter. This explicitly includes:
• Retrieving all ~100 lb cast-iron ballast weights (estimated 20 units) located in the 85-foot dispersal radius.
• Retrieving the ~150 lb rear connection assembly.
• Picking up small shattered debris, glass, fasteners, body panels, and structural fragments.
• Personal Effects Custody Protocol: Due to the fatal nature of the incident, personnel shall conduct a deliberate sweep for personal effects belonging to the deceased operator (e.g., wallet, phone, keys, clothing, personal tools, documentation).
• Any identified personal effects shall be treated with utmost dignity and immediately placed into clean, sealed bags/containers.
• Personal effects must be kept segregated from mechanical debris and turned over directly and privately to the designated Government POC or Air Force Office of Special Investigations (AFOSI) / Security Forces representative.
Under no circumstances shall personal effects be photographed, disclosed, or commingled with scrap.
5.4 Environmental Remediation and Spill Remediation
• Containment: Immediately deploy absorbent booms and pads to capture any lingering or active fluid trickles.
• Soil Excavation: Excavate all soil impacted by the estimated 20 gallons of hydrocarbon fluids (diesel, hydraulic oil, motor oil) situated beneath the tractor.
• Packaging and Labeling: Shovel/excavate contaminated soil into UN/DOT-approved 55-gallon open-head steel drums or heavy-duty bulk hazmat spill sacks. Properly label containers in accordance with California Environmental Protection Agency (CalEPA) / Department of Toxic Substances Control (DTSC) regulations.
• Disposal: Coordinate with the VSFB Environmental Management Office (30 CES/CEIE) for waste profiling, manifesting, and lawful off-site transport to an EPA/State-permitted hazardous waste treatment, storage, or disposal facility (TSDF). The contractor shall provide copies of certified disposal manifests to the Government POC.
5.5 Visual Privacy, Security, and Opaque Tarping
• Operations Security (OPSEC) & Privacy: Prior to initiating road transport along public or installation thoroughfares, the contractor shall completely cover the tractor (and cab/chassis area) with opaque, heavy-duty tarpaulins or form-fitting industrial vehicle covers.
• The covering shall be firmly lashed and secured to withstand 55 mph transit wind loads without flapping loose, tearing, or exposing the machinery.
• The purpose of this covering is to maintain privacy, respect the sensitivity of the fatal accident, and prevent unauthorized visual inspection or bystander photography/recording while in transit.
5.6 Transportation and Securement
• Provide heavy-haul tractors and lowboy/drop-deck trailers adequate for an approximate 36,000 lb tracked machine, a ~12,000 lb, 15-foot wide disc harrow, recovered weights, and containerized soil.
• Comply with DOT federal cargo securement standards (49 CFR Parts 392–393) using graded tie-down chains and commercial binders rated for the cargo weight.
• Provide wide-load escort vehicles, oversized transit banners, and amber warning lighting if required by VSFB base transportation regulations for the 15-foot wide implement.
5.7 Offloading and Destination Staging
• Safely transport all items approximately 20 miles across base roads to the Government-designated drop point.
• Offload the tractor, implement, ballast weights, and components in a neat, secure arrangement.
• Stage containerized contaminated soil in the Government's designated hazardous waste accumulation point pending final manifest sign-off.
6.0 PERSONNEL, VEHICLE, AND CERTIFICATION
REQUIREMENTS
6.1 Operator Certifications: Rigging personnel, wrecker operators, and equipment handlers shall possess professional licensing, NCCCO/crane certifications, or verified national towing/recovery certifications (e.g., WreckMaster, TRAA Level 3 or equivalent heavy recovery credential).
6.2 Environmental / HAZWOPER Compliance: Personnel engaged in the excavation, handling, packaging, and profiling of petroleum-contaminated soil shall be trained in accordance with OSHA 29 CFR 1910.120 (HAZWOPER) standards.
6.3 Base Access: Contractor personnel must be U.S. citizens or lawful permanent residents capable of passing background security checks to obtain Defense Biometric Identification System (DBIDS) installation access credentials for Vandenberg Space Force Base.
7.0 SAFETY AND INCIDENT REPORTING
7.1 The contractor shall establish a perimeter exclusion zone (hot zone / work zone) during uprighting, winching, and high-tension cable operations. Only essential rigging personnel shall be permitted within line-of-fire pull angles.
7.2 Stop Work Authority: The contractor and Government POC each possess mandatory "Stop Work Authority" if unsafe rigging conditions, unforecasted weather, ground slippage, or structural instability threaten life or secondary equipment damage.
7.3 Mishap Notification: Any unexpected fluid spill, rigging failure, personnel injury, or near-miss incident shall be reported immediately to the Government POC and the VSFB Emergency Dispatch (if medical/fire support is required).
8.0 ENVIRONMENTAL AND BASE COMPLIANCE
8.1 The contractor shall comply with all California Air Resources Board (CARB) off-road diesel standards, local Santa Barbara County Air Pollution Control District (APCD) rules, and VSFB Installation Environmental Management guidelines.
8.2 The contractor shall maintain dedicated spill cleanup kits (absorbent pads, containment dikes, dry absorbent, shovel, drums) on-site during all phases of extraction and transit.
9.0 GOVERNMENT RESPONSIBILITIES
The Government shall:
9. Provide authorized entry credentials and sponsor installation access passes for all approved contractor personnel and commercial vehicles.
10. Furnish an authorized Government representative (POC) on-site to verify boundaries, observe milestones, and facilitate coordination.
11. Identify the exact staging and offloading facility located on VSFB.
12. Authorize Notice to Proceed (NTP) once site access and clearances are finalized.
13. Receive and securely archive any recovered personal effects transferred by the contractor.
14. Provide designated staging coordinates for drummed contaminated soil and assist in validating waste profile coordination with 30 CES/CEIE.
10.0 PERIOD OF PERFORMANCE AND MILESTONE
SCHEDULE
10.1 Period of Performance: This is a firm-fixed-price, one-time heavy recovery, site remediation, and transportation effort.
10.2 Execution Timeline:
• Site Mobilization & Assessment: Within 24 hours of receiving the Government Notice to Proceed (NTP).
• Operational Completion: Complete recovery, ejecta retrieval, soil excavation, visual tarping, transport, and offloading within seventy-two (72) consecutive hours from the start of on-site recovery operations, unless severe weather or mission-essential base closures intervene.
11.0 GOVERNMENT ACCEPTANCE CRITERIA
Government acceptance and sign-off occur upon completion of all of the following:
15. Safe extraction and uprighting of both the Caterpillar Challenger MT765C and the Case 770 disc harrow from the ditch without secondary operational damage.
16. Complete field collection and inventory of all detached ballast weights (~20 units) and the rear hitch assembly.
17. Dignified, private handover of all discovered personal effects to the designated Government POC.
18. Excavation and drum packaging of the ~20 gallons of hydrocarbon-impacted soil beneath the tractor footprint, leaving the ground clear of free product or unmanaged petroleum staining.
19. Complete visual concealment of the tractor via opaque tarping prior to and during base roadway transit.
20. Successful transit, delivery, and offloading of all equipment, components, and waste containers at the Government laydown yard (approx. 20 miles away).
21. Full demobilization of contractor assets and final site walkthrough with the Government POC confirming clean, orderly closeout.
12.0 GOVERNMENT POINT OF CONTACT
The Government will assign a primary Contracting Officer's Representative (COR) or dedicated Technical Point of Contact (TPOC) upon contract award who will serve as the single authority for technical direction, access coordination, receipt of personal effects, and final service acceptance.
| STATEMENT OF WORK (SOW) |
| Heavy Equipment Recovery, Environmental Remediation, and Transportation Services |
| 1.0 GENERAL OVERVIEW / PURPOSE |
| 2.0 SCOPE OF WORK |
| 3.0 EQUIPMENT AND INCIDENT DESCRIPTION |
| 4.0 PLACE OF PERFORMANCE AND OPERATIONAL ACCESS |
| 5.0 CONTRACTOR RESPONSIBILITIES AND PERFORMANCE REQUIREMENTS |
| 5.1 Site Assessment and Work Plan |
| 5.2 Heavy Equipment Recovery Operations |
| 5.3 Debris Field Clearance and Sensitive Item Protocol |
| 5.4 Environmental Remediation and Spill Remediation |
| 5.5 Visual Privacy, Security, and Opaque Tarping |
| 5.6 Transportation and Securement |
| 5.7 Offloading and Destination Staging |
| 6.0 PERSONNEL, VEHICLE, AND CERTIFICATION REQUIREMENTS |
| 7.0 SAFETY AND INCIDENT REPORTING |
| 8.0 ENVIRONMENTAL AND BASE COMPLIANCE |
| 9.0 GOVERNMENT RESPONSIBILITIES |
| 10.0 PERIOD OF PERFORMANCE AND MILESTONE SCHEDULE |
| 11.0 GOVERNMENT ACCEPTANCE CRITERIA |
| 12.0 GOVERNMENT POINT OF CONTACT |