This Statement of Work (SOW) details the replacement of a natural gas generator for the Wind River Agency's Office of Justice Service (OJS) Buildings 1134 & 1135 in Fort Washakie, Wyoming. The project requires a contractor to remove the existing generator and install a new 48kW Generac Generator (RG04845ANAX) with specific technical specifications, including a liquid-cooled 4.5 Liter inline 4-cylinder engine, natural gas fuel, 120/240 volt single phase power, and a 200-amp main line circuit breaker.
The project is scheduled to start on July 1, 2025, with a 90-calendar day performance period. The contractor will be responsible for complete installation, including transportation, site preparation, electrical and gas line modifications, testing, and disposal of the old equipment. Key requirements include ensuring compatibility with existing systems, conforming to National Electrical Code and safety standards, providing warranty documentation, and training facilities staff on generator operation. The project location is at 15994 and 15596 Hwy 287 in Fort Washakie, Wyoming, at an elevation of approximately 5,571 feet.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140A0425R0005_Amd_0002.pdf | ||
| Sol_140A0425R0005_Amd_0001.pdf | ||
| Sol_140A0425R0005.pdf | ||
| IA_-_IEE_Representation_Form.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
OJS Generator Replacement
Wind River Agency
Fort Washakie, Wyoming
Background
The Wind River Agency is located at Fort Washakie, Wyoming. The Wind River Facilities Program supports the Office of Justice Service (OJS) in the administration of workplaces.
The building is a 24 hour facility for OJS staff.
Objective
The OJS Buildings 1134 & 1135 located at 15994 Hwy 287 and 15596 Hwy 287 Fort Washakie WY are in need of back up power to ensure emergency services have power for dispatch equipment. A replacement natural gas Generator is required to provide backup power to both the buildings.
Scope
The Bureau of Indian Affairs is seeking contracted services of a replacement generator for Wind River Agency OJS Buildings 1134 & 1135. The current generator is in disrepair and has recently surpassed the expected service date and necessitates replacement. The Wind River Agency is located at Fort Washakie Wyoming, at an elevation of approximately 5,571 feet.
Requirements
The contractor shall verify total area and size the natural gas generator to meet the requirements as specified and Contractor shall purchase and install new natural gas generator, with the appropriate wattage to meet the heating demands of each government building, cabling and switch rack.
The new natural gas generator shall be produced by an industry recognized manufacturer and at a minimum meet the following specifications, Generac Generator, RG04845ANAX consisting of the following features and accessories:
• 48kW Liquid cooled, 4.5 Liter inline 4 cyl engine, 1800 RPM
• Fuel: Natural Gas
• 120/240 volt single phase
• Main Line Circuit Breaker 200 amps
• Sound attenuated weather enclosure
• Critical silencer
• Fuel Flex Line
• 1000 watt engine block heater, thermostatically controlled
• Battery, group 26 (TWE installed)
• Battery trickle charger
The project will involve the removal & disposal of the existing natural gas generator and the installation of a new replacement natural gas generator.
Assessment of existing concrete pad and a determine if replacement generator will fit in the existing location. If necessary then contractor will replace or expand the existing concrete pad.
The contractor shall provide all labor, equipment, and materials to complete the project, including all associated materials/supplies required to successfully complete the installation work.
The Contractor is responsible for the transportation of the new gas generator to the appropriate government building, as well as the receipt and storage of the new natural gas generator.
The Contractor shall inspect all installation areas before the installation of the new natural gas generator, to ensure that the areas meet the manufacturer’s recommended installation requirements.
The Contractor shall modify/retrofit the existing electrical wiring & connections, natural gas lines, and other miscellaneous natural gas generator components with the goal of providing backup power.
The new natural gas generator and equipment shall fit within the locations of the existing natural gas-fired generator.
The Contactor is responsible for proper storage and disposal of all project waste and debris from the project site.
The Contractor shall ensure compatibility between the new natural gas generator and all the other natural gas generator system components that are not replaced or modified.
The demolished natural gas generator, including all debris generated by this project shall be removed at regular intervals from the project site and recycled or properly disposed of off-site by the Contractor.
Recycle all ferrous and nonferrous metals from the project. Disposal of materials shall be in conformance with applicable Federal, State, and local pollution regulations at the Contractor’s expense.
The contractor shall comply with manufacturer’s instructions for rigging and handling equipment.
The contractor is responsible for all work including electrical, gas, propane and plumbing to assure that the new natural gas-fired generator and equipment are compatible, and function as designed.
The contractor shall install natural gas-fired generator plumb and level, firmly anchored in locations of previous footprint and maintain manufacturer’s recommended clearances.
After installing the new natural gas generator, the Contractor shall start and test the new natural gas-fired generator to ensure that they are operational.
The contractor is responsible for testing the natural gas generator system to ensure no gas leakage and that it properly starts when power is out.
The contractor shall ensure that all controls, on/off functions, set point adjustments, alarm notifications, temperature sensing devices, factory settings, for the natural gas generator system work accordingly as designed.
The contractor shall provide training to Facilities staff for operation of generator.
The contractor shall complete the installation work according to Occupational Health and Safety Act Chapter 88:08 Act 1 of 2004 Amended by 3 of 2006, National Electrical Code (NEC), TTS 171: Part 1: 2015 and NFPA® 110 Standard for Emergency and Standby Power Systems.
PROJECT LOCATON
The project is located Wind River Agency, OJS Buildings 1134 & 1135 located at 15994 Hwy 287 and 15596 Hwy 287 Fort Washakie WY
Deliverables:
The contractor shall provide completed warranty documentation and owner’s manuals for all equipment installed.
Fully function natural gas generator to provide back up power to both OJS Buildings.
Government Furnished Property:
Floor plan drawing of the government buildings.
Travel:
Not applicable
Special Requirements:
The government quarters may be occupied during the contract period.
The contractor shall notify the Contracting Officer and Contracting Officer Representative if its necessary to shut down power.
All electrical work shall be performed by competent craftsmen skilled in the trade involved and shall be done in a manner consistent with normal industry standards.
All work shall conform to the currently adopted edition of the National Electric Code (NEC), NFPA® 110 Standard for Emergency and Standby Power Systems and all other applicable state and local codes or standards.
Contractor shall submit product information for the new natural gas generator prior to beginning any installation work for approval. No installation work shall commence prior to approval of submittals.
Period of Performance:
The estimated start date for this project is July 1, 2025 with a ninety (90) calendar day period of performance (POP) after issuance of Notice to Proceed (NTP). Additional working hours may be negotiated with the Contracting Officer. Access to the building will be coordinated through the COR.
Work shall be performed between 8 am on Monday through 4:30 pm on Friday, during the contract’s performance period.