SOW FY27 Loading Dock Removal and Installation of Asphalt Driveway CORRIGAN.docx
DOCX document 34 KB Posted
- Solicitation number
- BD-27-1022-DMH05-5410A-132170
- Issued by
- Bristol County, Massachusetts
About this file
This is a Scope of Work document issued by the Massachusetts Department of Mental Health for the John C. Corrigan Mental Health Center located in Fall River, MA, categorized under Trade Category TRD02 for Asphalt Paving Services. The project involves the complete removal and replacement of an existing asphalt driveway at the facility located at 49 Hillside Street, Fall River, MA 02720. The scope of work includes demolition and removal of existing asphalt pavement with proper disposal, subbase preparation with gravel scarification and compaction, installation of Hot Mix Asphalt in two courses (3/4-inch binder course and 3/8-inch top course) in accordance with MassDOT specifications, and restoration of all pavement markings including parking stalls, directional arrows, stop bars, crosswalks, and handicap spaces to ADA and MUTCD standards. A mandatory site visit is required prior to bidding and is scheduled for Thursday, August 13th, 2026 at 10:00 AM, with the bid opening date set for Monday, August 24th, 2026 at 2:00 PM. Interested contractors should contact Nicholas Keddie, Facilities Manager, at 508.235.7238/508.816.1541 or Nicholas.keddie2@mass.gov to confirm attendance at the site visit.
The contractor shall furnish all labor, materials, equipment, supervision, transportation, permits if required, and incidentals necessary to complete the project in accordance with applicable federal, state, and local regulations and industry standards. The contractor is responsible for coordinating work with the Owner to minimize disruption to facility operations, maintaining safe pedestrian and vehicle access, providing traffic control and safety measures, and verifying existing field conditions prior to beginning work. A minimum one-year warranty covering defects in workmanship and materials is required, beginning on the date of final acceptance. The bidding process requires submission of the OSD Bid Form with the bid, and prevailing wage rate requirements apply to this contract. No specific contract term, renewal options, or pricing information is detailed in the scope of work document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Loading Dock Removal and Installation of Asphalt Driveway John C. Corrigan Mental Health Center, 49 Hillside, Fall River, MA 02720 TRD02 Category 1: Asphalt Paving Services
Scope of Work Statement
AWARDING ENTITY
Awarding Entity: Department of Mental Health Southeast Area Agency Name and Address: John C. Corrigan Mental Health Center, 49 Hillside Street, Fall River, MA 02720
CONTACT INFORMATION
Name and Title: Nicholas Keddie, Facilities Manager, John C. Corrigan MHC Phone: 508.235.7238/508.816.1541 Email Address: Nicholas.keddie2@mass.gov
CONTRACT AND BIDDING INFORMATION
Project Name: Loading Dock Removal and Installation of Asphalt Driveway
Bid opening date: Monday August 24th, 2026, 2pm
Pre-Bid Conference: Mandatory Site visit required prior to bidding. Site visit to be held Thursday August 13th. 2026 at 10:00 AM. Contact Nicholas Keddie to confirm attendance at 508.235.7238/508.816.1541 or Email:Nicholas.keddie2@mass.gov.
OSD Trade Category: TRD02 Category 1: Asphalt Paving Services
SCOPE OF WORK
Asphalt Driveway Removal and Replacement Project Description The Contractor shall furnish all labor, materials, equipment, supervision, transportation, permits (if required), and incidentals necessary to remove and replace the existing asphalt driveway in its entirety. All work shall be completed in accordance with applicable federal, state, and local regulations, industry standards, and manufacturer recommendations.
Scope of Work The Contractor shall perform the following work:
1. Demolition and Removal
· Saw cut pavement where required to provide clean transitions.
· Remove the existing asphalt pavement.
· Load, haul, and legally dispose of all removed asphalt and associated debris at an approved disposal facility.
· Protect adjacent pavement, curbing, utilities, landscaping, and structures from damage during demolition.
2. Subbase Preparation
· Scarify the existing gravel subbase to the depth necessary to achieve the required finished grades.
· Furnish and install additional processed gravel as needed to correct deficiencies and establish proper drainage and pavement elevations.
· Fine grade the processed gravel subbase to the required lines and grades.
· Compact the subbase using appropriate compaction equipment to achieve a stable, uniform surface suitable for paving.
3. Hot Mix Asphalt Installation
· Install a Hot Mix Asphalt (HMA) 3/4-inch Binder Course at the specified compacted thickness.
· Install a Hot Mix Asphalt (HMA) 3/8-inch Top Course over the binder course at the specified compacted thickness.
· Place and compact all asphalt in accordance with Massachusetts Department of Transportation (MassDOT) specifications and accepted paving practices.
· Ensure smooth pavement transitions at all existing pavement tie-ins.
4. Pavement Markings
· Layout and install pavement markings to match the original striping configuration unless otherwise directed by the Owner.
· Pavement markings shall include all parking stalls, directional arrows, stop bars, crosswalks, handicap spaces, and other markings that previously existed.
· All pavement markings shall comply with applicable ADA requirements and current MUTCD standards where applicable.
5. Cleanup
· Remove all excess materials, equipment, and debris from the project site upon completion.
· Leave the work area clean and ready for use.
· Repair any damage caused by construction activities at no additional cost to the Owner.
Contractor Responsibilities
· Coordinate work with the Owner to minimize disruption to facility operations.
· Maintain safe pedestrian and vehicle access where required.
· Provide appropriate traffic control, barricades, warning signs, and safety measures throughout the duration of the project.
· Verify all existing field conditions prior to beginning work.
· Notify the Owner of any unforeseen site conditions before proceeding with corrective work.
Warranty The Contractor shall provide a minimum one (1) year warranty covering defects in workmanship and materials beginning on the date of final acceptance.
ATTACHMENTS
The following sections are included in the appendices and are part of this contract:
X Prevailing Wage Rate Requirements
FORMS
The following forms are to be completed and submitted with the bid:
X OSD Bid Form
Scope of Work Statement Page 2 of 2