Repair HVAC Fuel Cell Hangar 21
Solicitation number
W50S6L22B0001
Issued by

About this file

This statement of work and related federal contract opportunity outline requirements for repairing the HVAC system and fuel cell at Hangar 21, Joint Base Elmendorf-Richardson in Alaska. The statement of work provides project details including compliance with security, environmental, and antiterrorism regulations. The federal contract opportunity is a firm fixed-price solicitation seeking bids to provide all labor, materials, equipment, and supervision necessary to complete HVAC and fuel cell repairs according to attached specifications and drawings. Bids are due by December 2022 with project completion expected within 270 days of award. The total project value is estimated between $1-5 million. The solicitation is designated as a total small business set-aside with a 15% limitation on subcontracting.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PLANNING/CONSTRUCTION SERVICES

STATEMENT OF WORK

Repair HVAC, C-17 Fuel Cell, Hangar 21

FXSB172827

15 November 2021

1 GENERAL

1.1 The work covered by this Statement of Work (SOW) includes providing all plant, labor, equipment, and materials required to perform planning and construction of the tasks outlined below.

The contractor shall be responsible for necessary travel and services required to perform the work.

1.2 The contract procedures and project objective provide only general direction of what is required and does not constitute a complete explanation of the work involved. The government is relying on the contractor’s expertise in providing planning and construction that meets the intent of the task. The contractor shall work closely with designated government representative to work out details.

1.3 The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR).

The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of

Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force

Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

1.4 Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index

(NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

1.5 Defense Contractor Manpower Reporting Initiative. the contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the National Guard Bureau (or your organization) via the secure data collection site www.sam.gov.

1.6 Work shall comply with local, state, and federal codes and applicable ANG Engineering

Technical Letters (ETLs).

1.7 Materials incorporated into the work shall be new.

1.8 Asbestos Containing Materials (ACM) are not present in Hangar 21.

1.9 The contractor shall account for all contractor HAZMAT using the JBER Contractor Hazardous

Materials Usage Tracking Form (Appendix A of JBER IHMP). Additionally, all contractors and their subcontractors shall comply with applicable Federal regulations (FAR Clauses 52.223-3, Hazardous

Material Identification and Material Safety Data; 52.223-5, Pollution Prevention and Right-to-Know

Information; 52.223-7, Notice of Radioactive Material; 52.223-19, Compliance with Environmental

Management Systems; AFMAN 32-7002, Environmental Compliance and Pollution Prevention), local regulations, and JBER’s Environmental regulations including but not limited to JBER’s Integrated http://www.sam.gov/

Hazardous Material Plan (IHMP), and Hazardous Waste Management Plan (HWMP). These guidelines were established to protect the health and safety of personnel at JBER and to maintain compliance with the federal, state, and local laws. However these guidelines are subject to change. It is the contractors and subcontractors’ responsibilities to be familiar with the guidelines and seek approval before bringing on base any Hazardous Materials. The POC for environmental issues or concerns is 176 CES/CEV.

1.10 Anti-Terrorism / Operations Security / Information Protection.

1.10.1 Access and General Protection/Security Policy and Procedures. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s

Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security

Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection

Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

1.10.2 For contractors that do not require CAC, but require access to a DoD

Facility and/or Installation. Contractor and all associated sub‐contractors employees shall comply with adjudication standards and procedures using the National Crime

Information Center Interstate Identification Index (NCIC‐III) and Terrorist Screening

Database (TSDB) (AFI 31‐101 and AFI 10‐245), applicable installation, facility and area commander installation/facility access and local security policies and procedures

(provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

1.11 AT Level I Training. All contractor employees, to include subcontractor employees, requiring access Government Installations, Facilities and Controlled Access areas shall complete AT Level I awareness training within 10 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Certificates of completion for each affected contractor employee and subcontractor employee will be maintained by the COR or Antiterrorism

Representative. AT level I Awareness Training is available at the following website: http://jko.jten.mil

2 CONTRACT PROCEDURES

2.1 This contract shall be awarded on a firm fixed price basis.

2.2 The government has provided site plans, drawings and specifications for each of these projects.

2.3 Project specifications and drawings are attached to this Statement of Work (SOW) and are available for download at www.sam.gov.

2.4 The contractor shall clean up all construction debris and remove all unused materials.

2.5 The contractor shall walk the site with the government project manager for a final inspection to verify all tasks are complete and that objectives were achieved.

2.6 The contractor shall submit as-built drawings depicting actual work completed.

http://jko.jten.mil/ http://www.sam.gov/

3 PROJECT OBJECTIVES

BASE BID – Repair HVAC, Fuel Cell, Hangar 21. Non-personal services: services: Provide all plant, labor, new and current material, transportation, tools, equipment, appliances, supplies, services, permits, insurance and supervision necessary to repair the Hangar HVAC & Fuel Cell IAW this Statement of

Work (SOW) and the attached drawings and specifications prepared by Jacobs Engineering.

4 ATTACHMENTS

Attachment 1 – Specifications for project FXSB172827

Attachment 2 – Drawings for project FXSB172827

Attachment 3 – JBER Integrated Hazardous Material Plan (IHMP) dated 25 October 2020

Attachment 4 – JBER Hazardous Waste Management Plan dated 7 May 2020