This is a Statement of Work prepared by the Oregon Department of Corrections for corrective repairs at the Coffee Creek Correctional Facility (CCCF) located in Wilsonville, Oregon. The project addresses water intrusion affecting the dayroom area and requires comprehensive remediation of exterior window systems, flashing, sealant joints, and concrete drainage elements. The scope of work includes leak investigation and water testing at designated window and wall assemblies; removal and replacement of failed sealants and installation of new joint sealant per DOC specifications; installation of new stainless steel flashing, fluid-applied waterproofing, and associated components at sill and jamb locations; removal and reinstallation of electrical equipment, outlet shrouds, call boxes, and cameras as necessary; removal and replacement of exterior concrete panels to restore proper drainage; installation of a trench drain system connected to existing storm drainage infrastructure; replacement of damaged spandrel glass or insulated metal infill panels; and completion of interior dayroom repairs including drywall, paint, and finish restoration. All work will be performed during DOC daytime work windows, typically 6:30 AM to 2:30 PM, with final scheduling and phasing coordinated with DOC Facilities and Security.

Contractors must comply with all DOC security and escort requirements, submit tool lists in advance, follow DOC tool control procedures, maintain secure work zones with daily cleanup, and provide daily progress updates to DOC Facilities. Work must be performed per applicable codes, specifications, and manufacturer instructions. Project deliverables include confirmed leak remediation through successful water testing, installation of new waterproofing systems and components, completed interior repairs restoring dayroom functionality, and documentation of completed work including material specifications and installation notes. The scope is limited to identified locations contributing to dayroom water intrusion, and any unforeseen structural or system damage discovered during demolition requires separate authorization and approval.

View the file

Other files

File Type Posted
17624 ITB_GTC_SGC_SPECS.pdf PDF
17624 PLANS.pdf PDF
Check Off sheet ITB~17.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work Dayroom Curtain Wall Water Intrusion File No. 262006 Coffee Creek Correctional Facility (CCCF) 24499 SW Grahams Ferry Rd, Wilsonville, OR 97070

Project Overview This Statement of Work covers corrective repairs associated with water intrusion affecting the dayroom area at the Coffee Creek Correctional Facility. The objective is to restore waterproof integrity at exterior window systems, flashing, sealant joints, concrete drainage elements, and any impacted interior finishes.

Scope of Work

• Perform leak investigation and water testing at designated window/wall assemblies.

• Remove failed backer rod and sealant and install new joint sealant per DOC requirements.

• Install new stainless steel flashing, fluid-applied waterproofing, and associated components at sill and jamb locations.

• Remove and reinstall electrical equipment, outlet shrouds, call boxes, and cameras as needed for exterior repairs.

• Remove and replace exterior concrete panels as necessary to re-establish proper drainage.

• Install trench drain system and connect to existing storm drainage infrastructure.

• Replace damaged spandrel glass or insulated metal infill panels at window assemblies.

• Perform interior dayroom repairs including drywall, paint, and finish restoration as needed.

Contractor Responsibilities

• Comply with all DOC security and escort requirements.

• Submit tool lists in advance and follow DOC tool‑control procedures.

• Maintain secure work zones and ensure daily cleanup.

• Provide daily progress updates to DOC Facilities.

• Perform all work per applicable codes, specifications, and manufacturer instructions.

Schedule All work will occur during the DOC daytime work window, typically 6:30 AM – 2:30 PM. Final schedule, sequencing, and phasing will be coordinated with DOC Facilities and Security.

Deliverables

• Confirmed leak remediation through successful water testing.

• Installation of new waterproofing, flashing, sealants, concrete replacements, and drainage systems.

• Completed interior repairs restoring dayroom functionality.

• Documentation of completed work including material specifications and installation notes.

Assumptions & Exclusions

• Work is limited to identified locations contributing to dayroom water intrusion.

• Any unforeseen structural or system damage discovered during demolition requires separate authorization.