This is a Performance Work Statement (PWS) for administration and industrial building cleaning services at U.S. Coast Guard Base New Orleans, located on the NASA Michoud Assembly Facility at 1790 Saturn Boulevard, New Orleans, Louisiana 70129, effective July 2026.
The contractor shall clean all exterior vertical surfaces of two buildings using pressure washing, soft washing, chemical cleaning, or other industry-standard methods. The Administration Building encompasses approximately 60,000 square feet of surface area, and the Industrial Building encompasses approximately 40,000 square feet. The contractor must furnish all labor, tools, materials, transportation, equipment, supervision, and personnel necessary for project completion. Work shall be performed Monday through Friday between 8:00 AM and 4:00 PM, excluding federal holidays, unless otherwise approved by the Contracting Officer. The Service Contract Act applies to this procurement. The contractor is wholly responsible for work site safety and must comply with OSHA regulations (29 CFR 1910 and 1926), state and local safety laws, and all environmental regulations including RCRA compliance. All chemicals and cleaners must be environmentally friendly and preapproved by Base New Orleans Environmental Program prior to use. Hazardous waste must be properly manifested and disposed of off-site, with all storm drains protected or covered to prevent environmental discharge. Site visits require advance coordination with the Contracting Officer's Representative, CWO Mike Ackiss (carlton.m.ackiss@uscg.mil). The contractor must provide required submittals within 14 calendar days of award, including detailed work schedule, report of findings, safety data sheets for all cleaners, and repair quotes. Work must commence within 14 calendar days of submittal approval. The contractor is liable for any damage to government property and must return the site to a state equal to or better than the original condition, with final acceptance contingent on the Contracting Officer's approval of the job site appearance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site Visit Information.docx | DOCX document | |
| Cleaning of Admin Building Solicitation Questions 8-3-26.docx | DOCX document | |
| Cleaning of Admin Building Solicitation Questions.docx | DOCX document | |
| Wage Rates Orleans Parish.pdf | ||
| SERVICE CLAUSES FOR CLEANING OF ADMIN BUILDING.pdf | ||
| SF18 CLEANING OF ADMIN BUILDING.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement
Administration and Industrial Building Cleaning
Located at
U.S. Coast Guard
Base New Orleans on the NASA Michoud Assembly Facility
1790 Saturn Blvd. New Orleans, LA 70129
July 2026
United States Coast Guard Base New Orleans, LA
Facilities Engineering Department New Orleans, LA 70129
CWO Mike Ackiss Base NOLA Facilities Engineering Base New Orleans, LA
PART 1: GENERAL
1. INTENT: The intent of this project is to clean via pressure washing, soft washing, or any other industry standard means the Administration Building and Industrial Building at U.S Coast Guard Base New Orleans as outlined in this Performance Work Statement (PWS).
2. SCOPE OF WORK: Contractor shall furnish all labor, tools, materials, transportation, equipment, supervision, and personnel to clean all vertical, exterior, surfaces of dirt, biological growth, and natural buildup on the Administrative (approx. 60,000 sq. ft. surface area) and Industrial (approx. 40,000 sq. ft.) Buildings at Base New Orleans. No repairs outside of the Performance Work Statement are authorized without permission from the contracting officer or their representative.
3. QUALIFICATIONS: Contractor shall provide personnel who have the qualifications, knowledge and working experience on systems listed under Part 2 performance standards.
4. CONTINUITY OF FACILITIES OPERATION: Schedule work to minimize interference with the facility’s normal operations. Perform all on-site work between the hours of 8:00 AM and 4:00 PM, Monday through Friday (federal holidays excluded), unless otherwise approved by the Contracting Officer or Contracting officer’s representative.
5. GOVERNMENT FURNISHED MATERIALS: None
6. GOVERNMENT FACILITIES AND UTILITIES: Electrical power and water are available within proximity. The Contractor will be permitted to utilize these utilities in performing the work, provided that the existing systems are not overloaded. Telephone services will not be available for use by the contractor. Building restroom facilities are available for use.
7. SAFETY: The Contractor is wholly responsible for work site safety. The Contractor shall implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property, and avoids work interruptions. To accomplish this end, the Contractor shall provide appropriate safety barricades, signs, signal lights, etc. as well as complying with and abiding by all federal safety regulations as published by the Occupational Health and Safety Administration, 29 CFR 1910 (series), 29 CFR 1926 (series), State and Local safety laws, rules, and regulations. Any operation defined as “Hot Work” as per OSHA/NFPA requires a permit to be issued. In the event of Hot Work, the Contractor will notify the COR with dates and times Hot Work will be performed. Contractor is to give at least 48 hours notification. This includes welding, cutting, brazing, grinding or any work that could produce sparks or heat and may initiate a fire.
8. ENVIRONMENTAL COMPLIANCE: Any waste generated because of the project shall either be recycled or be disposed of IAW the Resource Conservation and Recovery Act (RCRA). Any Hazardous Waste shall be manifested off site with Base New Orleans listed as the Generator and signatory. Any hazardous waste shall be analyzed, characterized, stored, and disposed of IAW RCRA and all applicable federal, state (i.e., DOT) and local laws and ordinances. All solid waste/trash shall be removed from site and not disposed of in onsite dumpsters. Waste and recycling areas are reserved for RCF Tenants and shall not be used by Contractors at any time. All work will be performed IAW the BASE New Orleans Spill Prevention Control and Countermeasures Plan. All chemicals required for this project shall be preapproved by the contract POC along with SDS’s. All solid waste shall be removed from the RCF after each working day. All extra chemicals and products shall be removed from the site upon work completion, as the Emergency Planning and Community Right-To- Know Act requires Coast Guard maintains an inventory of all Hazardous Materials located at the site. A laydown area as required and an Erosion and Sediment Control Plan, shall be preapproved by the COR as needed. Nothing shall be discharged to a storm drain at any time during the project. All storm drains within range of a potential discharge shall be covered/sealed during installation and kept covered until the work has been completed and the system has been deemed fully operational and compliant with all applicable CG policies/plans/permits/laws/ordinances. All storm drains and waterways within range of a potential discharge shall be covered/sealed or protected by silt fence. All storm drains and waterways within range of a potential discharge shall be covered/sealed or protected by silt fence. All cleaners and detergents used at this facility must be environmentally friendly and receive approval from Base New Orleans Environmental Program prior to use.
9. SITE VISIT: All site visits should be scheduled with the Contracting Officers, Facilities
Engineer and/or their representative and are highly encouraged. Any personnel coming on site without a TWIC, military, or prior approved ID, will need to provide first and last name to representative at a minimum of (5) five business days prior to arrival, so a security badge can be created to allow access on the base.
• Contracting Officers Representative (COR)
CWO Mike Ackiss Email: carlton.m.ackiss@uscg.mil
10. MATERIALS:
a) The Contractor will furnish all materials, equipment, instruments, tools, safety lines and harnesses, and other items necessary for accomplishment of these services.
b) Materials shall be delivered to the jobsite in their original unopened packages, clearly marked with the manufacturer’s name, brand name, and description of contents. Storage shall be in accordance with manufacturer’s recommendations in a clean, dry, well-ventilated area. Stored materials shall be protected from sunlight and kept away from excessive heat. The contractor shall not store any highly flammable materials in the work area and all chemicals used shall be preapproved by POC. Laydown areas and parking should be on non-vegetated areas when possible.
c) The Contractor is required to comply with local VOC laws and regulations. All applicable Safety Data Sheets shall be available upon request.
11. LOCATIONS: Base New Orleans is located on the NASA Michoud Facility in New Orleans
East. 1790 Saturn Blvd New Orleans LA, 70129
12. LIABILITY OF CONTRACTOR: Any damage to government property caused by the contractor shall be repaired or replaced by the contractor at no cost to the government. The contractor shall not disconnect any service without approval from the Technical Representative.
PART 2 PERFORMANCE STANDARDS
1. PERFORMANCE REQUIREMENTS: The Contractor shall:
1. Clean all exterior vertical surfaces of Administration Building (approx.
60,000 sq ft) using pressure washing, chemical cleaning, or other industry standard practice.
2. Clean all exterior vertical surfaces of Industrial Building (approx. 40,000 sq ft) using pressure washing, chemical cleaning, or other industry standard practice.
2. LABOR LAWS: The Service Contract Act applies to the procurement.
3. SITE RESTORATION & CLEAN UP: The work site shall be cleaned up at the completion of each workday. Upon completion of the job, the Contractor shall clean up the job site, returning it to a state of cleanliness equal to or exceeding that in which it was found. The Contractor shall properly dispose of any trash, extra materials, dirt, debris, or other litter that remains, off-site.
There will be no final acceptance of the contract until the Contracting Officers Representative approves the appearance of the job site.
4. GOVERNMENT FACILITIES AND REGULATIONS: The Contractor, their employees, and any sub-contractors shall become familiar with and obey all Base/ Unit regulations. All personnel employed on the project shall keep within the limits of the work area and shall not enter any other area outside of the work site unless to do so in the performance of their duties.
There shall be No Smoking in any Coast Guard Building. All smoking must be done in the designated smoking area.
5. CONTRACT TIMELINE: The Contractor shall provide all required information and complete this contract within this time schedule, unless approved by the Contracting Officer.
a. Provide all required submittals to the Contracting Officer within 14 calendar days after contract award as applicable.
b. The U.S. Coast Guard will have 7 calendar days to review the submittals and respond to Contractor.
c. Contractor shall provide projected delivery schedule during proposal and provide a firm delivery date within 14 calendar days after the contract has been awarded.
d. The Contractor, upon receiving notification that the U.S. Coast Guard has approved the submittals and having received the Contractors firm delivery date schedule, will have 14 calendar days to begin work on the project.
The Contractor shall notify the Contracting Officer of any long lead time delivery of equipment, so that the Contracting Officer can modify the delivery date of the contract.
1. SUBMITTALS: Once awarded, the following list of submittals required for successful execution of this PWS and sets the specific minimum requirements for this contract. The submittal shall contain sufficient information that can be used to determine compliance of the material with these specifications and referenced specifications. Safety Data Sheets must be provided to COR and receive approval by Base New Orleans Environmental Protection prior to commencement of work.
a. Detailed work schedule
b. Report of findings
c. Data Sheets for all cleaners to be used
d. Quote for further repair as needed.
2. EXECUTION: Installation, workmanship, fabrication, assembly, erection, examination, inspection, and testing shall be in accordance with appropriate sections of 29 CFR 1910, 1926.
a. The Contractor shall schedule all work with the Technical Representative.
The Contractor shall understand the importance to schedule and complete all work in a timely fashion. The Contractor shall minimize the impact for the command and/or mission of the personnel located at each location.
b. The Contractor shall perform all work IAW all Federal, EPA, OSHA, and State of Louisiana laws and regulations.
File details come from the government source that posted it. Updated .