This is a Specification for Dockside Repairs for the USCGC HUDSON (WLIC 801) for Fiscal Year 2026, developed by the U.S. Coast Guard Surface Forces Logistics Center.
Work Item 19 addresses the replacement of pilothouse windows and requires the contractor to replace 13 individual window units across multiple locations in the pilothouse structure. The replacement items include eight fixed windows (ranging from 10"x18"x30" to 24"x30"), two sliding windows (24"x30"), and one forward windshield assembly with wipers containing six panels and three window sections. All windows specified are heat-treated glass with 3/8" thickness, with references to similar Kearfott and Cornell-Carr product types. The contractor must accomplish electrical disconnection and reconnection of wiper assemblies in accordance with applicable SFLC Standard Specifications, prepare disturbed areas per SSPC-SP 3 standards with 3-inch feathered boundaries, conduct inspections in the presence of Coast Guard inspectors for corrosion and deterioration, install new windows, perform boundary integrity testing, execute touch-up preservation coating to match existing surfaces, conduct welding and brazing per specification, and perform operational testing of all window wiper assemblies post-repair. The contractor must submit Cost and Financial Reports (CFR) for inspection results, wiper assembly testing, boundary testing, and final operational testing. No Contractor Inspection Reports (CIR) or Technical Representatives are required for this work item. The specification references multiple Coast Guard drawings and publications governing preservation, electrical work, welding, cable installation, and general contracting requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Synopsis Solicitation.pdf | ||
| WAGE DETERMINATIONS.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC HUDSON (WLIC 801)
SPECIFICATION FOR DOCKSIDE REPAIRS
FY2026
Developed By: Erik C Elasik
(Rev-0, 15 October 2025)
USCGC HUDSON (WLIC-l 60A) DOCKSIDE AVAILABILITY FY2026
S25 007 62500 HSM 0825 801
WORK ITEM 19: Pilothouse Window, Replace
1. SCOPE
1.1 Intent.. This work item desc1ibes the requirements for the Contractor to replace windows, as designated in Table 1.
TABLE 1 - WINDOW REPLACEMENT ITEMS
ITEM LOCATION DESCRIPTION
Pilothouse Fixed Window, Pilothouse (02-102-0-C) BM #338 PN 8, Window, Fixed, Heat Treated, 24"x30", Starboard (2 ea) 3/8" Thick Glass, Similar to Kearfott K-325-F
Pilothouse Fixed Window, Pilothouse (02-102-0-C) BM #338 PN 3, Window, Fixed, Heat Treated, Starboard (1 ea) 10"x18"x30", 3/8" Thick Glass, Triangular Shaped, Similar to Kearfott K-322-C Pilothouse Sliding Pilothouse (02-102-0-C) BM #338 PN 6, Window, Sliding, Heat Treated, Window, Starboard (1 ea) 24"x30", 3/8" Thick Glass, ¾" IPS Drain Connection, Similar to Kearfott K-322-C
Pilothouse Fixed Window, Pilothouse (02-102-0-C) BM #338 PN 8, Window, Fixed, Heat Treated, 24"x30", Po1t (2 ea) 3/8" Thick Glass, Similar to Kearfott K-325-F
Pilothouse Fixed Window, Pilothouse (02-102-0-C) BM #338 PN 5, Window, Fixed, Heat Treated, Po1t (1 ea) 10"x18"x30", 3/8" Thick Glass, Triangular Shaped, Similar to Kearfott K-322-C Pilothouse Sliding Pilothouse (02-102-0-C) BM #338 PN 6, Window, Sliding, Heat Treated, Window, Port (1 ea) 24"x30", 3/8" Thick Glass, ¾" IPS Drain Connection Pilothouse Aft Fixed Pilothouse (02-102-0-C) BM #338 PN 8, Window, Fixed, Heat Treated, 24"x30", Windows (5 ea) 3/8" Thick Glass, Similar to Kearfott K-325-F Pilothouse F01ward Pilothouse (02-102-0-C) BM #338 PN 1, Windshield w/ wipers, 6 Panel Window
Windshield - 3 Window Sections with Upper and Lower Panels, Similar to Cornell-Can-Type A CC-1026
USCGC HUDSON (WLIC-160A) DOCKSIDE AVAILABILITY FY2026
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 160-WLIC-3301-1, Rev F, Joiner Plan, Main, Upper Deck & Pilothouse Coast Guard Drawing 160-WLIC-0103-002, Rev A, Booklet of General Plans Coast Guard Drawing 160-WLIC-1107-002, Rev D, Pilot House Coast Guard Drawing 160-WLIC-1202-002, Rev A, Type K-322-C Window & Type K-325-F
Fixed Windows Coast Guard Drawing 160-WLIC-1202-003, Rev A, Six Panel Windshield Type K-1000
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard Electrical Cable Test Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation
OTHER REFERENCES
Coast Guard Bill of Material 160-WLIC-338, Rev -, BM No. 338 Cabin & Pilothouse Windows
& Main Deckhouse
3. REQUIREMENTS
3.1 General. The intent of this work item is to replace windows, as indicated on Table 1.
3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):
None.
3.1.2 Tech Rep.
None.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
• Insulation
• Electrical Cables
• Window Wipers
3.2 Window Replacement. The Contractor must accomplish the following tasks to replace the windows as designated in Table 1. See Coast Guard Drawing 160-WLIC-1107-002 for guidance and details.
3.2.1 Electrical Disconnections. The Contractor must disconnect and coil back electrical cables from wiper assemblies of windows designated in Table 1, in accordance with SFLC Std Spec 3042. Record wiring information for later re-connection.
3.2.2 Window Removal. Remove and discard window pannels. Remove and scrap all seals and fasteners.
3.2.3 Prepare all disturbed areas around the window opening in accordance with SSPC-SP 3. Feather the surrounding surfaces to obtain a 3-inch wide smoothly tapered boundary from the existing paint to the prepared surface.
3.2.4 In the presence of the Coast Guard Inspector, inspect the framing and plating around each opening for corrosion and deterioration. Submit a CFR if additional repairs are required.
3.2.5 Window installation. Install new windows in place of the one removed.
3.2.6 The Contractor must re-connect previously removed cables to window wiper assemblies.
Operationally test each affected window wiper assembly in accordance with SFLC Std Spec 3041.
Submit a CFR.
3.3 Boundary test, generic. The Contractor must verify the integrity of all boundaries affected by this work item using one of the methods described in SFLC Std Spec 0740, Appendix C. Submit a CFR.
3.4 Touch-up preservation. The Contractor must prepare and coat all new and disturbed surfaces to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, paragraph 3.1.13 (Touch-ups and minor coating repairs.)
3.5 Gas freeing. When entering a tank, compartment, confined space, or conducting hot work, refer to and comply with SFLC Std Spec 0000, General Requirements.
3.6 Welding and brazing. Perform all welding, brazing, and non-destructive testing (NDT) in accordance with SFLC Std Spec 0740, Welding and Allied Processes.
3.7 Electrical work. The Contractor must accomplish all electrical work in accordance with SFLC Std Spec 3042, and test cables in accordance with SFLC Std Spec 3041. Utilize the existing wire ways for new cable runs as much as possible.
3.8 Operational test, post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.
4. NOTES
This section is not applicable to this work item.